    Presentation #4 - Reflections On Pile Integrity Testing

    By Joram M. Amir

    Even when they are cased! [ ] In bored piles, as well as in drilled shafts, and in caissons too, defects will occur! [ ]

    Jan 1, 2001

  • DFI
    Slurry Wall Design For Hong Kong Station

    By Stephen T. Young

    The construction of Phase 2 of Hong Kong Station, its retail podium and International Finance Centre Two, the tallest building in Hong Kong, will be completed in the middle of 2003. This paper describ

    Jan 1, 2003

  • DFI
    Bored Piles With Base Preloading By Grouting - The Polish Experience

    By Bolestaw A. Ktosihski

    Preloading of bored pile bases by grouting is an effective way of reducing foundation costs. The bearing performance of a pile may be considerably improved. Various techniques and devices are used. Pr

    Jan 1, 2006

  • DFI
    Wave Equation Analysis And Dynamic Monitoring - A Presentation At The Deep Foundations Institute?McGill University Symposium Montreal, September 1983

    By Bengt Fellenius

    The conventional wave equation analysis without control of the representativeness of the parameters to the actual conditions does not provide accurate results. However, the representatives can be vast

    Jan 1, 1984

  • DFI
    Skilled Operative Training For The Foundation Industry - Summary

    By Geoffrey Birch

    A skilled and efficient workforce is a pre-requisite for the success of modern construction companies. The drive for improved performance, innovation and best value must be matched by the enhanced ski

    Jan 1, 2000

  • DFI
    Excavation Support At Historic Buildings In An Urban Environment - A Case Study

    By Tony Mazzo

    It has often been said by consulting engineers that foundation contractors are in the business of taking risks. One would agree that the mere fact a foundation project can be budgeted, planned, engine

    Jan 1, 2003

  • DFI
    Value Engineering of Reinforcement used in Large Diameter Drilled Shafts

    By Shahid Islam, Lucian Bogdan

    Deep and large diameter drilled shafts use mostly bundles of Grade 60 (415 MPa) reinforcing bars as longitudinal reinforcement with rebar splices to make it longer. Lower Grade steel requires large nu

    Jan 1, 2018

  • DFI
    High Strain Testing Of Augered Cast Piles At Miami Fort Power Station

    By C. Michael Morgano

    Static tests are costly and time consuming, so they are not always the best answer [ ]

    Jan 1, 2005

  • DFI
    The Effect Of Overburden On Pile Capacity In A Calcareous Marl

    By William M. Camp

    An extensive design phase testing program in which 10 piles and 2 drilled shafts were instrumented and statically load tested to failure, was undertaken to establish relevant foundation design paramet

    Jan 1, 1993

  • DFI
    Permanent Canal Closures and Pumps Cofferdams – Support of Deep Excavation in Soft Ground Using the Open Cell Sheet Pile System

    By Ryan Higbie, King Chin, Matthew Anderson, Mike Huggins, Rian Johnson, Dave Sinsheimer

    "The Permanent Canal Closures and Pumps (PCCP) project is the capstone piece of New Orleans’ extensive hurricane risk-reduction system constructed following Hurricane Katrina. The project consists of

    Jan 1, 2017

  • DFI
    A Novel Approach To The Performance Evaluation Of Driven Prestressed Concrete Piles And Bored Cast-In-Place Piles

    By Sridhar Krishnan

    This paper presents the results of a comprehensive pre-production pile testing programme for the US$ 800 million 1400MW Coal-Fired Jimah Power Plant Project in Negeri Sembilan, Malaysia. The testing p

    Jan 1, 2006

  • DFI
    Residual Load Development Case Study In Driven Cast-In-Situ Piles

    By Packer M. L

    Residual load development in driven precast piles has been widely researched in recent decades, however, cast-in-situ piles are often falsely assumed to be unaffected by this mechanism. In contrast to

    May 1, 2022

  • DFI
    Damage To Initially Bent Piles ? Synopsis

    By B. B. Broms

    A method for calculating the bending moment induced in misaligned or bent piles is described, The maximum bending moment varies with the angular rotation between the pile segments, the coefficient of

    Jan 1, 2010

  • DFI
    Three Case Histories Comparing Impact And Vibratory Driven Pile Resistances In Marl

    By Gregory J. Canivan

    Three test pile programs were conducted in Charleston, South Carolina to evaluate differences in bearing resistance due to installation methods. The tested piles were installed with impact hammers and

    Jan 1, 2002

  • DFI
    Resonant Pile Driving - Part I - The Promise & The Reality - Part II - Soldier Pile Installation - Light Rail Transit - Buffalo, New York - 1. Historic Background.

    By D. R. Dance

    The Resonant, or as it has more commonly come to be known the 'Sonic' Pile Driver, dates back to the early 1960's, when prototypes were produced by Charlie Guild, of Providence, Rhode I

    Jan 1, 1987

  • DFI
    Upgrading Projects of Existing Infrastructures by Steel Piles – Press-in Method and Implant Structure

    By Tsunenobu Nozaki

    "AbstractThe PRESS-IN METHOD is widely recognised as “an environmentally friendly piling method”. However, this characteristic is only one of the fundamental advantages of the method and this paper pr

    Jan 1, 2014

  • DFI
    Innovative European Technologies To Accelerate Construction Of Embankment Foundations - Part I: GEC, AUGEO & CFA

    By Ali Porbaha

    In today's fast-track construction environment, owners are searching for non-conventional technologies to build their projects faster and safer while maintaining traffic flow during construction.

    Jan 1, 2002

  • DFI
    Deep Mixing Method: A Global Perspective

    By Donald A. Bruce

    Various types of contemporary Deep Mixing Method (DMM) techniques have been used in the United States since 1986. Such techniques owe their origins to Japanese and Scandinavian developments, which beg

    Jan 1, 1998

  • DFI
    Inaccurate Interpretation Of Offshore Geotechnical Site Investigation Results And Risk Associated - A Case Study Of Conductors Collapse In Driving

    By Hodjat] [Shiri

    A 4-legged jacket structure was installed by an Offshore Installation Contractor (OIC) in the Persian Gulf. In addition to four open-end pipe piles, six conductors were installed by OIC. During the in

    Jan 1, 2006

  • DFI
    Interlocking Caisson Walls

    By William E. Lardner

    Interlocking caisson walls developed from conventional "soldier pile and lagging" shoring. In the latter, the soldier piles receive directly most of the soil load. Natural arches form in the soil behi

    Jan 1, 1987