    Redwood Tower; A Landmark In Deep Foundation Construction ? Synopsis

    By A. Partos

    It was decided to build a fourteen-storied office building over a six-storied garage and a four-storied office building. The high vertical and horizontal loads required foundations on rock approximate

    Jan 1, 2010

  • DFI
    A Realistic Approach Toward Stray Current Induced Corrosion Affecting Steel Sheet Piling

    By Anne Fagot

    Because of the risk of corrosion caused by stray currents, steel foundations and steel sheet piling are generally prohibited in the vicinity of railway structures. Steel solutions are only accepted if

    Jan 1, 2008

  • DFI
    Settlement Control Of A Road Embankment Using Vertical Drains

    By Wei Tu

    A grade separation was required to allow uninterrupted traffic crossing for a busy rail spur and a county road. The grade separation was achieved by creating a 30-foot (9-meter) high embankment that

    Jan 1, 2009

  • DFI
    Soil Improvement in Marina Coastal Expressway Project (C485) with Cement Deep Mixing (CDM) Method

    By Yoshinori Kurumada, Tatsuo Nagatsu, Keiji Uchida

    "Cement deep mixing method has been utilized in the process of construction of an underwater tunnel in Singapore. The soil was improved by this method to prevent undesirable heaving of the soil below

    Jan 1, 2015

  • DFI
    Effects Of Permanent And Temporary Loads On Allowable Bearing Capacity Of Piles Subjected To Nagative Skin Friction

    By Mohammad T. Izadi

    Piles are, often, used for transferring load from the super structure through soft consolidating strata onto relatively stiff uncompressible soils. Downward movement of the soft soil strata develops

    Jan 1, 2001

  • DFI
    Design Of Well Cap, Pier And Well Steiming At The Junction Using Strut-And-Tie Model - Synopsis

    Pier, well cap and steining junction is a complicated 3-d re-ion. The prevalent design procedure for the pier, well cap and steining in isolated manner is not rational. In absence of an integrated app

    Jan 1, 1996

  • DFI
    Experiences From A Large Scale Driven Precast Piling Project In India

    By Rajesh A. Vaidya

    A large scale piling work is undertaken in India for an important fast track industrial project. Thousands of solid square precast concrete piles are driven to depths of around 50m. Soils encountere

    Jan 1, 2007

  • DFI
    A Comparative Study on Behavior of Bucket Pile in Sand According to Installation Methods

    By Jinung Do, Sung-Ryul Kim, Juhyung Lee

    "Model tests have been performed to investigate the vertical, horizontal and cone tip resistances of bucket pile embedded in sand by different installation methods; suction force by pump and jacking f

    Jan 1, 2016

  • DFI
    Practice to Reduce Ground Displacement in Deep Mixing Work

    By Kozo Takeda, Arashi Shimano

    "Dry Jet Mixing (DJM) technique is widely known as soil mitigation technique with small ground displacement during installation comparing with other techniques. Some projects involving sensitive struc

    Jan 1, 2015

  • DFI
    Design Of Drilled Shaft Supported Mat Moscow Towers

    By Issa S. Oweis

    Two Towers are currently under construction in Central Moscow in the Russian Federation. Building A is a 96 story tower and Building B is a 65 story tower. The columns in both structures bear on a t

    Jan 1, 2007

  • DFI
    Effect of Sand Density on Load Sharing Mechanism of Piled Raft Foundation

    By Rouzbeh Vakili, Adel M. Hanna

    "The application of piled raft foundations has significantly increased during the last few years. In this system, the raft and the pile group collectively transfer the applied building load to the und

    Jan 1, 2017

  • DFI
    Axial Pile Response Evaluation By Geophysical Piezocone Tests

    By Paul W. Mayne

    The axial load-displacement-capacity and load-transfer response of deep foundations can be conveniently assessed by geophysical piezocone tests that provide four independent readings with depth, inclu

    Jan 1, 2002

  • DFI
    Laterally Loaded Model Piles In Jointed Soft Rock Masses

    By B. Francis

    Literature provides only limited information regarding the behaviour of laterally loaded piles socketed into weak rock masses. A laboratory program, comprising a number of tests of scaled models of th

    Jan 1, 2004

  • DFI
    Installation Of Augered Cast-In-Place Piles - Equipment (66bbaadf-14f6-4860-86d8-a6149d09411b)

    ? Hollow Stem Auger ? Drill Bits ? Leads/Torque Arm ? Hydraulic Gearbox ? Hydraulic Power Unit ? Grout Pump ? Crawler Crane

    Jan 1, 1998

  • DFI
    Case Study: Natomas Levee Improvement Program Cutoff Walls

    By Matthew D. Marks

    "The Sacramento Area Flood Control Agency initiated the Natomas Levee Improvement Program in 2006 which would bring the entire 42 mile Natomas Basin perimeter levee system into compliance with applica

    Jan 1, 2017

  • DFI
    Development Of Vertical-Horizontal Yield Envelopes Of Pile Group Supported Bridges Subjected To Scour

    By Aditi Sharma, Sumanta Haldar

    Scouring of soil is the major concern forthe various hydraulic structures built in the flowing rivers since scouring impacts the bearing capacity of foundations. Hence, consideration of scouring in th

    Sep 1, 2022

  • DFI
    Optimization Of Pile Length Using Decision Analysis With Information From Load Tests During Construction

    By Jiun-Yih Chen

    Pile load tests are regularly used to verify pile capacities. Sometimes, they are used to optimize pile designs. This paper presents a case study based on a real project, in which the information ob

    Jan 1, 2009

  • DFI
    Helical Piles With Grouted Shafts - A Case History

    By Shawn Downey

    A helical pile with in-situ grouted shaft was used to underpin the existing slab of a large retail store in the Edmonton, Alberta Canada area. The existing structural slab did not have the capacity to

    Jan 1, 2003

  • DFI
    Pile Construction And Related Problems ? Synopsis

    By K. Fujita

    In order to deal properly with the fundamental aspects of pile construction, the following problems and their solutions are introduced: For driven piles - stresses, damage, movements of surroundings,

    Jan 1, 2010

  • DFI
    Construction Of Large Scale Diaphragm Walling And Related Problems - Part One - The Building Of Diaphragm Walling - I. The General Situation Of The Project

    By D. X. Xu

    A pump station was constructed at the food of a steep mountain, very close to a riverside. To protect the pump station from being washed out, and to guarantee the stability of the steep hillside behin