Excessive Pile Breakage, Gaylord National Resort And Conference Center, A Look Back 15 Years Later

- Organization:
- Deep Foundations Institute
- Pages:
- 11
- File Size:
- 662 KB
- Publication Date:
Abstract
In August 2004, the long-awaited National Harbor project in the DC metro area sprang to life with the
design of Gaylord National Resort and Convention Center. When the project was in its final stages of
construction in 2007, it was noted as largest building development of the east Coast and the 4th largest
Building project in the U.S. The final construction costs were above $900M and it served as the catalyst
for the overall National Harbor development which added another $1B in construction costs over the next
few years. The Gaylord Hotel is supported by approximately 150,000 linear-feet of driven precast concrete
piling, one of a handful of major DC area projects in the early 2000s that were supported by this pile type.
The project overall was a success, but the fast-paced construction schedule created significant challenges
to the designers and contractors. Piling installation was the first major building construction task, and it
did not start out well. While the test piles were installed without damage, when production pile driving
began in the summer of 2005, pile head and body breakage soon became evident. Typical of most highprofile
projects, there are many stakeholders involved and an equal number of opinions on why the piles
were breaking. The financial and contractual implications of starting the project off awkwardly were evident
to all. The pile driving criteria was scrutinized by the contractor, and the engineer’s had reservations about
the size and type of the hammers used for pile driving. Ultimately, it was proven the leading cause of pile
breakage was neither the pile driving criteria nor equipment, rather the pile materials themselves. The
author of this paper is also the Geotechnical Engineer of Record for Gaylord National and many of the
adjacent National Harbor buildings including the recently completed MGM casino. About 100 piles were
damaged during Gaylord’s construction some requiring multiple piles for replacements. Over the past
decade or so, rumors on the causes of the pile breakage have spread in the market, with some alleging this
pile type is not compatible with the geologic setting. I have purposely avoided writing this case-study due
to the controversy surrounding the subject, but now some 15 years later it seems appropriate to do so
considering DFI’s annual conference location. This will be a fact-based assessment of pile breakage at
Gaylord and will also include a comparison to the neighboring buildings where far fewer driven piles
were damaged, once a more appropriate concrete mix design was required. The pre-cast supplier is no
longer in business.
Citation
APA:
Excessive Pile Breakage, Gaylord National Resort And Conference Center, A Look Back 15 Years LaterMLA: Excessive Pile Breakage, Gaylord National Resort And Conference Center, A Look Back 15 Years Later. Deep Foundations Institute,