On Driven Piles In Coralline Deposits: A Selected Case From The Red Sea Coast Of Saudu Arabia
By Waddah Akili
At an offshore site along the Red Sea coast of Saudi Arabia, marine structures were supported on tubular steel piles driven into coral and coral contaminated sands and silts. Surprises and disappointm
-
Design And Specification Considerations For Environmental Cutoff Walls
By Daniel Ruffing, Jeffrey Evans
Vertical cutoff, or barrier, walls are an integral part of environmental site remediation efforts. Vertical barriers are commonly deployed to limit the influx of clean ground water and/or to control t
-
Pre-engineered Hydraulic Bracing Systems
By Braxton P. Erbe, Douglas C. Brunot
A variety of systems and techniques exist to support deep excavations where sloping is not feasible. This paper will explore an example project involving the use of pre-engineered hydraulic bracing sy
-
AN EXPERIMENTAL INVESTIGATION ON THE BENEFITS OF A HYBRID PILE/FOOTING SYSTEM ON SAND
By Mohammed Al Maadheedi
This paper explores the capacity effects of a square steel plate welded at the ground surface on a driven open-ended steel pile (i.e. the plate would touch the ground surface after the pile achieves t
-
Design-Build Synergy To Deliver Pile Foundations
By David P. Sauls
Design-build contract delivery provides unique opportunities for efficiencies in pile foundation design and installation. The Louisiana Department of Transportation and Development (LADOTD) US Highwa
-
Stabilizing A 100 Ft Rock Slope With Limited Access And Tight Construction Tolerances Using Observational Method And Real-time 3d Modeling
By Travis A. Shoemaker, Mitchell S. Youmans, Nancy T. Chin, Michael S. Senior
A geologic assessment and stability analysis of the right abutment of Boundary Hydroelectric Dam in Pend Oreille County, Washington was completed in May 2017. The stability analyses identified a poten
-
Evaluating Bending Failure Of Floating Soil-cement (Sc) Columns Under Road Embankments Using 3d Fea
By Sailesh S. Author
The current design method for soil-cement (SC) columns improved soft clayey ground under the highway embankments assumes a slip circle failure surface shearing through the columns and the soils using
-
Trencher Method Vs. Slurry Trenching: A Pros & Cons Comparison Of Case Studies
By Daniel Ruffing, Charlie Krug
In recent years, the chain-style trencher has been proven a valuable tool for installing vertical walls on challenging sites where conventional methods may be less desirable. Like many tools, trencher
-
Diaphragm Wall Technique Used In A Different Way Cutting Trenches Up To 823 Ft. (251 M) For An Exploration And Bulk Sampling Program
By Stefan Schwank, Alexander Blatt, Franz-Werner Gerressen
Diaphragm wall technique is usually used to install diaphragm walls, which are known as underground structural elements commonly used for retention systems and permanent foundation elements as well as
-
Capitol Complex Phase 1 Expansion
By Eric S. Lindquist, Charles A. Luxford
The State of Texas recently adopted a master plan to expand the existing Capitol Complex in Austin. Phase 1 of this expansion will add two new State office buildings and five levels of underground par
-
Ideas To Improve Driven Pile Foundation Design And Installation Procedures
By Armin W. Stuedlein, Steven R. Saye
The differences between calculated axial pile capacity and the capacity realized during and following installation has long presented a significant concern for foundation engineers and contractors. Su
-
Delving Deeper Into Foundation Slurry Rheology
By Greg Plutko
Laboratory testing has shown that the Marsh Funnel test can be significantly impacted by long-chain polymer entanglement. In general, shorter hydration time leads to more chain entanglement which in-t
-
John F. Kennedy Airport Site Redevelopment: Tapertube Pile Foundation
By Gisele R. Passalacqua, Aly Mohammad, Joanna Smith
The $13 billion John F. Kennedy (JFK) airport construction redevelopment program includes new terminals and buildings that are supported on piles to meet the airport expansion demand due to increased
-
Case Studies/case Histories In Geotechnical Engineerin: Enhancing The Practice In An Interactive Learning Environment
By Waddah Akili
This paper describes the steps taken in planning, developing, and executing a case study/ case history course in geotechnical/ foundation engineering at an international university. The paper sheds li
-
Comparing Analytical Models With Slipping And Non-slipping Interface In Axially Loaded Tension Piles
By Kelvin Lo, Erwin Oh, Darren Newel
The use of interface elements is widespread in most numerical methods to separate the structural elements from soil elements. It allows slipping and gapping or overlapping between the two media in con
-
Design And Construction Of Underground Basin Using Composite Slurry Wall 500 Feet Away From The Pacific Ocean
By Ihab Allam PE, Meeok Kim. PE. Ph. D
The wet weather equalization basin (EB) planned for Pacifica, CA is a 45 feet deep rectangular shaped underground water tank containing over 2.1 million gallons of water, and located only 500 feet awa
-
Is Excess Pore Water Pressure Build Up An Engineering Demand Parameter For Excavation Analyses?
By A. Felipe Uribe-Henao, Camilo Ballesteros, Luis G. Arboleda-Monsalve, David G. Zapata-Medina
Conventional excavation analysis based on total or effective stress methods can result in inaccurate estimation of ground movements when impervious soil conditions or rapid excavation sequences are no
-
Cost Analysis Of Multiline Ring Anchor Systems For Offshore Wind Farm
By Junho Lee, Leopoldo Bello, Mohammad Khan
Multiline ring anchor (MRA) was developed as a cost-effective solution for securing floating offshore wind turbines (FOWTs) to the seabed. Since FOWTs are placed in arrays compared to conventional oil
-
Costa Rica Circunvalacion Norte Project: Lessons Learned From Foundation Drilling
By Bernardo J. Jiménez, Harlem Lora, Roberto Acosta Mora
Circunvalacion Norte project is currently the most important infrastructure project in Costa Rica. It is the last segment of the urban perimeter highway. Site investigation of local geotechnical condi
-
Geospatial Project Information Management System At Herbert Hoover Dike
By Jamey Rosen
A Project Information Management System (PIMS) was developed to manage and analyze QC data at the Herbert Hoover Dike Rehabilitation Dam Modification Cutoff Wall (owned by the Jacksonville District of