Machine Design Parameters For High Seam Truss Bolting ApplicationsBy G. Bucelluni
An essential element of truss bolt installation requires machines to angle a hole in the top of approximately 39° to 45° from its vertical axis. Parameter which inherently effect the drill position ar
Jan 1, 1982
-
The Directional Drill Monitor For Long Hole Gas Drainage In Coal Mines (d6b87c76-5ad8-4cc5-b4ae-23b79c52c32b)By G. Skybey
The Directional Drill Monitor (DDM) is an advanced instrument for real time in hole surveying. It was developed by Du Pont (Australia) to suit Australian gassy coal mining conditions. The instrumen
Jan 1, 1992
-
The Requirements of a Database to Store Geotechnical Data to Assist in Roof Support DesignBy Ross Seedaman
The specification of roof support needs to consider rock strength, imposed ground stresses, and more importantly the bedding and joint structure of the immediate roof rocks. A database structure has b
Jan 1, 2003
-
Tailgate Support Practice In U.S. Longwall Mines - A SurveyBy S. S. Peng
To acquire knowledge on the general trend of primary and supplemental supports used in tailgates of US longwall mines a survey of 76 mines with 86 longwall panels was carried out in the summer of 1993
Jan 1, 1994
-
Pillarless Longwall Mining For Multiple SeamsBy Victor V. Nazimko
Longwall mining technology without interpanel pillars is feasible from a geomechanical point of view. A set of pillarless longwall layouts are proposed including tailentry pillar recovery, headentry p
Jan 1, 1994
-
Topography and Coal Seam Initial Stress Estimation: a Sensitivity StudyBy Jeffrey K. Whyatt
Estimation of the initial vertical stress carried in a coal seam is an important first step in virtually all methods of evaluating the required size of pillars in coal mines. Such estimates are a triv
Jan 1, 2011
-
Localized Horizontal Stress And Its Effect On Ground ControlBy John Stankus
Regional high horizontal stress has long been recognized as an important factor affecting roof stability However, localized high horizontal stress, although causing many ground control problems, has n
Jan 1, 1999
-
Visual Recognition of the Load of Roof-Bolts by an IndicatorBy Joachim Leonhardt
Hundreds ofbolt-indicators were already used successfully in the German deep hard coal-mines to increase the safety and economy. The bolt-indicator offers the simple possibility to show roof-bolt (anc
Jan 1, 2001
-
Non-Destructive Testing Method for Determining the Characteristic Length and Initial Axial Bolt Load and Its ApplicationBy Houquan Zhang, Yu Wu, Yanlong Chen, Zhenfu Luo, Aihong Lu
"A non-destructive detection scheme for bolt installation quality was designed by adopting the method of non-destructive detection on bolt installation quality. Based on the field measurements, a rand
Jan 1, 2016
-
The Duncan Method of Partial Pillar Extraction at Tasman MineBy Kent D. Mctyer
Mining commenced at Tasman Mine in late 2006. The current method of mining is bord and pillar using continuous minerbolters and shuttle cars for first workings and secondary extraction using mobile ro
Jan 1, 2011
-
Study on Top-Coal Loss and the Optimum Drawing Interval of Longwall Top-Coal Caving MiningBy Qiang Fu
ABSTRACT This paper aims to identify the main issues concerning top-coal loss and the optimum drawing interval of LTCC (Longwall Top-coal Caving) mining by underground tests and DEM (Distinct Element
Jan 1, 2002
-
A Study On Application Of Comprehensive Rock Mechanical Properties And Geological Characteristics In Coal MinesBy Xu Linsheng
Datong coal Mine suffers from delays and sudden caving of its massive competent conglomerate roof. Detailed geological studies of the nature of pebbles and matrix of the conglomerate and its sparse be
Jan 1, 1992
-
Analysis Of The Seam Inclination Effect On Roof StabilityBy Hanjie Chen
Mining experiences have shown that in a pitching seam, roof behavior is significantly different from a flat seam. Uphill mining usually experiences more roof problems than downhill mining. Based on a
Jan 1, 2000
-
lnterpanel Barriers for Deep Western U.S. Longwall MiningBy Leo Gilbride
Western U.S. longwall operators face increasing challenges with optimizing ground control and productivity as mines reach greater depths and coal bursting hazards increase. Some western U.S. mines, ma
Jan 1, 2004
-
Proposed Criteria for Assessing Subsidence Damage to Surface StructuresBy Swapan Bhattacharya
Section 516 of Public Law (PL) 95-87, commonly known as the Surface Mining Control and Reclamation Act of 1977 (SMCRA), requires that underground coal mine operators must 'adopt measures consiste
Jan 1, 1984
-
Cyprus Shoshone Tailgate Roof Control: Case StudyBy Andrew P. Schissler
Cyprus Shoshone is an underground coal mine in southern Wyoming owned by Cyprus Coal Company, a subsidiary of Cyprus Minerals Company. To date, seven longwall panels have been extracted from the pitch
Jan 1, 1993
-
Progression of Longwall Gateroad Support as Conditions Change at Lodestar Energy's Baker MineBy David Miller
Longwall gateroad support can be supplied by a variety of methods. The system of support also needs to be flexible as conditions change. This is especially true in the complex geological conditions of
Jan 1, 1998
-
Prognosis And Control Of Mining Induced Surface Subsidence And Ground Movements In The German Hardcoal Sector, Case StudiesBy Axel Preusse
This paper shows basic considerations about the prognosis and prediction of surface subsidence and other ground movements in the German hardcoal industry. The following case studies describe experienc
Jan 1, 2000
-
Surface Subsidence Due to the Combined Effects of Underground Coal Mining and Groundwater WithdrawalBy Shu Cheng
Abstract: Based on the consolidation theory of soil dewatering and land subsidence prediction methods in soil mechanics, preliminary analysis of surface subsidence and movement due to groundwater with
Jan 1, 2002
-
An Alternative for More Productive Rib Bolting in Underground Mining ApplicationsBy Joe E. Bryan, John P. McDonnell
"Underground mine rib stability is an ongoing safety issue in all mining applications. Rib-related accidents present at least as many problems as roof-related ground control. Underground coal mine rib
Jan 1, 2015