    RISKGATE« - A Case Study in Application to Fires on Mobile Plant

    By J Harris, P Kirsch, D Cliff, M Spinks, S Goater, D Sprott

    Fires are a common and recurrent unwanted event in the operation of open pit mines. In most cases, the causes of events such as fires are already æknownÆ but are either overlooked or not fully address

    Sep 18, 2012

  • AUSIMM
    An integrated approach to mine planning – building the integrated planning model at Tropicana gold mine

    By M Kent, D Elder, J Woodward, R Edwards, B Catto

    At Tropicana gold mine (TGM), mine planning is completed from ‘one source of truth’ known as the Integrated Planning Model (IPM). The IPM is a block model which forms a core component of the TGM Mine

    Sep 20, 2017

  • AUSIMM
    Open Pit Production Scheduling Optimisation - Why the Mining Industry Needs a New Phase Design Approach

    The long-term production schedule of open pit mines that maximises the net present value (NPV) of a given project relies on the proper design of phases (pushbacks) within the ultimate pit limits. Ther

    Dec 6, 2010

  • AUSIMM
    Gas Evolution Trends for Coal from Two Different Areas at Clarence Colliery

    By J Sargeant, T Levi, J Theiler, B Beamish

    Two coal samples (810 Panel and Area 900) collected from Clarence Colliery have been tested under a controlled heating procedure to evaluate the gas evolution trends corresponding to increasing temper

    Aug 31, 2015

  • AUSIMM
    Precision Analysis of Iron Ore Sampling, Preparation and Measurement -Overcoming Deficiencies in the Current Standard ISO 3085

    At Cliffs Natural Resources Ltd (CNR) crushing and shipping sample stations, precisions are estimated for the sampling, preparation and measurement stages of iron ore sampling in accordance with ISO 3

    Mar 1, 2010

  • AUSIMM
    The application of critical chain project management to sublevel open stoping at Olympic Dam

    By J Light

    Since 2019, the mine planning team at Olympic Dam has been establishing and maturing a shift from deterministic to probabilistic scheduling techniques. This paper outlines this journey undertaken by t

    Mar 29, 2023

  • AUSIMM
    Mine to Mill Reconciliation - Three Case Studies

    By J T. Carswell, N A. Schofield

    Fluctuations in periodic reconciliations between the mine and the mill are an expected and common experience in mining and processing operations. These fluctuations are caused in part by errors in the

    Nov 20, 2012

  • AUSIMM
    Seam Gas Drainage Experiments in some Colleries of B.H.P.

    By Hargraves AJ

    Pre-drainage experiments have been conduct- ed at Appin, Cook, John Darling, Leichhardt, Macquarie, Metropolitan and Moura No. 2 Collieries. Appin (550 m deep) experiences particular gas problems i

    Jan 1, 1982

  • AUSIMM
    A day in the life of a mineworker in 2045

    By G McCullough, J Bassan, d P. Knights, C T. Farrelly

    By 2045, carbon-neutral mines will be economically producing products that are vital for the world’s transition to renewable energy. After overcoming significant technical challenges (and the investme

    Sep 1, 2024

  • AUSIMM
    Environmental Auditing as a Driver for Continuous Improvement in Environmental Performance (ede55e7e-c054-4fc6-ae90-dd762e66d692)

    Continuous improvement in environmental management assists in the achievement of sustainability goals for the mining and processing of minerals. The use of regular internal environmental audits (score

    Jan 1, 2004

  • AUSIMM
    Now, this is the Time for Mining Companies to Choose - Real Option Valuation or Discount Cash Flow

    By S Shafiee, N Abbate

    The evaluation of mining projects requires a methodology that will give flexibility and manage the existing uncertainty within the projects. The discount cash flow (DCF) and other traditional evaluati

    May 24, 2012

  • AUSIMM
    Bulk carrier vessel tracking automation – the Dalrymple Bay use case

    By W Russell, P Wighton, J Franke

    Recent advances in ruggedised industrial control system technology and architecture in combination with latest technologies in the fast-evolving 3D LiDAR sensor sector becoming available have enabled

    Nov 8, 2021

  • AUSIMM
    Adapting to Geotechnical Change – a Case Study of the Carina Open Pit Mine

    By R Jaine, D Strang, M Fowler

    "This paper presents a case study demonstrating active geotechnical pit slope management at the now completed Carina Iron Ore Project operated by Mineral Resources Ltd (MRL). The site is located 105 k

    Nov 15, 2016

  • AUSIMM
    The Importance of Collaboration between Designers and Contractors in Implementing a Design in Challenging Conditions

    By V Gumba, S Narendranathan, C Barker, R D. H Thomas, G P. Bungard

    This paper presents the positive outcomes on an EPCM project, which was undertaken in a challenging environment, whereby the design team had to generate a design with a number of stringent serviceabil

    Sep 18, 2012

  • AUSIMM
    Demonstrating Efficiency Gains from Installing Truck Turntables at Crushers

    By P A. Grossman, J H. Rubinstein, M Brazil

    The installation of truck turntables at above-ground crushers has the potential to yield gains in efficiency and productivity by eliminating the need for the trucks to turn around and reverse up to th

    Nov 24, 2014

  • AUSIMM
    In Situ X-ray and Neutron Diffraction Studies of Silico-Ferrite of Calcium and Aluminium Iron Ore Sinter Phase Formation

    By M I. Pownceby, N A. S Webster, A J. Studer, I C. Madsen, J A. Kimpton, M J. Fisher-White, L Lu

    In situ synchrotron X-ray and in situ neutron diffraction-based experimentation have been implemented to characterise the formation of the complex calcium ferrite iron ore sinter bonding phases silico

    Aug 12, 2013

  • AUSIMM
    Setting new standards at Kanmantoo – effective grade control procedures

    By M Reid, H Arbon

    Hillgrove Resources (HGO) commenced open pit mining in 2011 and from 2011 to 2016 the geology team experienced a consistent negative reconciliation between grade control estimated copper (Cu) grade an

    Sep 20, 2017

  • AUSIMM
    The Impact of Fluidised-bed Flotation for Treating Coarse Sulfides

    By H Thanasekaran, M J. Mankosa, J N. Kohmuench, G H. Luttrell

    "Fluidised-bed flotation has been demonstrated over the last 16 years as an effective method for improving the flotation recovery of coarse particles. This technology has been successfully deployed in

    Oct 10, 2016

  • AUSIMM
    Distributed Collaborative Immersive Virtual Reality Framework for Future Mine Scenarios

    By T Bednarz

    The present work proposes a distributed collaborative immersive virtual reality framework for prospective applications in the mining industry. A human-centered approach is described, with people being

    Nov 22, 2011

  • AUSIMM
    Nova-Bollinger unfolding versus DA estimate

    By P M. Hetherington, M P. Murphy, K E. Crook, F Pym

    Resource characterisation is critical for informed decisions in both strategic and operational space. The sources of information for resource characterisation are limited by: direct measurement of res

    Mar 22, 2022