Design And Construction Of Large Diameter Drilled Shafts For The Bath - Woolwich Bridge

- Organization:
- Deep Foundations Institute
- Pages:
- 12
- File Size:
- 1028 KB
- Publication Date:
- Jan 1, 1999
Abstract
The Maine Department of Transportation offered this challenging design-build project for a new, 12-span, bridge over the Kennebec River in Bath, Maine. This structure would be built to replace the existing Carlton Bridge connecting the village of Bath, Maine to neighboring Woolwich, Maine. The design build team of Flatiron Structures, Inc., and Figg Engineers, Inc., elected to design and build a segmental concrete bridge. Site conditions dictated that this bridge would be supported primarily on deep foundations. Case Foundation Company joined the project team in the winter of 1997 to install twenty-two, eight foot diameter drilled shafts. The drilled shafts were designed with 8' diameter, permanently cased shaft sections and 7.5' diameter rock sockets. Shaft lengths ranged from 20' long near the river's edge to 100' deep in the middle of the river. Rock socket lengths ranged from 12' to 30' deep. Two Osterberg Cell load tests were conducted on production drilled shafts. Figg Engineers utilized the results of the load tests to "fine-tune" the rock socket design during construction of the drilled shafts. Construction of the drilled shafts proved to be very challenging and called on every member of the design-build team to work together throughout the project. One of the most challenging aspects of this project was in the installation of the 8' diameter permanent casing and drilling of the rock sockets. Early in the project, it became apparent that the top of bedrock was broken and unstable. This condition limited the advancement of the permanent casing and the affect of a "seal" at the top of rock socket. As a result, as the rock socket was advanced, loose material spilled into the hole and stopped progress of the socket. In order to resolve this problem, the design-build team developed a redesigned drilled shaft which included the installation of a steel sleeve to seal off the unstable rock formation. Following installation of the sleeve, the rock socket diameter was reduced to 7' diameter and advanced additional length to achieve required design capacity. All drilled shafts were installed with equipment supported on floating barges. Water access, along with the long shaft lengths and very hard bedrock required the use of cranes and drilling equipment that far exceeded the requirements of typical drilled shaft projects. This paper will discuss the relationship between design, construction, and equipment utilization on this challenging design-build project. [ ]
Citation
APA:
(1999) Design And Construction Of Large Diameter Drilled Shafts For The Bath - Woolwich BridgeMLA: Design And Construction Of Large Diameter Drilled Shafts For The Bath - Woolwich Bridge. Deep Foundations Institute, 1999.