Execution And Evaluation Of High Capacity Caisson Load Tests In Glacial Deposits

- Organization:
- Deep Foundations Institute
- Pages:
- 33
- File Size:
- 2943 KB
- Publication Date:
- Jan 1, 1992
Abstract
As part of the Boston Harbor clean up project, the new 1,000 mgd Deer Island Sewerage treatment plant includes ten 240 feet high egg-shaped "residuals" tanks. Contract documents called for these structures to be supported on 2,600 sixteen inch concrete filled pipe piles. The project site is underlain by highly variable glacial and marine deposits. Subsurface conditions vary from one extreme where firm glacial deposits exist at subgrade to the other extreme where 70 feet of medium stiff clays overlying weathered bedrock must be dealt with. The most common profile consisted of 15-20 feet of sands, 20-40 feet of marine clays, and 20-60 feet of stratified glacial deposits (commonly called tills) overlying Argillitic bedrock. Post bid redesign work, initiated as a cooperative effort between the owner and the general contractor, demonstrated that an $8 million savings could be realized if high capacity 48 inch diameter caissons replaced the specified pipe piles. A highly unusual arrangement of having the general contractor and specialty subcontractor providing input to the owner's engineering team allowed the redesign work to proceed on a "fast-track" schedule.
Citation
APA:
(1992) Execution And Evaluation Of High Capacity Caisson Load Tests In Glacial DepositsMLA: Execution And Evaluation Of High Capacity Caisson Load Tests In Glacial Deposits. Deep Foundations Institute, 1992.