Organization
Organization
  • DFI
    Real-Time Anchor Testing and Data Management

    By Bora Okumusoglu, Devon K. V. Mothersille

    "AnchorTest is an innovative software package, specifically developed for tablets, that permits ground anchor test data assessment and management in real time. The solution has two components: a front

    Jan 1, 2017

  • DFI
    Session 24 "Compaction Grouting and Consensus Guide"

    By Richard Berry

    The spacing of grout injections is typically about 2 to 2 V½ meters if the purpose of the grouting is densification of the in-situ soils. Hole spacing will vary with the in-situ soil properties and th

    Feb 10, 2003

  • DFI
    Innovative SSP Design and Construction for a Complex Soil Remediation Project

    By Matthew C. Janes, Mark C. Spence

    "A former coal gasification site next to Rock Bay in Victoria, BC, Canada required a barrier to permit dewatering and excavation of the bay and surrounding property. The adjacent property owners had s

    Jan 1, 2016

  • DFI
    Wick Drain Guide Specification (Method)

    "1.0 DESCRIPTIONThis work consists of furnishing all necessary labor, equipment, and materials to install prefabricated vertical (wick) drains in the ground in accordance with the Plans and as specifi

    Jan 1, 2014

  • DFI
    Newest Developments in Quality Control and Soil Mixing for Actual and Future Demands

    By Franz-Werner Gerressen

    "New developments are required day by day. On the one hand site to improve the actual situation, on the other hand site to create the future and to ensure that future demands can be fulfilled. This re

    Jan 1, 1900

  • DFI
    Screening Tool for Impact Hammer Selection

    By Gerald Verbeek, David Tara

    "When selecting an impact hammer to drive a particular pile, the decision is often based on local experience. In those cases, the contractor falls back on previous experience or draws on the experienc

    Jan 1, 2017

  • DFI
    Innovation In Spliced Prestressed Piles: Testing And Use Of The Emeca Pile Splice

    By John C. Ryan

    The Emeca Pile Splice, an innovative mechanical prestressed concrete pile splice, is the first robotically welded splice to be fabricated in the United States. An analytical and experimental study wa

    Jan 1, 2010

  • DFI
    Physical Modeling and Development of Design Criteria for Maintainable Drains for Earth Retention Systems

    By J. Erik Loehr, Andrew Z. Boeckmann

    "Poor drainage is a common cause of poor performance of earth retention systems, resulting in burdensome serviceability problems that can progress to outright failure of the retention system if not ad

    Jan 1, 2016

  • DFI
    Sustainability and Consideration of the Re-Use of Foundations for the Hurricane Deck Bridge

    By Timothy C. Siegel, Paul J. Axtell

    The Missouri Department of Transportation (MoDOT) recently replaced the Hurricane Deck Bridge that carries Highway 5 traffic across the Osage Arm of the Lake of the Ozarks in Camden County, Missouri.

    Jan 1, 2017

  • DFI
    Risk Management For Dam Rehabilitation Projects

    By Dave Paul

    Dam rehabilitation involves a range of design, construction, and operation risks, some of which are not encountered in new dam construction. These risks can have significant impact on project schedule

  • DFI
    Bluestone Dam Safety Assurance Program: An OPA Runner Up

    By Jeff Hopple

    "Bluestone Dam in Hinton, W.Va., along the New River, is owned and operated by the U.S. Army Corps of Engineers (USACE). Completed in 1949, the dam is 165 ft (50 m) tall, 2,048 ft (624 m) wide, and en

    Jan 1, 2014

  • DFI
    Design and Construction of High-Capacity Rock Anchors for the Willow Island Hydroelectric Project

    By James M. Tantalla, Roderic A. Ellman, W. Allen Marr, Scott R. Bamford

    "Construction of the powerhouse for the Willow Island Hydroelectric Project required a 100-ft deep excavation inside the limits of a cofferdam and embankment-seepage cut-off wall through soil and rock

    Jan 1, 2017

  • DFI
    Doyle Drive – Extreme Pile Installation

    By Peter Faust

    "The south access road to San Francisco’s Golden Gate Bridge, known as Doyle Drive or Presidio Parkway, needs to be replaced. Built in 1936, it is the primary highway and transit linkage through San F

    Jan 1, 2012

  • DFI
    Risk Management Techniques to Avoid Litigation

    By Kevin Cunningham

    "Litigation resulting from neighboring structures with settlement and/or lateral movement or improper pile design and faulty soils engineering analysis, are a multi-faceted opportunity for law firms.

    Jan 1, 2015

  • DFI
    Trench Cutter - The Multi Purpose Solution

    By Alexander Blatt, Franz-Werner Gerressen

    Power Point Presetation at DFI 2022

    Sep 1, 2022

  • DFI
    Secant Pile Top-Down Construction for a Drainage Channel in Puerto Rico: An OPA Finalist

    By Bill Shea, Gordon King

    "For a drainage channel built in San Juan, Puerto Rico, a value engineering (VE) proposal incorporating a secant pile top-down approach saved time and facilitated construction work on the larger flood

    Jan 1, 2012

  • DFI
    Recent Advances in Quiet & Vibration-less Steel Pile Installation

    By R. K. Filip

    "Steel bearing piles have long been used to carry high compressive, tensile and lateral loads. Such piles are most commonly tubular or ""H"" profile and are typically installed using percussive techni

    Jan 1, 2005

  • DFI
    Energy Geostructures: Analysis from Research and Systems Installed Around the World

    By Tony Amis, Marco Barla, Alice Di Donna

    "Energy geostructures are becoming an increasingly popular solution around the world for Developers looking to reduce CO2 and system running costs. Energy geostructures are geotechnical structures tha

    Jan 1, 2017

  • DFI
    Foundations Of Self Drilling Micropiles In 4G And 5G Network Telecom Masts In India

    By Annika Gram, Teddy Johansson, Lutfi Ay

    Micropiles transfer tension or compression forces as well as cyclic loads into the ground via skin friction. The Self Drilling Micropiles (SDM) can be utilized for permanent applications. The hollow b

    Nov 1, 2022

  • DFI
    Innovative Non Encroaching Retaining Wall

    By Dino Kartofilis, Rick Deschamps, Giovanni (John) Bonita

    "Anew condominium complex in Arlington, Va., presented some formidable constraints. One was the requirement for a permanent retaining wall to support a 48.5-ft (15-m) cut and an existing 16- story bui