Innovative Deep Foundation Support Using Ductile Iron PilesBy Thomas Billups, Brendan FitzPatrick, Doug LeDo, David Carchedi
"Working in urban environments presents unique logistical challenges beyond those typically associated with traditional geotechnical analysis and design. These challenges often include working on site
Jan 1, 2016
-
Three Mass Stabilization Phases in the West Harbor of Helsinki, Finland – Geotechnical and Environmental Properties of Mass Stabilized Dredged Sediments as Construction MaterialBy Leena Korkiala-Tanttu, Noora Lindroos, Juha Forsman
"Construction works at the Helsinki city sea shoreline requires dredging and handling of contaminated sediments. Most of these soft dredged sediments are regarded as too poor quality material for eart
Jan 1, 2015
-
Grouting of an Artesian Zone in Advance of Powerhouse Excavation for the Red Rock Hydroelectric ProjectBy Dewey W. Geary, Rachael V. Bisnett, R. Michael Bivens, Thomas G. Andrews
"The powerhouse for the Red Rock Hydroelectric Project is being constructed at the toe of the existing U.S. Army Corps of Engineers’ Red Rock Dam immediately adjacent to the existing stilling basin re
Jan 1, 2016
-
Marine Prefabricated Vertical Drains for the Craney Island Eastward Expansion (c2c7d75f-a035-4e5c-9df5-e768ce1a9e85)By Mohamed Mekkawy, William W. Wheaton, Ira Brotman
"The Virginia Port Authority and the U.S. Army Corps of Engineers are partnering to construct the Craney Island Eastward Expansion (CIEE) to meet the dual purpose of extending the life of Craney Islan
Jan 1, 2017
-
Marine Prefabricated Vertical Drains For The Craney Island Eastward ExpansionBy Ira Brotman
The Virginia Port Authority and the U.S. Army Corps of Engineers are partnering to construct the Craney Island Eastward Expansion (CIEE) to meet the dual purpose of extending the life of Craney Island
-
Behavior Of Piled Raft Foundation Systems Under A Combined Set Of LoadingsBy Renato P. Cunha
The paper explores a parametric analysis of a four-pile group in contact (hence piled raft) and without contact (hence standard pile group) with the superficial soil layer, under a combined set of loa
Jan 1, 2006
-
Sustainability: A Role for Blended Cements and Industrial Byproducts in Soil Mixing, Grouting, and Slurry WallsBy Charles M. Wilk, Lori Tiefenthaler
"Information presented in this paper can be used to support deep soil mixing, subsurface grouting and slurry wall technology as sustainable construction technologies. Ordinary Portland Cement (OPC) is
Jan 1, 2017
-
Pile Driving Between the Amazonas and Xingu Rivers in the Tucuruí-Manaus Transmission Line – Lessons Learned and Solutions Found for a Challenging ProjectBy José Carlos do Amaral, Marcelo Groszownik, Jorge Beim
"Initiated in 2008, the project of this 1800 km long Electrical Transmission Line is a job of extreme technical complexity, crossing regions of major forests and rivers. When ready, it will allow the
Jan 1, 2015
-
Wrigley Field – The 1060 ProjectBy Darren S. Diehm
"Construction for the restoration and expansion of 102-year-old Wrigley Field in Chicago, Illinois began at the conclusion of the 2014 baseball season. This six year project involves structural upgrad
Jan 1, 1900
-
Cost and Technical Comparison of Non-Destructive Test Methods for Drilled ShaftsBy Ronnie Melker, Joel Webster, Daniel Belardo, Thomas Hyatt
Quality assurance of drilled shafts is highly dependent upon the construction practices used during the excavation and concrete placement process. When performed under slurry, challenges are presented
Jan 1, 2019
-
Mobilizing CIDH Pile Base Resistance on the Gerald Desmond Bridge Replacement Project with Tip GroutingBy Adam Zagorski, Rusty Lucido, Curt Scheyhing
"The current California Department of Transportation (Caltrans) practice based on AASHTO LRFD Bridge Design Specifications is to use the O’Neill and Reese method (FHWA, 1999) for calculating the side
Jan 1, 2017
-
Westlink Projects – Geotechnical Challenges During The Execution PhaseBy Robert Thurner, Albin Norrman, Sami U. Raja
The West Link is a double track railway project currently under construction in Gothenburg, Sweden. The project includes the construction of 8 kms of track, 6 kms of which will be in tunnels. Beside s
May 1, 2022
-
Cost Effective Drilling Of Extra Large [XL] Monopile FoundationsBy Phil Wilkinson, Sam Whitaker
"The installation of large (XL) diameter monopiles offshore typically requires expensive and specialist plant, equipment and vessels. Due to the increasing size (weight, diameter and length) of the fo
Jan 1, 2017
-
Excessive Pile Breakage, Gaylord National Resort And Conference Center, A Look Back 15 Years LaterBy Karl A. Higgins
In August 2004, the long-awaited National Harbor project in the DC metro area sprang to life with the design of Gaylord National Resort and Convention Center. When the project was in its final stages
-
Soil Mixing for the Rio Puerto Nuevo Project in San Juan, PR: A Case HistoryBy Filippo Maria Leoni, Wesley Schmutzler, Matteo Bertoni
"Deep Mixing Method (DMM) for the Rio Puerto Nuevo Project (Project) in San Juan was chosen by the Corps of Engineers to improve the soils adjacent to a 92 inch ID forced sewer main relocation and to
Jan 1, 2015
-
Developments In Thermal Integrity Testing Practice And InterpretationBy A. Fisher
The use of thermal integrity testing to verify the quality of deep foundations has increased significantly in the UK and other world markets over the last 5 years. The introduction of distributed fibr
Oct 1, 2022
-
Design, Modelling And Construction Of A 12-Sided Diaphragm Walled ShaftBy Stephen Buttling
The construction of a water treatment plant in Dandenong, Victoria, required detention tanks and a pumping well. The design provided by the Engineer used conventional rectangular cast-in-situ reinforc
Nov 1, 2022
-
San Francisco International Airport Air Traffic Control Tower Pile FoundationsBy Camilo A. Alvarez, Stephen K. Harris, Brian R. Zuckerman, Philip J. Meymand, Danielle M. Steinmetz
"The sleek new air traffic control tower at the San Francisco International Airport stands at 221 feet tall and is set to replace the existing air traffic control tower by 2016. This aluminum-clad, to
Jan 1, 2017
-
Dynamic Response of Short Piles under Lateral Transient LoadBy Ambarish Ghosh, Rituparna Dey, Indrajit Chowdhury
"In port and harbor facilities, jetties and cargo berth terminals are usually installed on piles that remain partially embedded in soil, while a part of it behaves as columns supporting top deck. Tech
Jan 1, 2015
-
Automation Of Pile Foundation Design Post-Processing To Produce Pile PlansBy Rajasekar Subbian, Jessica Oudhof
In the Netherlands pile foundation design is done using CPTs in accordance with EC7 national annexure. The capacity per tip level is calculated for every CPT followed by zonation to find the tip level
May 1, 2022