    Design and Construction of the Thames Water Lee Tunnel Shafts, London

    By Sivilay Sayavong, David Puller, Julian Gatward, David Hard, Martin Stanley

    "AbstractThe Thames Water Tideway Tunnels programme involves the upgrade of London’s combined sewer and storm water system. The first section is the Lee Tunnel between the Beckton Sewage Treatment Wor

    Jan 1, 2014

  • DFI
    Wave Equation Analysis And Dynamic Monitoring - A Presentation At The Deep Foundations Institute?McGill University Symposium Montreal, September 1983

    By Bengt Fellenius

    The conventional wave equation analysis without control of the representativeness of the parameters to the actual conditions does not provide accurate results. However, the representatives can be vast

    Jan 1, 1984

  • DFI
    Production And Testing Of 600 Reinforced-Concrete Piles For The Central Bank Of Iraq

    By H. Meseck

    The new building of the Central Bank of Iraq in Baghdad was footed in difficult underground conditions on more than 600 reinforced concrete driven piles, with cross-sectional diameters of 45 x 45 cm a

    Jan 1, 1989

  • DFI
    Quality Control Of Augered Cast-In-Place And Displacement Piles ? Introduction

    By Rudolph P. Frizzi

    Quality control is essential for augered cast-in-place (ACIP) piles (also known as continuous flight auger (CFA) piles outside the United States) and augered displacement (AD) piles since the pile is

    Jan 1, 2002

  • DFI
    Augered Cast-In-Place Piles: Regional Project Profiles - Community Osteopathic Hospital Harrisburg, Pa

    GENERAL CONTRACTOR: ALEXANDER CONSTRUCTORS, INC. STRUCTURAL ENGINEER: CAGLEY & ASSOCIATES, INC. GEOTECHNICAL ENGINEER: F.T. KITLINSKI & ASSOCIATES, INC. PILE FOUNDATION CONTRACTOR: L.G. BA

    Jan 1, 2001

  • DFI
    Underpinning A Crane Foundation

    By Donald R. McMahon

    This paper presents a unique case history that documents the use of a braced secant pile wall to underpin a heavily loaded footing inside of a manufacturing plant. Construction of a pit for a new man

    Jan 1, 2006

  • DFI
    Disconnected Piled Raft Foundations Performance (DCPRF) With Cushion

    By Saeed Salehi Malekshah

    In hybrid foundation system or piled raft foundation (PRF), the raft has adequate bearing capacity and piles are usually required to ensure overall stability of foundation and also to act as settlemen

    Jan 1, 2011

  • DFI
    Recent Developments In Continuous Flight Auger Piling

    By P. H. Derbyshire

    The use of continuous flight auger piles has increased significantly in the U.K. to such an extent that it is now the most widely used method of constructing small diameter bored piles. This paper des

    Jan 1, 1989

  • DFI
    Prediction And Calculation Of Construction Vibrations - Summary:

    By Mark R. Svinkin

    Construction-induced vibrations may be detrimental to adjacent structures and sensitive electronics operating nearby. Construction vibration sources have a wide range of energy and velocity, as a func

    Jan 1, 1999

  • DFI
    Improvement Of The Cost-Effectiveness Of H-Bearing Piles By Using High-Strength Histar Steels. - Summary

    By Lucien P. Weber

    Over the last few years, increased customer demands as well as strong competition from substitute materials have accelerated the development of advanced technologies to improve both the performance an

    Jan 1, 1997

  • DFI
    Resonant Pile Driving - Part I - The Promise & The Reality - Part II - Soldier Pile Installation - Light Rail Transit - Buffalo, New York - 1. Historic Background.

    By D. R. Dance

    The Resonant, or as it has more commonly come to be known the 'Sonic' Pile Driver, dates back to the early 1960's, when prototypes were produced by Charlie Guild, of Providence, Rhode I

    Jan 1, 1987

  • DFI
    Pile Top Hydraulic Hammer Drive Down The Hole Chiselling Round Steel Piling System - Summary

    By J. Nakayama

    For installation of round steel piles or cast-in-place pile construction through boulder contained ground or rocky formation, usual system does not function properly or impossible to work. This paper

    Jan 1, 1999

  • DFI
    Real-Scale Tests on Soil Mix Elements

    By Nicolas Denies, Gust Van Lysebetten, Bart Lameire, Jan Maertens, André Vervoort, Noël Huybrechts, Flor De Cock

    "Abstract Originally developed for ground improvement works, the deep mixing method (DMM) has increasingly been applied in recent years for the realization of soil and water retaining structures and a

    Jan 1, 2014

  • DFI
    Augered Cast-In-Place (ACIP) And Drilled Displacement (DD) Pile Quality Control ? Introduction

    By Rudolph P. Frizzi

    Quality control is essential for augered cast-in-place (ACIP) piles (also known as continuous flight auger (CFA) piles outside the United States) and drilled displacement (DD) piles since the pile is

    Jan 1, 2004

  • DFI
    Slurry Wall Design For Hong Kong Station

    By Stephen T. Young

    The construction of Phase 2 of Hong Kong Station, its retail podium and International Finance Centre Two, the tallest building in Hong Kong, will be completed in the middle of 2003. This paper describ

    Jan 1, 2003

  • DFI
    New Technology of Force Monitoring of Post-Tensioning Ground Anchors

    By Shahid Islam, Lucian Bogdan

    There is a rapid expansion of world’s infrastructure and simultaneously existing infrastructure is aging. The maintenance of infrastructures has been of particular concern to the engineering community

    Jan 1, 2018

  • DFI
    Dynamic And Static Loading Tests Of Piles For Bridges In Surinam - Introduction

    By W. J. van Niekerk

    Ballast Nedam is in Surinam constructing two bridges that will improve communications in the coastal region. The bridges will cross the Coppenam and Surinam rivers and will be founded on open-ended st

    Jan 1, 2000

  • DFI
    Damage To Initially Bent Piles ? Synopsis

    By B. B. Broms

    A method for calculating the bending moment induced in misaligned or bent piles is described, The maximum bending moment varies with the angular rotation between the pile segments, the coefficient of

    Jan 1, 2010

  • DFI
    Deep Foundation Construction Using "Top/Down" Building Techniques In The United States

    By David C. Lager

    While not a new construction technique "top/down" construction is seeing increased use in high rise building construction. Using diaphragm wall, drilled shaft and mining construction techniques, top/d

    Jan 1, 1987

  • DFI
    Quality Assurance In Jet Grouting For A Deep Seated Slab In Amsterdam

    By Thomas Passlick

    By means of further developed machines and techniques and with growing experiences in jet grouting, the challenge of this building method becomes more and more complex. To keep the concerning risks as