Deign of Support System for Mining Tunnels in Carboniferous Rock ConditionsBy B. N. Whittaker
The paper briefly reviews the type of support and stability problems encountered in mining tunnels in U.K. Carboniferous rock conditions, particularly the Coal Measures where almost all such tunnels a
Jan 1, 1987
-
Effect of High Horizontal Stress on Coal Mine Entry Intersection StabilityBy K. Hanna
This manuscript describes an extensive ground control study at the Inland Steel No. 2 Mine near McLeansboro, IL, conducted by the U.S. Department of the Interior's Bureau of Mines (USEM) in coope
Jan 1, 1986
-
Roof Monitoring In Limestone Mines-Experience With The Roof Monitoring Safety System (RMSS)By Thomas E. Marshall
During the past few years, the Pittsburgh Research Laboratory of the National Institute for Occupational Safety and Health (NIOSH) examined and characterized conditions at a majority of the undergroun
Jan 1, 2000
-
Effect Of Face Advance Rates On The Characteristics Of Subsidence Processes Associated With U.S. And German Longwall Mining OperationsBy Yi Luo
Regulating the face advance rate in longwall mining operation can be an effective means to reduce the disturbance potential to surface structures associated with a longwall subsidence process. However
Jan 1, 2001
-
Observations of Impacts to Pennsylvania's Interstate Highways by Longwall MiningBy Anthony Iannacchionc, Jessica Benner, Harold Miller, Megan Witkowski
"Longwall bituminous coal mining has been practiced in Pennsylvania since the 1970""s. Hundreds of longwall panels have been mined during the last 40 years but only 24 have actually undermined Pennsyl
Jan 1, 2010
-
Monitoring For The Evaluation Of The Stability Of Underground OpeningsBy P. K. Kaiser
The purpose of deformation monitoring for the evaluation of the stability of underground openings is reviewed briefly and some results from laboratory tests of small tunnels are presented. The ground
Jan 1, 1981
-
Time Dependent Strength Of Coal Strata For Long-Term Pillar StabilityBy Z. T. Bieniawski
A major study was performed on determination of long term strength of coal strata directed to the design of coal pillars to ensure their stability beyond the life-time of a mine. Based on field invest
Jan 1, 1994
-
Development Of A Remote Reading Dual-Height Telltale System For Monitoring Mine Roof DeformationBy David Bigby
A remote reading dual height telltale system has been developed to provide mine management with early warning of impending roof failure. This system is a logical development from the visual dual heigh
Jan 1, 2001
-
Longwall Pace Bursts and Inadequate Caving: A Came StudyBy K. Y. Haramy
Deep coal mines with strong roof and floor strata frequently encounter face and rib bursts. The burst problem becomes more severe with increased depth. While the exact causes of bursts are often diffi
Jan 1, 1987
-
The Influence Of Stream Valleys On Coal Mine Ground ControlBy John L. Hill
Over 50 mines of the Appalachian and Illinois Basins are presently experiencing poor ground conditions believed to be caused by overlying stream valleys. The Bureau of Mines is conducting research int
Jan 1, 1988
-
Controlled Thrust And Torque Placement Of Mechanical Anchor Bolts And Their Relationship To Improved Roof ControlBy Anil Mahyera
Under contract to the Bureau of Mines, a roofbolting machine has been developed which will: control torque on the bolthead to within 4 percent of a set point, control thrust to a low level (150 lbf),
Jan 1, 1981
-
Implementation and Evaluation of Roof Bolting in MICARE Mine IIBy Gustavo Herrera Rico
As part of a general effort to increase safety, efficiency, and profitability of its mining operations, MICARE personnel with the support of NorWest Mine Services, Inc. determined that the key to impr
Jan 1, 1997
-
Premature Rock Bolt Failure Through Stress Corrosion Cracking (SCC)By Bruce Hebblewhite
An ACARP-funded industry research project in Australia recently investigated the problem of premature rock bolt failures in underground coal mines. The project carried out limited sampling from 9 diff
Jan 1, 2003
-
International Experience with Longwall Mining into Pre-driven Rooms (7f55d3bb-2127-4b96-860d-e3684bbd8397)By David Oyler
Unusual circumstances may require that a longwall retreat into or through a previously driven room. The operation can be completed successfully, but there have been a number of spectacular failures wh
Jan 1, 1998
-
Anchorage Pull Testing for Fully Grouted Roof BoltsBy Chris Mark
Fully-grouted roof bolts comprise more than 80% of the primary roof supports used in U.S. coal mines. However, nearly 1,500 MSHA reportable, non-injury roof falls occur each year, and most of these ar
Jan 1, 2002
-
Stooping Low Safety Factor Pillars at Goedehoop Colliery - 12 Months LaterBy Gift Makusha
Pre-feasibility work at Goedehoop Colliery indicated that stooping of the undersized pillars could be undertaken safely and economically. In light of the findings a decision was taken in may 2003 to u
Jan 1, 2004
-
Behavioral Aspects of Roof/Rib Injuries--Implications for Training Utilizing Stereoscopic PhotographyBy Edward A. Barrett
A significant number of injuries resulting from fa118 of roof and rib may be avoided by modifying the reactive behavior of miners as they encounter potentially hazardous ground conditions. In 1984-85,
Jan 1, 1986
-
Design Of The Ventilation Shaft In The South Link Railway Tunnel Construction, TaiwanBy Jay Keng
During the construction of shaft on the fractured and weak rock strata, the stability of construction plays an important role. This study includes earth stress estimation, support method, and stabi
Jan 1, 1988
-
Flexibolt Flexible Roof Bolts: A New Concept For Strata ControlA high strength steel strand bolt has been developed by Barrett, Fuller & Partners as a replacement for conventional rigid bars for primary roof support in coal mines. It is based on a 23mm diameter m
Jan 1, 1993
-
Stress Analysis and Support Design for Longwall Mine-Through Entries (A Case Study)By Keith Heasley
An eastern longwall mine was required to mine through a set of three entries located midway down the length of a panel. Of course, the mine desired to design a successful support system for the mine-t
Jan 1, 2003