Design And Construction Of Tower Foundations For 345kV Youngheung Marine Transmission LineBy Suk han Jang
This paper describes the tower foundation design and construction experience for the 345kV Youngheung marine transmission line, which has been in commercial operation in Korea since July, 2004. This
Jan 1, 2007
-
Design and Construction of Tunnel and Shaft PlugsBy James W. Marold
Tunnel and shaft plugs have been designed to assist in construction of new and rehabilitation of existing tunnels and shafts. Tunnel plugs have been used to provide construction access for side by sid
Jan 1, 2008
-
Design and Construction Performance of a Large Diameter Tunnel Constructed in Soft-Ground by the Stacked Drift MethodBy Paul H. Madsen, Victor S. Romero
The Tren Urbano project in Puerto Rico includes a 19 m diameter tunnel constructed by the stacked drift method, which involves installation of a pre-supported concrete arch using multiple tunnels. Geo
Jan 1, 2001
-
Design And Development Of A Low Noise Rockdrill (e23ff3f9-7637-41de-a805-68931d062e82)By N. D. L. Burger
A low noise blast hole drilling system was developed to limit the risk of noise-induced hearing impairment in mining operations. Noise- induced hearing loss has been identified as a major occupational
Jan 1, 2004
-
Design And Development Of A Novel Thickener Feedwell Using Computational Fluid Dynamics - SynopsisBy T. V. Nguyen
The feedwell performance in gravity thickeners and clarifiers relies on the efficient mixing between solid particles and flocculant to achieve effective flocculation, as well as energy dissipation of
Jan 1, 2012
-
Design And Development Of The Northeast Layback Of The Betze-Post Open PitBy Nick Rose, Robert Sharon, Mark Rantapaa
Development of the Northeast Layback of Barrick’s Betze-Post open pit commenced in June 2000 and was successfully completed to a height of 400m (1,300 ft) in January 2003. Following a brief exploratio
Jan 1, 2005
-
Design and Evaluation of the Roof Bolt Corrosion Test System in a Simulated Underground Coal Mine Environment Mining, Metallurgy and ExplorationBy Kanchan Mondal, Gopi Bylapudi, Anand Bhagwat
Corrosion of steel roof support systems can cause potential premature failure of the support, thus adversely affecting the excavation stability and rock-related safety. An in-house corrosion test syst
-
Design and Evaluation of the Roof Bolt Corrosion Test System in a Simulated Underground Coal Mine Environment Mining, Metallurgy and Exploration (7cabb148-285f-4ad0-9583-a6d360323de4)By Kanchan Mondal, Gopi Bylapudi, Anand Bhagwat
Corrosion of steel roof support systems can cause potential premature failure of the support, thus adversely affecting the excavation stability and rock-related safety. An in-house corrosion test syst
-
Design and Implementation of a Brownfield Sag Pre-Crush CircuitBy G. Castillo, G. Thies, C. Bissue
"Newmont’s Phoenix mine began gold production in 2006 and has since experienced difficulties in reaching design throughput due to variability in ore hardness. In 2010, a debottlenecking study was cond
Jan 1, 2013
-
Design And Implementation Of A Multimodal Transportation Cost Analysis Model For Domestic Lignite Supply In Turkey ? SynopsisBy E. Demir
Transportation cost is the dominant cost and accounts for almost half of the total mining cost in surface mining. Therefore, determining transportation cost is critically important for the economic fe
Jan 1, 2012
-
Design and Implementation of Advanced Automatic Control Strategy Based on Dynamic Models for High Capacity SAG MillBy Rodrigo Toro, Ivan Yutronic N
"The Copper Concentrator Plant of Compañía Minera Doña Inés de Collahuasi (CMDIC) is composed of three grinding lines, the third one being the largest. Due to the capacity feature of the third line, s
Jan 1, 2010
-
Design and Installation of Gudrun Platform Jacket PilesBy Gunhild Hennum, Tewodros Tefera, Gisle Håland, Annette Jahr
"Abstract The Gudrun field is located west of Stavanger in the North Sea at water depth of 109 m. A jacket substructure was selected to support the topside and was installed in 2011. The jacket shall
Jan 1, 2014
-
Design And Installation Of Pretensioned Spun Concrete Piles To Support A Large Diameter SewerBy Naresh Koirala
The Greater Vancouver Regional District completed installation of a 2.5 Km long, 2400 mm diameter concrete sewer in Delta, British Columbia in 2000. The sewer traverses through area of peat and soft
Jan 1, 2004
-
Design And Instrumentation Results Of A Reinforcement Concrete Piled Raft Supporting 2500 Ton Oil Storage Tank On Very Soft Alluvium DepositsBy Shaw-Shong Liew
This paper presents the design concept using floating piles to support 2500Ton oil storage tanks on a very soft alluvial clayey soil of about 40m thick in Riau Province of Sumatra, Indonesia. The floa
Jan 1, 2002
-
Design and Operation of a Counter Current Gas Scrubbing SystemFor many years the scrubbing of roaster gas carrying sulphur dioxide has been carried out at the plant of the Electrolytic Zinc Co. of Australasia Ltd. at Risdon, Tasmania, using long horizontal tubes
Jan 1, 1949
-
Design and Operation of a Future MillBy D. E. Pickett, J. A. Roland Faucher
"INTRODUCTIONMineral processing is undergoing growth and change at a rapid rate. The modern flotation process was discovered only in the mid-twenties, and uranium leaching in the mid-fifties. The grow
Jan 1, 1979
-
Design and Operation of the Key Lake Uranium MillBy M. Neven, R. A. Steane, E. Lam
"The Key Lake uranium mill is located in Northern Saskatchewan. It treats a high grade, complex uranium and metal sulphide ore. The plant and process are in many respects unique, because commercial tr
Jan 1, 1986
-
Design and Positive Financial Impact of Crush Pillars on Mechanized Deep-Level Mining at South Deep Gold MineBy B. P. Watson
Crush pillars have been incorporated into a mechanized, low-profile trackless system at South Deep Gold Mine. These pillars had to be designed to fail near the face and to ensure that pillar failure i
Jan 1, 2014
-
Design And Preliminary Testing Of Low-Energy Planetary Excavator - Preprint 09-134Development of a permanent human base on the Moon for exploration requires a self sustaining system. This entails production and processing of limited amounts of raw material on the Moon. Any mining a
Jan 1, 2009
-
Design And Start Up Of The Cortez Gold Mines Pipeline MillBy R. N. Powell
The Pipeline ore body was discovered in March 1991. The construction of the new mine and mill did not start until early March of 1996. Upon completion of permitting and corporate project approval, the