Construction Of The Main Tower Pier Caissons For The Greenville Bridge In MississippiBy F. Keith Jacobson
To be involved in the construction of a deep dredged caisson for a major bridge pier is one of the most rewarding and professionally challenging experiences one can have in the bridge construction bus
May 11, 2007
-
Soil Fatigue Analysis for Pile Driving Simulations Using an Impact HammerBy Peter Middendorp, David J. Tara, Gerald E. Verbeek, Jan Fischer
"For pile driving simulation the model used must be accurate for the entire process, i.e. from the start of pile driving until the pile has reached its target depth. Of the various model components (h
Jan 1, 2017
-
Pile Lateral Behaviour under Full Scale Lateral Load Tests in Thick Compacted Marine Carbonate Sand Fill of an Artifical IslandBy Challa Venkata Rami Reddy, Anindya Roy, G. R. Konni
This paper presents the results of pile lateral capacities obtained from both conventional design and fullscale pile lateral load tests. Conventional design using P-Y curve analysis is very commonly b
Sep 8, 2021
-
Deep Drilled Shafts For The Pearl Harbor Memorial Bridge New Haven, ConnecticutBy Theodore von Rosenvinge
Large diameter (2.4 meter) drilled shaft foundations were installed to depths of over 62 meters through soil into Arkose bedrock for Connecticut?s Pearl Harbor Memorial Bridge (I-95 over New Haven Har
Jan 1, 2011
-
Elliptical Jet Grouting for the Sela-22 Project in New Orleans, LA: An Innovative SolutionBy Filippo Maria Leoni, Gianluca Pianezze
"As part of the Southeast Louisiana (SELA) drainage program, designed to reduce flood damages in the City of New Orleans and surrounding parishes, the SELA-22 project entailed the construction of a co
Jan 1, 2017
-
Ground Improvement by Dry Concrete ColumnsBy Tatiana Tronda
"The territory of Belarus is characterized by nonhomogeneous ground conditions. In some cases soft ground layers can reach tens of meters in depth. Application of piles and other conventional foundati
Jan 1, 2016
-
Case History: Comparison of CSL Results to Physical ObservationsBy David S. Graham, Paul J. Axtell
Crosshole Sonic Logging (CSL) non-destructive integrity testing identified anomalous readings near the base of a 6.5-foot diameter drilled shaft rock socket. The anomaly was confirmed to be a defect b
Jan 1, 2019
-
Deep Foundations - Experience & Problems Encountered-Case Study For Second Thane Creek Bridge At Vashi, New Bombay. - SynopsisBy S. R. Nandargikar
Construction of open foundations for the Second Thane Creek Bridge was indeed a challenging task. Some major problems were encountered during the construction of foundations for pier No. P22 (S/N), P.
Jan 1, 1996
-
Micropile Performance Variability: A Fundamental Case StudyBy Walter E. Vanderpool
Type 1B micropiles (Bruce and Juran, 1997) can be installed rapidly and efficiently. During an 85-day period, 536 micropiles were installed to depths of 61 meters within a site 41 meters by 43 meters.
Jan 1, 2002
-
Drilled Displacement Piles - An Innovative Alternative to Typical Steel Driven PilesBy Patrick Granitzki, Alicia Plinio, Janitha Batagoda, Peter Howell
The City of Newark is making a comeback with new mixed-use multi-storied Residential Development projects. The majority of developers tend to use driven H-pile deep foundation systems to support their
Sep 8, 2021
-
Long-Term Performance Of Wind Turbine Foundations Through Numerical ModelingBy Spencer Ness, Yazen Khasawneh, William Tjaden, Mohammad Nassim
The evaluation of long-term performance of the wind turbine structures is essential in lowering the Levelized Cost of Electricity (LCOE) from wind sources. The required maintenance of the wind turbine
Oct 1, 2022
-
4 Equipment Installation: Recent Developments - Equipment Installation - Recent Developments: General Report On 'Deep Foundation Installation Monitoring' - 1. IntroductionBy B. De Paoli
At Pietrafitta, between Assisi and Perugia, ENEL (Italian National Electricity Authority) has for some time been managing a power-station operated with lignite, mined from an open mine on the way to e
Jan 1, 1994
-
Mooring Bridge Caissons During Construction Using Jetted-In Driven Plate AnchorsBy Osama A. Safaqah
Driven plate anchors can be used to hold in place large bridge caissons during floating construction. Their small size and simple method of installation make them a very cost effective alternative to
Jan 1, 2013
-
Performance Of Cast-In-Place Piles Installed With A Fixed Mast Drilling Platform In Claystone ? Glenrock WYBy Brent Wilkins
The project team was tasked with the design and installation of a deep foundation system to support an expansion to a power generating station in Glenrock WY. Cast-in-place piles installed by a fixed
Jan 1, 2009
-
Anchored Double-Tier Retaining Walls on Sloping EmbankmentBy Chu E. Ho, Paul Napoli
A new waterfront park was developed on Long Island in close proximity to the East River and Newtown Creek. The existing ground consisted of fill over soft organic clay, medium dense silty sand, glacia
Jan 1, 2019
-
Response of Pile and Pile Groups against Excavation Induced Ground MovementBy K Ilamparuthi, R. K. Madhumathi
"This paper presents the results of 1g model tests conducted on model piles both single and two pile groups embedded in sand by physically inducing lateral soil movement. From the test results it was
Jan 1, 2015
-
Laboratory Mixing and Testing for Controlled Waste Disposal SiteBy Tomohiro Yamasaki
"At the pre-construction foundations of the controlled waste disposal site built at the Port of Kinuura, the clayey soil account for the most, and with lesser amounts of sand compaction piles and sand
Jan 1, 2015
-
Innovative Micropile Retrofi t of an Existing StructureBy Kenneth R. Chadwick, Thomas J. Tuozzolo, Terence P. Holman
"Micropiles are often installed to retrofit existing foundations that experience distortion and to underpin structures prior to future construction. The Dublin Road Pump Station project is an example
Jan 1, 2008
-
High Capacity Hollow Core Bar PilesBy Lawrence F. Johnsen, Felix Ferrer, Dino Tomasetti, Cassandra A. Wetzel
"A 17 story building was constructed at the Brooklyn Navy Yard on a site with a long history of development. Most recently the site supported a dewatering well and craneway to service two adjacent dry
Jan 1, 2017
-
Session 20 "Grouting for Water Retaining Embankments"By Timothy Flaherty
We observed the boiling in the water very close to the water adjacent to where we were drilling. That only happened at the very beginning before it was switched to water flushing. Yes, it was performe
Feb 10, 2003