A Novel Ground Control Program at Plateau Mining CompanyBy Hamid Maleki
A novel ground control program has been developed at Plateau Mining Company through five years of geotechnical investigations. The study was initiated to determine the causes for roof stability proble
Jan 1, 1987
-
The Formation And Effects Of Transient Abutment Stress During Nonuniform Face AdvanceBy George J. Karabin
Since the inception of a qualitative pressure arch theory by Haak4 in 1911, much work has been done in an effort to apply this concept to underground mining. It has been used in both longwall and room
Jan 1, 1982
-
Roof Bolting Application In Longwall Mining In Indonesia And JapanBy Herryal Anwar
The application of roof bolting technology to control the stability of roadways in coal mining within weak strata or under high ground pressure has improved progressively. One of several factors that
Jan 1, 1999
-
Analysis Of Longwell Shields And Their Interaction With Surrounding Strata In A Deep Coal MineBy Duk-Won Park
A vast majority of the operating longwall sections use shield-type face supports to provide ground control in the United States. As a co-operative research program between the University of Alabama (U
Jan 1, 1992
-
Elasto-Plastic Finite Element Structural Stability Analysis Of Room And Pillar Mine Workings (1726bb0c-5e63-4f04-a636-538432c37ec9)By S. Bensehamdi
An advanced elasto-plastic finite element model adopting a modified Von Mises yielding criterion was used to simulate progressive failure of the rock strata surrounding a room and pillar mine structur
Jan 1, 1992
-
Extended Cut Out Distances In Continuous Miner Sections In South African CollieriesBy Ismet Canbulat
The cut out distance in the continuous miner sections in South African collieries is limited to 12 m. However, this distance can be extended to 24 m by the permission of the Department of Mineral and
Jan 1, 2000
-
The Use of Pneumatic Stowing in Germany Considering Subsidence AspectsBy Axel Preusse
Stowing or waste fill is common in the German mining industry since the beginning of mining activities, With increasing mechanization, flat and gently inclined seams (0 -- 18) were mined. These mines
Jan 1, 2002
-
Evaluation of Instrumented Cable and Rebar Bolts as Ground Support at a Trona Mine (958ba3b7-4ed1-4b81-9815-5e4d6ebd9ea2)By Lewis A. Martin
Instrumented cable bolts developed at the Spokane Research Laboratory of the National Institute for Occupational Safety and Health were used in conjunction with existing ground control systems to moni
Jan 1, 2001
-
Characterization Of Structural Integrity And Stress State Via Seismic Methods: A Case StudyBy Erik C. Westman
The objective of this Bureau of Mines study is to determine the structural integrity and stress state of coal structure using seismic techniques. Bureau personnel conducted seismic transmission and re
Jan 1, 1993
-
Roof Bolting for Long-Term Entries in Underground Coal MinesBy Peter Zhang
As simpler and easier reserves are exploited to depletion, underground coal mining continues in more complex geologic settings and conditions. Roof bolting for long-term entry stability is always a ch
Jan 1, 2011
-
Load And Convergence Measurements In Longwall Faces And Design Guidelines For Face-Support SystemsBy Reha Ozel
The stability in longwall faces depends on the interaction beman the roof strata, face supports and floor strata. The load distribution on the other hand, depends upon relative stiffness of the three
Jan 1, 1990
-
An Investigation of the Causes of Cutter Roof Failure in a Central Pennsylvania Coal Mine: A Case StudyBy John L. Hill
Cutter roof failure is a specific type of ground control problem which frequently results in massive roof failure. It is a cannon occurrence in coal mines of the Northern Appalachian Coal Sasin, causi
Jan 1, 1984
-
The Design of Room and Pillar Mining Systems in the UKBy Graham Daws
State of the Art Room and Pillar mining techniques have been employed at two coal mines in the UK in the last two years. This paper describes the design of pillars and rockbolted support systems for R
Jan 1, 1998
-
Stooping Low Safety Factor Pillars At Goedehoop CollieryBy Gift Makusha
The Witbank Coalfield in South Africa contains up to five economically viable coal seams. These seams have been mined continuously for over 100 years and the reserve in now becoming depleted. The norm
Jan 1, 2003
-
Resin Annulus Size Effects On Rebar Bolt Pull Strength And Resin Loss To Fractured RockBy Al Campoli
One of the critical variables affecting resin bolt performance is the size of the resin annulus, defined as the difference between the hole and bolt radius. The vast majority of the millions of resin
Jan 1, 1999
-
Control Technology For Roof Drill OperatorsBy Bob Thomas
The roof drill operator productivity can be enhanced by the introduction of control technology The operators control station can be improved by considering human factors such as handle forces and cont
Jan 1, 1999
-
Variation In The Load Transfer Of Fully Encapsulated RockboltsBy Paul Hagan
A diverse range of rockbolt designs and resin anchors are available for use in underground mines. Despite their wide spread use, the factors that affect the performance a rockbolt is not fully underst
Jan 1, 2004
-
Longwall Surface Subsidence Prediction Through Numerical ModellingBy Noor Mohammad
Comprehensive numerical modelling of the subsidence associated with longwall mining in UK Coal Measures strata has been conducted and validated against UK data. The Rock Mass Classification System (RM
Jan 1, 1997
-
Influence Of The Sloping Of Ground Surfaces On Mine Subsidence (165d3ebb-e4c1-4bc8-a5e4-409b4e24155c)By D. M. Shu
A two-dimensional finite element modelling technique is applied to predict the subsidence movements on a sloping ground surface above a completely mined panel. The modelling is carried out for the sur
Jan 1, 1992
-
Pressure Distribution Of 2-Leg Shield Supports (fb20894a-e0d3-49e8-b331-69176f4a54a3)By Rao Pothini
Measurement of pressure distribution under the base plate of the Hemscheidt 2-leg 800-ton shield was performed underground for two shifts using 12 pressure cells installed in two rows, one each under