Systematic Evaluation of Foundation Reuse for a Metro StationBy Haoran Zhang, Chu Ho
A recent design-build project in New York involved various degrees of additions and improvements to four existing transit stations. Reuse of the existing foundations was considered a more sustainable
Sep 8, 2021
-
Geotechnical Challenges of Pile Driving in a Marginally Stable Slope Terminal 46 Apron Upgrade, Port Of Seattle, WA (18615664-0169-4e91-aa2b-8ec5994bb0a0)By Monique Nykamp
"INTRODUCTIONTerminal 46 is located just south of downtown Seattle, and is one of the Port of Seattle’s busiest container terminals. The Terminal 46 Redevelopment Project was undertaken to replace the
Jan 1, 2007
-
Geotechnical Challenges of Pile Driving in a Marginally Stable Slope TERMINAL 46 APRON UPGRADE, PORT OF SEATTLE, WABy Monique Nykamp
"INTRODUCTIONTerminal 46 is located just south of downtown Seattle, and is one of the Port of Seattle’s busiest container terminals. The Terminal 46 Redevelopment Project was undertaken to replace the
Jan 1, 2007
-
New CIGMAT Downhole Penetrometer (DHP-CIGMAT) for Use During Drilled Shaft Construction (7493fc91-7396-4eac-bed2-0406570252cc)By Omer F. Usluogullari, C. Vipulanandan
"It is critical to monitor the ground conditions during excavation and drilling of boreholes during construction to identify possible changes in the soil and rock formations. Drilled shafts are increa
Jan 1, 2017
-
Deep Mixing Core Data from LPV 111By Donald Bruce, Alex Reeb, George Filz, Wesley Schmutzler, Mitsuo Nozu
"One million seven-hundred thousand cubic yards of deep mixing were installed to support an elevation raise of an earthen levee known as LPV 111, which is located in east New Orleans. The deep mixing
Jan 1, 2015
-
Evaluation of Existing T-Z Models for Caliche Based on Numerical Analysis of Bi-Directional Load Tests Using NVShaftBy Ramin Motamed, Fahim M. Bhuiyan, Raj V. Siddharthan, Joseph Toth
The difficulty in material characterization and the erratic response of cemented soil layers, such as caliche in the Las Vegas valley, creates challenges for practicing engineers to reliably predict t
Sep 8, 2021
-
120 Years of Caisson Foundations in ChicagoBy Robert E. Schock, Eric J. Risberg
"Less than 20,000 years ago, the last of the glaciers retreated from the Chicago region. They left behind sheets of glacial clay till underlain by dense, over-consolidated till (“hardpan”) below which
Jan 1, 2016
-
Designing Piles for Seismic EventsBy H G. Poulos
"This paper sets out a simplified approach by which the practical foundation designer can undertake the relevant calculations to satisfy the requirements for deep foundation design in seismic areas. T
Jan 1, 1900
-
The Use of Rigid Inclusions to Support Large SpansBy Michael Shedlosky, Sonia Sorabella Swift, Nina Carney, David Tarasovic
Rigid inclusions were used to support roadway fills and mechanically stabilized earth (MSE) walls for the South Capitol Street Corridor project. The first phase of this two-phase, nearly $1 billion pr
Jan 1, 2019
-
Monitoring Auger Cast In Place Pile Construction And Testing In Hard ClayBy C. Vipulanandan
Installation procedure and the quality of the material used in the construction have significant effects on the behavior of the Auger Cast in Place (ACIP) piles. In this study, Installation and curing
-
Field Test of Braced Excavation Supported with Rows of Dry Deep Mixing ColumnsBy Stefan Larsson, Sadek Baker, Razvan Ignat
"This paper describes the execution of two full-scale field tests where a braced steel sheet pile wall interacting with rows of overlapping dry deep mixing columns was first excavated and then loaded
Jan 1, 2015
-
Efficient Torque-Installed Pile Use in Southern CaliforniaBy Jason Buenker, Molly Winston
Torque-installed piles are gaining popularity in Southern California as the go-to deep foundation element for small- to medium-capacity loads in urban environments. The torque-installed pile is a disp
Jan 1, 2019
-
The Design of Partial Depth Cement Deep Mixing (CDM) Foundation for an Immersed TunnelBy J. S. Lee, R. K. Massarsch
"A 3.2 km long immersed road tunnel forms part of the Busan-Geoje Fixed Link in South Korea, which connects Korea's second largest city Busan, with the island of Geoje. To ensure the water tightness o
Jan 1, 2015
-
Case Studies Of Driven Tubular Steel Piles In Soils And Basalt On Woolgoolga To Ballina Pacific Highway UpgradeBy Henry Zhang
This paper presents two case studies of large diameter driven tubular steel piles for the ongoing Woolgoolga to Ballina Pacific Highway upgrade (W2B). This project forms part of Australia’s largest re
Nov 1, 2022
-
“Special Application Of Micro-Piles” For The Construction Of A Bridge Well FoundationBy Nagarajkumar BV
Pavai-and TeampT JV started working on the project T49A, Sumbar J & K State as part of slope and earth stabilization for ongoing Banihal - Katra Railway Connection Project. This project has several tu
Nov 1, 2022
-
A Discussion Of Inconsistencies Between Lrfd And Asd Methods For Geostructural Design Applications Of The Aashto Bridge Design SpecificationsBy Dimitrios Polantzas P. E., Collin E. Sweeney E. I. T., Franklin M. Grynkiewicz P. E., Leili Javidanian P. E.
In the latest AASHTO design specifications, the Load and Resistance Factor Design (LRFD) method is prescribed for the design of retaining walls. However, inconsistencies arise when LRFD is used for re
Oct 1, 2022
-
Hybrid Shoring System for a Deep Temporary ExcavationBy Nadir Ansari, Brian W. Wilson, Marina S. W. Li
"A hybrid Deep Mixing (DM) shoring system was recently constructed for a high-rise development in downtown Vancouver, British Columbia, Canada for the temporary support of a five-level basement excava
Jan 1, 2017
-
Excessive Pile Breakage, Gaylord National Resort And Conference Center, A Look Back 15 Years LaterBy Karl A. Higgins
In August 2004, the long-awaited National Harbor project in the DC metro area sprang to life with the design of Gaylord National Resort and Convention Center. When the project was in its final stages
-
Pile Driving Between the Amazonas and Xingu Rivers in the Tucuruí-Manaus Transmission Line – Lessons Learned and Solutions Found for a Challenging ProjectBy José Carlos do Amaral, Marcelo Groszownik, Jorge Beim
"Initiated in 2008, the project of this 1800 km long Electrical Transmission Line is a job of extreme technical complexity, crossing regions of major forests and rivers. When ready, it will allow the
Jan 1, 2015
-
An Unique Formula for the Stone-Column Group EfficiencyBy Abhijit Saha
"The stone columns improve the performance of foundations on soft and loose soil due to the ability of composite ground to sustain increased structural loads under reduced settlements. The interaction
Jan 1, 2015