Problems Of Cast In Situ Driven Piles Added To Existing Piles And Built Near A Standing StructureBy L. F. Albert
The paper describes solutions given to foundation problems during the reconstruction of a power plant set on fire, located adjacent to several still Working Units. After a detailed site and laboratory
Jan 1, 1989
-
Deep Excavation Retaining Systems In Unsaturated SoilsBy Tariq B. Hamid
Deep excavation is commonly associated with construction of different deep below-grade structural elements (e.g., basement walls and slabs, tunnels, retaining walls, tanks, utilities, etc.) Deep Excav
Jan 1, 2006
-
DFI and NDT – Parallel Histories and Mutual BenefitsBy Bernard H. Hertlein
"When the Deep Foundations Institute (DFI) was founded, quality assurance and quality control (QA/QC) of foundation construction was rudimentary. Nondestructive testing (NDT) was a nascent technology,
Jan 1, 2017
-
Caisson Design And Construction Challenges On The New Tiger Stadium Project - SummaryBy Fritz J. Klingler
From site demolition, to design, to construction, Detroit's new Tiger Stadium project is required to be completed within a short 2 ½ years from award of the design-build contract. Such extreme sc
Jan 1, 1999
-
High Capacity Drilled Cast-In-Place Piles, House Of Representatives Building, Lansing, Michigan - SummaryBy Robert C. Rabeler
Soil and Materials Engineers, Inc. (SME) has utilized drilled cast-in-place (D-CIP) piles on a number of projects in the midwest. These foundation systems have typically consisted of drilling an 8 to
Jan 1, 1999
-
Construction, Inspection And Lessons Learned For 3.81-M Diameter CIDH Piles ? Richmond-San Rafael Bridge Seismic RetrofitBy A. R. Dover
The Richmond-San Rafael Bridge is a 6.92 kilometer (4.3 mile) long major toll bridge span that crosses the northern San Francisco Bay in a highly seismically active region. Tutor-Saliba / Koch / Tidew
Jan 1, 2008
-
Charles Grimes Bridge Foundations, Melbourne, Australia - SynopsisBy Charles Pol Vuillier
Piling work for modification to the Charles Grimes Bridge in Melbourne, Australia required piles to be installed through 15 to 20 m thickness of very soft to soft silty clay overlying 10 m of stiff cl
Jan 1, 2000
-
Evaluating Geotechnical Resiliency Solutions in New York CityBy Karen C. Armfield, Gisele R. Passalacqua, Joanna Smith
When selecting a solution for improving resiliency at facilities, such as airports, utility and transit sites, there are many options to protect structures and equipment against potential flooding. Ea
Jan 1, 2018
-
Numerical Modelling of a Deep Excavation Shoring for Replacement of Control Structure at a DamBy Lok M. Sharma, Deep K. Khatri, Bradfield. Brett
"A shored enclosure was required to access a control structure upstream below the dam of a deep lake. The shoring involves the interaction of the structure, soil, and water and the loads imposed inclu
Jan 1, 2017
-
Application Of Bu-Type Steel Sheet Pile On Construction Of Ports ? PrefaceBy Zhou Lu-Jian
The Port of Shekou is situated at Shenzhen Bay on the east bank of Lingding Ocean. Its coastline is about 6 km long and the water depth near the shore is Favourable. Across the bay is the ' New T
Jan 1, 1991
-
Construction Of A Continuous Flight Auger Secant Wall: Chattahoochee Water Treatment Plant, Atlanta, Georgia - Project DetailsBy Gordon King
The City of Atlanta Water Department required the construction of a two sludge tanks and a wet well at the existing Chattahoochee Water Treatment Plant. Western Summit won a design build contract to b
Jan 1, 2003
-
Dynamic Stability Of An Axially Loaded PileBy S. S. Gajin
The paper deals with parametric vibrations of an axially loaded pile. The dynamic model is derived by means of Hamilton's principle and reduced to a partial differential equation with variable c
Jan 1, 1989
-
World Financial Center Foundations, New YorkBy G. Tamaro
The World Financial Center is situated on a 60,000 square meter site at Battery Park City at the southern tip of Manhattan Island. The foundations for the buildings and the related infrastructure pose
Jan 1, 1989
-
Design And Construction Of Integral Drilled Shaft - Columns For The Boscawen-Canterbury BridgeBy Frederick C. Rhyner
Drilled shafts have become an economical foundation choice for bridges in the northeast United States, especially when they can be constructed over water without the use of cofferdams. For the Boscaw
Jan 1, 2004
-
Installation Of Augered Cast-In-Place Piles - Equipment (b596934a-6910-4dd1-8c4a-72745306d21b)By Tracy Brettmann
? Hollow Stem Auger ? Drill Bits ? Leads/Torque Arm ? Hydraulic Gearbox ? Hydraulic Power Unit ? Grout Pump ? Crawler Crane
Jan 1, 2001
-
Estimation of Shaft and Base Responses from Pile Load TestBy Vidyaranya Bandi, Madhav Madhira, Kota Vijay Kiran
"Using hyperbolic relationships for the non-linear responses of shaft and base resistances, a method is proposed for estimating initial shaft and base stiffnesses and ultimate shaft and base resistanc
Jan 1, 2017
-
Design And Construction Aspects Of A Deep Basement In Dublin - SynopsisBy Philip J. Daynes
As part of the regeneration of the centre of Dublin, a multi-functional development is being constructed on the site of the historic Smithfield Fruit Market. The site is being developed in three phase
Jan 1, 2003
-
Low Strain Integrity Testing Of Deep Foundations ? IntroductionBy Jay A. Berger
Nondestructive testing of deep foundations for integrity problems made great strides in the late 1980's. Inexpensive portable computers have allowed the immediate and rapid processing of field me
Jan 1, 1990
-
Installation And Testing Of Instrumented Tieback Anchors - IntroductionBy Joan Stoupa
The expansion of the West Point wastewater treatment plant located in Seattle, Washington, will require a permanent tieback retaining wall to enlarge the plant site for the new treatment plant facili
Jan 1, 1990
-
Design And Construction Of Large Diameter Drilled Shafts For The Bath - Woolwich BridgeBy Andrew Peterson
The Maine Department of Transportation offered this challenging design-build project for a new, 12-span, bridge over the Kennebec River in Bath, Maine. This structure would be built to replace the exi