Jet Grouting Underpinning Of A Building In The US
By Gustavo E. Armijo
This job was done in Morristown, NJ, with mono fluid system jet grouting for the construction of a new bank building. After the demolition of the existing two story structures, an excavation in loose
Jan 1, 2002
-
Low Strain Integrity Testing Of Deep Foundations ? Introduction
By Jay A. Berger
Nondestructive testing of deep foundations for integrity problems made great strides in the late 1980's. Inexpensive portable computers have allowed the immediate and rapid processing of field me
Jan 1, 1990
-
Theoretical Examination of Initially Bent Piles
By Janne P. Isohaka, Anssi M. Laaksonen
"Abstract In Scandinavia the use of steel pipe piles in bridge foundations started in the mid-1980s and has increased steadily since. As the piles driven in soft soils are slender, they can fail by bu
Jan 1, 2014
-
Design And Construction Of The Rion Antirion Brdoge Foundations
By Alain Pecker
The choice of a design concept for a bridge foundation is guided by various factors; several of these factors are indeed of technical origin, like the environmental conditions in a broad sense, but ot
Jan 1, 2005
-
Pile Load Test Results Using The New Statnamic Method
By Matthew Janes
Quality control procedures are increasingly important with today's higher capacity foundations and complex loading conditions. The need for a mobile, repeatable, nondestructive and economical loa
Jan 1, 1990
-
Dynamic Stability Of An Axially Loaded Pile
By S. S. Gajin
The paper deals with parametric vibrations of an axially loaded pile. The dynamic model is derived by means of Hamilton's principle and reduced to a partial differential equation with variable c
Jan 1, 1989
-
Issues In The Performance-Based Seismic Evaluation Of Sheet Pile Quay Walls
By Dimitris Pachakis
In this paper, the authors give a brief overview of the current practice guidelines and tools for the seismic design of sheet pile quay walls, emphasizing how the design guidelines are lacking when th
Jan 1, 2011
-
Conventional And Box-Shaped Piled Rafts
By Heinz Brandl
Box-shaped pile and diaphragm wall foundations have proved suitable for transferring heavy loads of bridges, power plants, tanks, towers or other buildings in a concentrated form into the ground. The
Jan 1, 2002
-
Uplift Micropile Load Transfer In Unsaturated Missoula Flood Deposits
By John N. Cunningham
Despite the wide use of micropiles for rehabilitating and retrofitting existing structures, little is known regarding the load-transfer distribution of grouted micropiles in various soil deposits. Th
Jan 1, 2011
-
Plastoelastic Analysis Of Bearing Capacity For Soil Anchor
By Hui Yongning
This paper presents a simulating test of constitutive relation of soil anchor in laboratory and puts forward a new plastoelastic mechanical model, on which a new calculating formula of elastic and pla
Jan 1, 1991
-
St Joseph Hospital Of Bellingham, Washington Addition Supported On Helical Pulldown Micropiles
By J. L. Goen
The Saint Joseph Hospital of Bellingham is located on a site underlain by glacial outwash. The construction of a five-story tower addition above an existing two-story wing was supported by five large
Jan 1, 2004
-
A Need To Reevaluate Attitudes In Engineering And Construction
By d&apos, E. Appolonia
A construction project is successful when all parties contributing to it are winners. It is not a success when there are winners and losers. Contractors, engineers, suppliers and equipment developers
Jan 1, 1985
-
Practical Experience With Nondestructive Testing Of Augered Cast-In-Place Piles
By Bernard H. Hertlein
All methods of deep foundation construction present challenges to the contractor and engineer that vary according to the method employed, and the geotechnical conditions in which it is being used. Aug
Jan 1, 1997
-
Differing Site Conditions
By James J. Tansey
A Deep Foundations Institute meeting with the University of Michigan at Ann Arbor in March of 1984 featured legal rights under Differing Site Conditions. A workshop conducted by the authors and Gerard
Jan 1, 1985
-
Thornton Road, Listerhills, Bradford
By B. C. Slocombe
A large derelict inner city site was regenerated for use as a distribution warehouse. Difficult topography and soils conditions required the adoption of a combination of specialist geotechnical proces
Jan 1, 1989
-
Effect Of Vertical Heterogeneity In Soil Strength On Pile Bearing Capacity Prediction From CPT Data
By Amaneh E. Kenarsari
Among the different sources of uncertainty in pile bearing capacity prediction including inherent heterogeneity, measurement and model uncertainties, the inherent heterogeneity of soil properties is o
Jan 1, 2011
-
Pile Top Hydraulic Hammer Drive Down The Hole Chiselling Round Steel Piling System - Summary
By J. Nakayama
For installation of round steel piles or cast-in-place pile construction through boulder contained ground or rocky formation, usual system does not function properly or impossible to work. This paper
Jan 1, 1999
-
Simulation of Brittle Failure of Cement Treated Soil Using Smoothed Particle Hydrodynamics
By Tomohide Takeyama, Yuki Yoshida, Masaki Kitazume
"Abstract A series of centrifuge model tests was conducted to investigate the failure pattern and stability of cement treated clay ground having an unsupported vertical slope. The model ground was sub
Jan 1, 2014
-
To Protect Pit-Wall By Means Of Chemical Grouting In Excavation Work Of Deep Foundation Pit
By Xiong Houjin
In the excavation works of some deep foundation pits within the boundaries of Guangdong Province of China, though some measures, such as steel sheet piles, diaphragm walls, etc. were taken to protect
Jan 1, 1991
-
Multiple Foundation Systems For The Porter Street Outfall Relocation For The North Approach - Summary
By William D. Spielvogel
The Massachusetts Highway Department awarded the Porter Street Outfall Project to the J.M. Cashman Company in November 1991. Timely completion of the Project in one and one half years is critical to t
Jan 1, 1994