Rock Removal Utilizing Ice Bridges in the Mackenzie River Northwest Territories, for Pipeline Trenches to Man-Made Islands a Deepening Shipping ChannelsBy William A. Travnik
For more than 60 years, ESSO RESOURCES CANADA LIMITED has been producing and refining oil at a small refinery in Norman Wells, Northwest Territories, and supplying diesel fuel and other oil products
Jan 1, 1986
-
Investigation of Ground Vibration Induced by Blasting at Hisarcik Boron Open Pit Mine in TurkeyBy Gungor Tuncer, Ali Kahriman
This paper presents the results of ground vibration measurements carried out in Hisarcik Boron open pit mine located on the west side of the central Anatolia near Kütahya province in Turkey. Within th
Jan 1, 2006
-
Control Blasting at Sherman MineBy Peter N. Calder, John N. Tuomi
The development of a successful control blasting program for an open pit iron mine in hard jointed rock is described. The objectives and mechanics of control blasting are discussed. Design and impleme
Jan 1, 1980
-
Overburden Blasting Vibrations: Analysis, Prediction, and ControlBy Otto E. Jr Crenwelge, Timothy A. Peterson
We have developed a site-specific method for analysis, prediction, and control of ground vibrations induced by overburden blasting operations in surface coal mines. Field tests conducted at R&F Coal C
Jan 1, 1986
-
Azimuthal Variation of Ratiation of Seismic Energy from Cast BlastsBy Robert Martin, Brian W. Stump
As part of a series of seismic experiments designed to improve the understanding of the impact of mining blasts on verifying a Comprehensive Test Ban Treaty, a sixteen station network of three-compone
Jan 1, 1997
-
Modernizing Operations: Leveraging GIS in Drilling, Blasting and Quarry ApplicationsBy Dr. Anurag Agrawal, Steve Franklin, Clint Zimmerman, Elijah Williams
In a time when data has become a highly valued commodity within many mining and quarry operations, managing large amounts of current and historical information can be difficult. If not managed properl
Jan 21, 2025
-
Front-End Loader Proof of Concept to assess the performance of an autonomous fragmentation analysis system.By Tyler Rockley, Carla Reyes
Autonomous fragmentation measurement systems designed for shovels have been in operation for nearly two decades, however fragmentation systems capable of performing in the dynamic conditions of the fr
Jan 21, 2025
-
Blast Vibration Monitoring, Prediction and Control at Old Cliffe Hill QuarryBy Rob Farnfield, Mark Pegden
Old Cliffe Hill quarry produces between 4 and 5 million tonnes of crushed granite per year and is located in the county of Leicestershire in the East Midlands region of England. Blasting is carried ou
Jan 1, 2010
-
The Use of Explosives to Backfill and Reclaim Former Quarry SitesBy Conny Postupack, Jim Petrunyak, John Hope
The authors discuss the concepts, engineering considerations, and cost relationships involved in the use of drilling and blasting to accomplish backfilling and reclamation with minimum use of mechanic
Jan 1, 1989
-
Drilling and Blasting in TarsandBy Bill Romanchuk, Real Doucet
Suncor Inc. has been operating the first commercial tarsand open pit mine in the world since 1967. Drilling and blasting operations are required to facilitate overburden removal and tarsand mining by
Jan 1, 1985
-
Controlled Sequential BlastingBy E Emery Jr Gray
A need for more delay periods other than those normally manufactured throughout the explosives industry rarely occurs. This paper will discuss one such incident from an analytical view through practic
Jan 1, 1976
-
Cost Effective Loading of Large Diameter Pre-Split HolesBy LaRay Collyer
San Juan Mine began pre-splitting the highwall prior to cast blasting in August 1986. The first pre-split shot used six inch PVC (polyvinylcloride) pipe inside a 10 5/8 inch hole, drilled at a 74 degr
Jan 1, 1990
-
A New Generation of Drilling at the Minntac MineBy Don Thompson
The Minntac Mine drills and blasts approximately 75 million long tons of taconite per year. This requires drilling one million feet of 1 6-inch diameter holes. We are in the process of replacing our o
Jan 1, 1998
-
Reduction of Air Blast and FlyrockBy Don Rapp, Rufus Flinchum
Air blast and flyrock are two of the most critical concerns facing the blaster of today. This paper will provide the blaster with proven procedures for recognizing open face and bench surface problems
Jan 1, 1993
-
Blast Designs to Achieve a Plant Tonnage Goal in a New MineBy Cristian Rodriquez, Fernando Fernandez, Rodrigo Fuentealba, Tom BoBo, Maria Rocha, John Kemeny
This paper describes a case study that was conducted at a new mine in South America. This mine has significant geologic variations that will result in different distributions of hard and soft ore bein
Jan 1, 2015
-
Damage Criteria for Nearby Structures During Underground Explosions and EarthquakesBy Krishna Nand
For assessing the safety of structures during underground explosions, ground particle velocity gives the best damage criteria, and 100 mm/see of ground particle velocity has been internationally accep
Jan 1, 1988
-
Strain and Peak Particle Velocity as Vibration Criteria: Some ThoughtsBy Syed Haq, Kyle Optt, David Campo, Doug Anderson
Limitations on allowable levels of vibration from construction activities generally consider either annoyance or damage. While activities such as drilling and roller compaction primarily create annoya
Jan 1, 2004
-
Borehole Pressures in an Air Decked SituationBy W. Fourney
In the late 70’s and early 80’s in conjunction with other oil and gas well stimulation studies, personnel from the Dynamic Effects Lab performed model testing to demonstrate the effectiveness of utili
Jan 1, 2006
-
Improved Blast Control Through the Use of Programmable Delay DetonatorsBy C Deacon, M Jones, P Duniam
Electronic blast timing has been in use around the world since the mid-eighties, and, whilst it has yet to be used commercially by large operations on an ongoing basis, significant inroads have been m
Jan 1, 1997
-
Measuring Blast Induced Damage by Applying the MASW Geophysical MethodBy Charles Zdazinsky
Many blasting applications in the mining industry demand that the hard rock being blasted remains structurally competent. For example, pre-splitting is a common technique to reduce fracturing, and ope
Jan 1, 2011