    The Spadina Pier Cofferdam - Design, Installation & Performance

    By Jan A. Nilsen

    This paper describes a key element in the construction of a major project undertaken by Harbourfront Corporation in its efforts to rejuvenate the central Toronto waterfront. The Spadina Pier forms one

    Jan 1, 1987

  • DFI
    Interlocking H-Sections For Cofferdams Resist High Pressure

    By Marc Dondelinger

    Interlocking H sections with deep webs and high section modulus are being used for cofferdams and shore enclosures where pressures are excessive. The H sections can be as much as a meter deep; they ca

    Jan 1, 1985

  • DFI
    Deep Excavations And Foundations For Locks ? Synopsis

    By B. H. Moore

    Foundation and excavation problems associated with lock construction projects vary widely. Each lock requires a different foundation to respond to a unique geologic setting. The range of heights and f

    Jan 1, 2010

  • DFI
    Augered Cast-In-Place Piles: Regional Project Profiles - Community Osteopathic Hospital Harrisburg, Pa

    GENERAL CONTRACTOR: ALEXANDER CONSTRUCTORS, INC. STRUCTURAL ENGINEER: CAGLEY & ASSOCIATES, INC. GEOTECHNICAL ENGINEER: F.T. KITLINSKI & ASSOCIATES, INC. PILE FOUNDATION CONTRACTOR: L.G. BA

    Jan 1, 2001

  • DFI
    Offshore Wind Turbine Foundations - In Denmark And Belgium - Introduction

    By Jørn H. Thomsen

    This paper presents the experience gained and the lessons learned over the last decade within the numerous offshore foundation projects undertaken in the offshore waters of Denmark and Belgium by COWI

    Jan 1, 2013

  • DFI
    New Technology For An Old Seawall: Micropile Installation At Ellis Island National Park In New York Harbor

    By Helen D. Robinson

    The seawalls that surround Ellis Island were constructed in the early 1900s and now show varying degrees of deterioration. An innovative approach to the structural repair of the seawalls was develope

    Jan 1, 2008

  • DFI
    Deep Soil Mixing for Contaminated Soil Remediation at a Superfund Site

    By Larry Stearns, Lori Tiefenthaler

    Remediation of contaminated soil represents a significant market for application of Deep Soil Mixing (DSM). Eighty-one percent of U.S. Environmental Protection Agency (EPA) Superfund Program’s site re

    Jan 1, 2018

  • DFI
  • DFI
    Fenway Park Modernization - Foundations For A Red Sox Nation

    By Mark H. Balfe

    Over the last decade, Fenway Park has undergone annual improvements to modernize the facility for players and fans. These renovations include the Monster Seats, the Right Field Roof expansion, a new

    Jan 1, 2011

  • DFI
    Vibratory Driver/Extractors Do More Than Drive Sheet Piles - Summary

    By John L. White

    Vibratory driver/extractors do more than drive and extract sheet piles. I would say more than sixty percent (60%) of the time, vibratory pile driver/extractors are engaged in work that has nothing to

    Jan 1, 1997

  • DFI
    Söderströmstunneln – An Immersed Tunnel Founded on Steel Core Piles

    By Frank Haehnig, Kjell-Åke Averstad, Johannes Glückert

    "AbstractThe Söderströmstunneln is part of the Citybanan project that is currently under construction in the centre of Stockholm. Main part of the lot Söderströmstunneln is a 300m long immersed tunnel

    Jan 1, 2014

  • DFI
    Construction Of Large Underground Openings And Use Of Grouts ? Synopsis

    By E. Mongilardi

    The construction of large underground openings through cohesionless or weak cohesive soils and under the water table in particular, often requires a ground improvement to be done from the surface or a

    Jan 1, 2010

  • DFI
    Lake Champlain Temporary Ferry Dock Fast-Track Design And Construction Challenges And Successes

    By John E. Lens

    Minutes after the Friday afternoon October 16, 2009 announcement that the 80 year old Lake Champlain Bridge was closed to traffic out of concern for public safety, emergency detour planning started at

    Jan 1, 2011

  • DFI
    Seal Slab / Steel Pile Interface Bond From Full-Scale Testing

    By Gray Mullins

    This paper presents results from model and full-scale tests to assess the interface bond between a cast-in-place concrete seal slab and steel H-piles in cofferdams. Three different seal slab placemen

    Jan 1, 2013

  • DFI
    Improvement Of The Cost-Effectiveness Of H-Bearing Piles By Using High-Strength Histar Steels. - Summary

    By Lucien P. Weber

    Over the last few years, increased customer demands as well as strong competition from substitute materials have accelerated the development of advanced technologies to improve both the performance an

    Jan 1, 1997

  • DFI
    Lateral Performance Of Two-Section Helical Piles In Soft Soils

    By Mohammed Sakr

    A Two-Section Helical Pile (TSHP) is a steel pipe with two shaft sections of different diameters and with one or more helix plates near the bottom of each shaft section. TSHPs are used regularly in we

    Jan 1, 2009

  • DFI
    Float-In Cofferdams

    By Robert B. Bittner

    Large diameter piles (2 to 3 m diameter, both driven and drilled) are being used more frequently by designers of bridge foundations. The use of these large piles allows the pile cap to be positioned

    Jan 1, 2013

  • DFI
    Numerical Analysis Of Load Bearing Capacity Of Drilled Shafts With Defects

    By Khamis Y. Haramy

    Quality assurance and quality control of drilled shafts has become a concern due to difficulties in accurately locating construction anomalies and determining load bearing capacity of defected drilled

    Jan 1, 2007

  • DFI
    Field Trials for Deep Mixing in Land Remediation: Execution and Early Age Monitoring, QC and Lessons Learnt

    By Ziyad Abunada, David O’Connor, Abir Al-Tabbaa

    "Abstract Contaminated land remediation using soil mix technology (SMT) is a relatively recent development which has been shown to be a cost effective and versatile system with numerous environmental

    Jan 1, 2014

  • DFI
    Design And Construction Of A Cut-Off Wall In Warm Permafrost

    By Steven L. Anderson

    A cut-off wall has been designed and is currently under construction along the Back Dam of the existing tailings impoundment at Red Dog Mine, Alaska. The cut-off wall, which will be in the order of 5

    Jan 1, 2010