    Tanana River Bulkhead Expansion, Flexibility In Construction; Key To Arctic Dock Construction

    By Roy Peratrovich

    An innovative cost-saving design for a 1,100 ft bulkhead on the Tanana River at Nenana in central Alaska won Alaska Construction & Oil magazine's Construction Achievement Award. The designers uti

    Jan 1, 1985

  • DFI
    Argosy Casino Expansion: Open Cell Sheet Pile® Harbor Project

    By Michael Lane

    With the success of their existing casino operation on the Ohio River in Lawrenceburg, Indiana, the Indiana Gaming Co., LP planned a major expansion of the current facilities. This expansion includes

    Jan 1, 2008

  • DFI
    Non-Destructive Testing Methods For Drilled Shaft And Acip Piles

    By George Piscsalko

    There are numerous methods currently available to assess the integrity of drilled shaft and ACIP piles. Each method has its advantages and limitations. This paper will compare the various available me

    Jan 1, 2011

  • DFI
    Innovative Methods for Underground Parking in Central Cities

    By Qi Wang, Zengzhu Kang, Jianguo Liu, Guanglei Liu

    "Due to the increase of automotive vehicles, available parking spaces become a new type of limited resource in central cities of China, especially in those old districts without visionary urban planni

    Jan 1, 2017

  • DFI
    Deep Vibrocompactation By Stone Columns And Liquefaction Investigation

    By P. Ventura

    Reliability of the liquefaction analysis is based on data plotted as by piezocone, as by deep vibrocompactation monitored tests. The negative porewater pressure, re lated to hydrostatic value, recorde

    Jan 1, 1989

  • DFI
    Instrumented Rock-Socketed Drilled Piers Hamilton General Hospital ? Introduction

    By R. G. Horvath

    In the Hamilton area, and in many other areas of Ontario and around the world, large diameter drilled pier (caisson) foundations are frequently selected as the most appropriate foundation system for h

    Jan 1, 1987

  • DFI
    Design And Construction Of Bored Piles And Diaphragm Wall For MHA Headquarters Complex, Singapore - Synopsis

    By N. S. Yet

    This paper shall present the design and construction of bored pile and diaphragm wall for the proposed MHA complex in Singapore. The work was carried out by L&M Foundation Specialist Pte Ltd and PWD C

    Jan 1, 2000

  • DFI
    Quality Control Of Piling And Deep Foundations In Belgium, From The Design To The Execution. ? Synopsis

    By D. Goossens

    Quality control is a system which should guarantee that quality is achieved. It is the execution and verification of a project in an organised way, in order to obtain the maximum of certainty that the

    Jan 1, 1996

  • DFI
    A Critical Appraisal Of Is-Code Provisions For Pile Design ? Synopsis

    By N. Som

    The pile capacity in cohesive and granular soils depends on a number of parameters. The values of these parameters as recommended by Indian Standard Code of Practice vary over wide ranges. A designer

    Jan 1, 1996

  • DFI
    Dynamic Analysis Of Follower Driven Piles For The Venice Flood Gate Project

    By Frank Rausche

    Without doubt, driven piles are the most economical deep foundation element for a nearshore environment, providing for high bearing capacities and stiffness, quick installation times, assured quality

    Jan 1, 2006

  • DFI
    Execution And Evaluation Of High Capacity Caisson Load Tests In Glacial Deposits

    By Franklin M. Grynkewicz

    As part of the Boston Harbor clean up project, the new 1,000 mgd Deer Island Sewerage treatment plant includes ten 240 feet high egg-shaped "residuals" tanks. Contract documents called for these struc

    Jan 1, 1992

  • DFI
    Lateral Capacity Of Rigid Piles In Clays Based On Earth Pressure Concepts - Synopsis

    By S. Narasimha Rao

    Significant amounts of lateral load may act on pile foundations supporting structures such as transmission line towers, tall structures, bridge abutments, offshore platforms, quay wails, harbour struc

    Jan 1, 1996

  • DFI
    Lake Champlain Temporary Ferry Dock Fast-Track Design And Construction Challenges And Successes

    By John E. Lens

    Minutes after the Friday afternoon October 16, 2009 announcement that the 80 year old Lake Champlain Bridge was closed to traffic out of concern for public safety, emergency detour planning started at

    Jan 1, 2011

  • DFI
    I-880 Replacement Project (Cypress Freeway) Large Diameter Driven Pipe Pile Foundations Test Program And Construction - Program Development - Background - Collapse

    By Darrell L. Beddard

    The Loma Prieta earthquake occurred on October 17, 1989 at 5:04 PM, Pacific Daylight Time. It measured 7.1 in magnitude and was felt from Los Angeles north to the Oregon state line and east to western

    Jan 1, 1996

  • DFI
    Simulation of Offshore Piling using Advanced Dynamic Material Point Method (MPM)

    By Shreyas Giridharan, Fursan Hamad, Sujith Gowda, Christian Moormann

    "Pile installation in soil is a dynamic process which exhibits large deformation in the soil region. Experimental investigation of pile installation is both time and resource intensive. Numerical inve

    Jan 1, 2017

  • DFI
    New CIGMAT Downhole Penetrometer (DHP-CIGMAT) For Use During Drilled Shaft Construction

    By C. Vipulanandan

    It is critical to monitor the ground conditions during excavation and drilling of boreholes during construction to identify possible changes in the soil and rock formations. Drilled shafts are increas

  • DFI
    Case History: Use Of Rock-Socketed Augered Cast-In-Place Piles

    By Tracy Brettmann

    The use of rock-socketed Augered Cast-In-Place (ACIP) piles is new to the Austin and central Texas region. This case history describes the design methodology, load test results, quality control proced

    Jan 1, 1998

  • DFI
    Interlocking H-Sections For Cofferdams Resist High Pressure

    By Marc Dondelinger

    Interlocking H sections with deep webs and high section modulus are being used for cofferdams and shore enclosures where pressures are excessive. The H sections can be as much as a meter deep; they ca

    Jan 1, 1985

  • DFI
    Use Of Auger Pressure Grouted (APG) Piles Inside An Existing Operational Structure

    By Lawrence P. Goldfarb

    The City of Alexandria, Virginia, Public Safety Center (PSC) is a 64,000 square foot facility that houses the Police Department, Office of Sheriff and the Office of Magistrate. In addition, the center

    Jan 1, 2009

  • DFI
    Longitudinal Splitting Of Precast Reinforced Concrete Piles During Driving ? Synopsis

    By B. B. Broms

    The high transverse tensile stresses that develop in precast concrete piles during driving have been investigated experimentally from pile load tests and theoretically using the finite element method

    Jan 1, 2010