    The Effect of Clearance Angle on Wear of Rotary-Drag Bits

    By testing rotary-drag bits in granodiorite it was found that an increase in bit clearance angle from 241 0 to 33° decreased insert wear. Severe wear has precluded economic application of rotary-

    Jan 1, 1969

  • AUSIMM
    The Determination of Bismuth in Soils, Sediments, and Rocks

    Samples weighing 0·5 g are fused with potassium hydrogen sulphate, leached with 4 ml. of 4 M nitric acid and diluted to 10 ml. with water. An aliquot of the clear solution is treated with EDTA, a

    Jan 1, 1971

  • AUSIMM
    The Kwinana Nickel Refinery Western Corporation Limited

    Construction of Western Mining Corporation's nickel refinery at Kwinana, Western Australia, commenced in July, 1968. Production of 15,000 tons per annum of refined nickel metal will commence ea

    Jan 1, 1969

  • AUSIMM
    A Preliminary Crustal Model of Bougainville Papua New Guinea

    Models of the genesis of existing ore oodles and targetting of exploration for new mines are greatly enhanced by an-understanding of the plate tectonic environment existing at the time of mineral

    Jan 1, 1987

  • AUSIMM
    Block Cave Evaluation

    By R J. Butcher

    Many deposits have been evaluated as potential block caves over the last 20 years due to the perceived benefit of low operating costs. However, block cave projects are typically capital intensive, wit

    May 9, 2016

  • AUSIMM
    A Multidisciplinary Approach to the Optimisation and Control of a Copper-zinc Grinding and Flotation Circuit

    By D Hatton, S Wilson, F Orrante, M Taghimohammadi, F van der Walt, N Arslan, M Westcott

    "Cayeli Bakir Isletmeleri is an underground copper-zinc mine in turkey. The ore is highly variable with feed grades ranging from 1–4 per cent copper and 1–10 per cent zinc. Due to this variability, or

    Oct 10, 2016

  • AUSIMM
    Machine learning in resource geology – why data quality is critical

    By P M. Hetherington, F A. Pym, M P. Murphy, K E. Crook

    Consultants in the mining industry have the opportunity to visit interesting deposits all over the world. Each deposit has its own set of challenges to face when it comes to defining and understanding

    Mar 22, 2022

  • AUSIMM
    Process Control Developments at Queensland Alumina

    The completion of the 3rd expansion at Queensland Alumina added 725,000 t.p.y. capacity to what was already the world's largest alumina refinery. Rated design capacity is now 2.0 million t.p.

    Jan 1, 1974

  • AUSIMM
    The Carbon Requirements of the Aluminium Industry-A Challenging to Australian Technology

    The smelting operation associated with the production of aluminium has a voracious appetite for high grade carbon materials. Within the technical parameters of the Hall-Heroult process, the reductio

    Jan 1, 1977

  • AUSIMM
    Rethinking variogram modelling

    By A Boucher, M Baudin, P Androszczuk, I Minniakhmetov, A Rigby, P Machado, M Wright, B Van Dijken

    IGO Ltd’s (IGO’s) Nova Operation (Nova), which is 160 km east-north-east of the town of Norseman in Western Australia (WA), mines and processes nickel-copper-cobalt (Ni-Cu-Co) sulfide ore from the mag

    Mar 22, 2022

  • AUSIMM
    The Hematite Ores of Mount Tom Price and Mount Whaleback, Hamersley Iron Province

    The ore deposits investigated are composed primarily of hcmatite and can be grouped into three categories depending on the amount of leaching of silica and carbonate which has occurred from the origin

    Jan 1, 1971

  • AUSIMM
    Outline of Electrical Plant Layout Mount Isa Mines Ltd

    By Edmonds G. A

    The power station went into operation in 1931, when the installed capacity was 12,500 kVA. with a loading of 4,000 kVA. In 1936 the loading increased to 6,750 kVA. which necessitated the addition of a

    Jan 1, 1953

  • AUSIMM
    The Red Rock Deposit: A Late Permian Submarine Epithermal Precious Metal System in Northeastern New South Wales

    The epithermal silver-gold Red Rock Deposit is hosted in the Late Permian inter- mediate to silicic composition Drake Volcanics of New England, N.S.W. This deposit represents one of the few low sul

    Jan 1, 1987

  • AUSIMM
    Selective Leaching of Low Grade Middlings from Lead-Zinc Flotation

    By Manlapig EV, Lawson F, Clarkson CJ

    A low grade middling sample from Mount Isa, Australia, assaying 31.7 per cent zinc, 12.9 per cent lead and 14.5 per cent iron was leached under atmospheric pressure in sulphate and sulphate-chloride

    Jan 1, 1993

  • AUSIMM
    The Alkalic Au-Cu Porphyry Province of NSW

    By V Lickfold, A J. Crawford, A J. Wilson

    A total of 12 alkalic porphyry centres of Late Ordovician age have been discovered in two mineral districts within NSW. The alkalic porphyry deposits are hosted within shoshonitic volcanic centres tha

    Jan 1, 2002

  • AUSIMM
    Ramp-up and long-term performance of the Albion Process™ plant at GeoProMining Gold Armenia

    By D Walker, A Tsvetkov, P Voigt, O Kloiber-Deane

    The GPM Gold Operation has been employing an Albion Process™ plant at its Sotk (Zod) gold mine in Armenia since 2014. Long term data from the operation is now being published for the first time. The

    Aug 29, 2018

  • AUSIMM
    Mine rockfall and rock wall failures – proven digital laser-based approach for monitoring slopes at the Kanmantoo Copper Mine

    By J Herrmann, J Richards, B Hutchison

    An extensive trial of laser-based survey and monitoring systems at Hillgrove Resources Kanmantoo Copper Mine in the Adelaide Hills, South Australia, has proved the capabilities of the system in monito

    Nov 30, 2018

  • AUSIMM
    Application of Different Drive Systems for Horizontal Mills

    By M Neurohr, B Wacker, D Mensing, C Murphy, W Kitz

    Mining operations have large power requirements. The biggest consumers of energy are the drives for the mills located in the concentrators. Assuming that the decision is made on how many mills are nee

    Jul 13, 2015

  • AUSIMM
    Optimisation of Installed Mill Power Post-installation of Secondary Crushing Circuit at Northparkes Mines

    By F Kock, Y Sulianto, T Trott, B G. Putland, D Morgan

    "Northparkes installed and commissioned a secondary crushing circuit in 2010 to debottleneck the semi-autogenous grinding (SAG) mill constrained grinding circuits. Following further improvements to th

    Oct 10, 2016

  • AUSIMM
    Carbon distribution behaviour between molten iron and CaO-Al2O3-FeOSiO2- MgO slag at 1873 K

    By G H. Park, Y J. Jun, J H. Park

    The carbon solubility of the CaO-Al2O3-FeO-SiO2-MgO slag, the main system formed in the Ruhrstahl-Heraeus (RH) vacuum degasser, was measured at 1873 K to understand the effect of slag compositions on

    Jun 19, 2024