    Design, Construction, And Instrumentation Of An Atypical A-Frame Micropile Wall In Aspen, Colorado

    By Kyle Kershaw

    Micropiles are routinely used in the United States for foundation support and stabilization of slopes. In recent years, several retaining walls have been constructed using micropiles in an A-frame ty

    Jan 1, 2007

  • DFI
    Design, Construction, and Long-Term Monitoring of a Pile-Supported LNG Tank in Savannah, Georgia

    By Cheng Lin, Guoming Lin

    "This paper presents a case history for the design, construction and long-term performance monitoring of a driven prestressed concrete (PSC) piled foundation supporting a large liquefied natural gas (

    Jan 1, 1900

  • TMS
    Design, Construction, and Operation of Periodic Reverse Current Process at Tamano

    By Tatsuzo Kitamura

    The tank house of Tamano refinery, that started its operation in January, 1972, was constructed incorporating the application of Periodic Reverse Current (P.R.C.) from the outset of design works. In 1

    Jan 1, 1976

  • DFI
    Design, Construction, and Performance of the Temporary Earth Retention System at No. 9 Walton

    By Joel B. Dellaria, Justin R. Lewis

    "No. 9 Walton is a new high-rise condominium building located in the Gold Coast area of Chicago. The adjacent building, Walton on the Park, featured 4 levels of below grade parking and utilized a seca

    Jan 1, 2017

  • CIM
    Design, Construction, and Start-up of Stillwater Mining’s East Boulder Concentrator

    By P. Lefebvre, J. Sargent, K. Major, B. Darnton

    "Stillwater Mining commenced mining operations at Nye, Montana in 1987 for the recovery of platinum and palladium. Exploration identified that the J-M Reef extended for 43 km. In 1998 Stillwater Minin

    Jan 1, 2003

  • DFI
    Design, Construction, And Testing Of A Precast UHPC Pile

    By Thomas L. Vande Voort

    The strategic plan for bridge engineering issued by AASHTO in 2005 identified extending the service life and optimizing structural systems of bridges in the United States as two grand challenges in br

    Jan 1, 2008

  • AUSIMM
    Design, Construction, Commissioning And Operating Of the Elura Concentrator

    By Morrison R. D

    This paper describes major events in the design, construction, camtissioning and operation of the Elura concentrator. It covers the period fran September, 1974 when laboratory testwork on drill co

    Jan 1, 1983

  • AUSIMM
    Design, Development and Operation of a Hardrock Roadheader

    By Bromley JC

    Eimco Great Britain, a division of Baker Mining Equipment Company, was contracted to develop a hardrock tunnelling machine in conjunction with British Coal. The objective: a machine to cut rock up

    Jan 1, 1987

  • CIM
    Design, development, and verfication of a Lovat 7.6-metre full-face tunnel-boring machine

    By R. Lovat, J. A. Hunter

    "The design, development, and verification of the Lovat 7.6metre diameter full-face tunnel-boring machine is reviewed. Programmatic and technical challenges are outlined with a review of the specifica

    Jan 1, 1984

  • SME
    Design, Development, Application, and Operating Benefits of 100-m3+ Outokumpu TankCell Flotation Cells

    By Adolf J. Jonaitis

    Outokumpu developed TankCell flotation cell technology beginning in 1990, following 35 years of successful flotation cell experience and application. In 1994, Outokumpu proved favorable operating succ

    Jan 1, 1999

  • SME
    Design, Excavation, Support Of A Large Diameter Coal Mine Access Decline Using A Tunnel Boring Machine

    By Steve Polegato, J. Coady Marsh, Gary Landry

    The Donkin-Morien Mine in Cape Breton, Nova Scotia, has successfully completed the excavation of a 7.6m (25-ft) diameter access decline over a distance of 3.5km out under the Atlantic Ocean. The tunne

    Jan 1, 1985

  • AUSIMM
    Design, implementation and field performance of a face destress blasting method for mine development

    By E Villaescusa, C Drover, I Onederra

    Development face destress blasting is a construction technique in deep mining, which aims to prevent, reduce the frequency, or manipulate the timing of violent, stress-driven rock mass instability at

    Nov 29, 2022

  • CIM
    Design, Implementation, and Commissioning of the Gibraltar Development Plan 3

    By S. A. H Tyrrell, R. Rotzinger

    "Taseko Mines Limited recommenced operation of the Gibraltar copper-molybdenum mine in 2004 and embarked on series of development projects to modernize the mine and increase throughput capacity. The G

    Jan 1, 2014

  • AUSIMM
    Design, Inspection and Rehabilitation of the New Croton Aqueduct, New York City

    By A Fareth

    Constructed between 1885 and 1891, the New Croton Aqueduct (NCA) in New York State is a 50 km long (31 mi) brick-lined tunnel conveying water from the Croton watershed north of New York City to distri

    Jan 1, 2008

  • SME
    Design, Installation And Effectiveness Of A Degasification System At The Pasta De Conchos Mine

    By F. Gonzalez, A. Zambrano, J. Schwoebel, S. Kravits

    Significant lost time delays were experienced by Carbonifera de Nueva Rosita, S.A. de C.V. ("CNR") during mining development of the Pasta de Conchos Mine ("the Mine") near Nueva Rosita, Coahuila, Mexi

    Jan 1, 1993

  • SME
    Design, Installation And Operation Of The Pinto Valley Moly Flotation Columns

    By R. Rodgers

    The Pinto Valley Concentrator of BHP Copper Inc. restarted its sulphide mining operations in September 2007 to produce copper and moly concentrates. During the plant production ramp up, the copper/mol

    Jan 1, 2010

  • DFI
    Design, Installation And Performance Of Earth Retention System To Limit Ground Movements Around Sensitive Structures In Washington, Dc

    By Douglas R. Hardin, Stanley L. Worst, Joanna Mason

    A challenging earth retention project presented itself in Washington, DC in the backyard of the historic House of the Temple (The Scottish Rite of Freemasonry, Supreme Council 33°). Located at 15th St

    Oct 1, 2022

  • SAIMM
    Design, Installation And Testing Of The No 250 Wemco Smartcell? Flotation Machine At Minera Los Pelambres

    By A Weber, L MacNamara, H Schreiber

    Design and development of the world?s largest flotation cell was completed in 2002. This was the first 257 m3 flotation cell installed in the mineral industry and represents a major development in t

    Jan 1, 2007

  • DFI
    Design, Installation, and Testing of Hollow Bar Tiebacks Used as Excavation Support

    By Marco D. Boscardin, Kenneth A. Pidgeon, Adriane G. Boscardin

    "Hollow bar tiebacks can offer an economical alternative to conventional solid bar and strand tieback systems for use in temporary excavation support construction. However, the limitations associated

    Jan 1, 2016

  • AUSIMM
    Design, Installation, Commissioning and Operation of Fine Grinding Technology at the Kevitsa Mine

    By B Nielsen, H Lehto, B Musuku

    "The demand for fine and ultra-fine grinding associated with the processing of more challenging, finer grained orebodies and the global driver of minimising energy consumption has been an increased fo

    Oct 10, 2016