Prediction Of Subsidence Basin By The Weibull Distribution FunctionBy R. H. Zeng
Many subsidence researchers in the U. S. have developed new empirical function methods to predict subsidence, or attempted to validate some empirical functions developed by foreign researchers for use
Jan 1, 1986
-
Development Of A Percussion Assisted Rotary Drilling System For Blasthole DrillingBy J. W. Langford
A more effective method of fracturing and chipping the formation is necessary to significantly increase the productivity of blasthole drilling with a roller cone bit. The conventional rotary blasthole
Jan 1, 2011
-
Limestone Marketing In A Changing Economy - The Economic RealitiesBy Robert C. Freas
While on the surface limestone marketing may appear mundane, it has continued to provide a series of challenges beyond the realm normally envisioned with this industry. This paper presents a case hist
Jan 1, 1981
-
Tribute To J. Robert WoolseyBy Michael Cruickshank
Bob Woolsey was born in 1936 in the state of Georgia and grew up to be a man of great integrity, vitality, wisdom and charm, totally neutral on matters of race, gender, and religion. A true Southern G
Jan 1, 2008
-
Roadheader Tunneling and Microtunneling in Low Strength Claystone at Standley Lake, ColoradoBy Glen Church, Don W. Deere, Christoph M. Goss
The Standley Lake Dam Rehabilitation Project in Colorado included the complete replacement of the outlet works. This required two 1.8m (6 ft) diameter microtunneled wet lake taps, 380m and 186m (1246
Jan 1, 2005
-
The Outlook For MicaBy S. A. Montague
In spite of the many new insulating materials, both synthetic and manufactured, that have been put on the market since the end of World War II, and notwithstanding the many millions of dollars applied
Jan 1, 1962
-
Up-to-date Excavation, Support, and Lining Solutions Meet Timing Requirements for the First Two Tunnels of the 2006 Winter Olympic GamesBy Georgios Kalamaras, Chiaia Dinu, Platania Paolo, Alessio Carlo, Giampiero Cirvegna, Claudio Santucci
The Project alignment initiates north of Pinerolo, along the State Road 23[S.S. 23] that is one of the principal arteries to the northwestern Alps where a number of Olympic events for the 2006 Winter
Jan 1, 2005
-
Assessment of equipment operator?s noise exposure in western underground gold and silver minesBy Ellsworth R. Spencer
An assessment of U.S. western hardrock miners? noise exposures was conducted as part of a multi-year National Institute for Occupational Safety and Health (NIOSH) survey of noise exposures in each sec
Jan 3, 2010
-
Design and construction of a surface air cooling and refrigeration installation at a South African mineImpala Platinum?s No.16 Shaft mine is currently under construction and is expected to reach full production of 256 500 tons per month by 2014. Mining will start at 1 260 m below surface with a maximum
Jan 1, 2009
-
Onsite Assembly And HARD Rock Tunneling At The Jinping-II Hydropower Station Power Tunnel ProjectBy Stephen M. Smading
Unique onsite assembly of a 12.43 m Main Beam TBM and back-up system was completed on September 18, 2008 in the remote mountains of the Sichuan province of China. The equipment was assembled onsite, w
-
South Interceptor Tunnel Construction Using a Lovat EPBMBy Dennis Molvik, Omar Fulton, Chris D. Breeds, Don Gonzales
This paper presents and describes the South Interceptor Parallel Phase III Contract C93012C, which involved construction of a nominal 2.7 m (9-ft) finished diameter sewer conveyance using both pipe ja
Jan 1, 2003
-
Barrick Goldstrike Roaster Facility Roasting And Gas HandlingBy A. Cole, A. Bolland
The roasting and gas handling circuits at Goldstrikes' new Roasting Facility incorporate proven technologies in a unique combination. During the design of the plant, every effort was made to uti
Jan 1, 2001
-
Collapse and Remining of Tunnel TO8 at THSRC Contract C230By William Stewart, John Tinkler, Gary B. Hemphill
Of the 345 km long Taiwan High Speed Rail Project, connecting the cities of Taipeiand Kaohsiung, the 23 km alignment on Contract C230 required the construction of5755 m of shallow mined tunnels rangin
Jan 1, 2005
-
Are Nanoparticulates Present In Typical Mineral Processing Practices And Can They Be Suppressed?By C. R. Copeland
Airborne dust emission standards are receiving growing attention. This trend is motivated by significant health studies that have shown adverse health effects due to exposure to dust. Currently, the a
Jan 1, 2007
-
Construction of Deep Shafts and Ground Improvement for the West Side CSO Tunnel Project, Portland, OregonBy Yves St-Amour, Vince Luongo
This paper will discuss one of the largest construction projects the City of Portland has undertaken. This phase of the Willamette River Combined Sewer Overflow (CSO)project consists of approximately
Jan 1, 2005
-
Shield Tunneling in Pure Sands - Merging the Application Fields of EPB and Slurry Shield TechnologiesBy Carlos Henrique Turolla Maia, Ulrich Maidl, Marc Comulada, Julio Claudio Di Dio Pierri
"Pure sands are typically the domain of slurry shields due to their high permeability and their granular characteristics. However, the Earth Pressure Balanced (EPB) shield machine technology has advan
Jan 1, 2016
-
General Legal Conditions for Land ReclamationBy K. Freytag
The extraction of lignite in open-cast mines has a severe impact on the landscape. Proper landscaping after the shut-down of the mines has always been the statutory responsibility of the mine operator
Jan 1, 2005
-
The Kensico–City Tunnel for New York City Water SupplyBy Robert J. F. Goodfellow, William A. T. Meakin, Kevin Clarke, Eric Cole
INTRODUCTION New York City Water Supply—Background and History Since the 1840s New York City has been developing the largest, and perhaps, the best urban water supply and distribution system in
Jan 1, 2005
-
Bulk Material Handling by Conveyor Belt at El AbraBy Rainer Kahrger
During the last decade, advances were made in solvent extraction/electrowinning (SX/EW) technologies. Combined with heap leaching, these technologies made it viable to exploit large, low-grade oxide
Jan 1, 1996
-
Nickel Laterite Processing: Second Generation Design ConsiderationsBy N. L. Hayward, V. H. Ness
In the past decade Australia has seen the development, construction and commissioning of three complex processing plants for the treatment of lateritic nickel ores. These have all been based on high p