    Experiment to Determine the Influence of Groundwater Level on Grid-Form Deep Mixing Walls for Liquefaction Control

    By Tsuyoshi Honda, Kazuhiro Kaneda, Masayuki Imai, Kazuo Konishi, Kunio Higashinaka

    "In recent years, the demand for measures to control liquefaction of existing airport runways and harbor structures has increased. However, from the perspectives of constructability and cost, applicat

    Jan 1, 2015

  • DFI
    Water Powered Percussive Downhole Hammers – Energy Savings And Productivity

    By Shyam Chengalath, Johan Jeansson, Magnus Hörman

    Down-The-Hole (DTH) drilling usually uses compressed air to power the hammer. However, there are now DTH hammers on the market which instead of compressed air use high pressure water to power the hamm

    Sep 1, 2022

  • DFI
    Diaphragm Wall Technique Used In A Different Way Cutting Trenches Up To 823 Ft. (251 M) For An Exploration And Bulk Sampling Program

    By Stefan Schwank, Alexander Blatt, Franz-Werner Gerressen

    Diaphragm wall technique is usually used to install diaphragm walls, which are known as underground structural elements commonly used for retention systems and permanent foundation elements as well as

  • DFI
    Northeast Boundary Tunnel – Mount Olivet Road Drop Shaft

    By Jeremiah M. Jezerski, Russell H. Lutch

    The Mount Olivet Road Drop Shaft (MOR-DS) support of excavation (SOE) is a circular unreinforced concrete shaft with an inside diameter of a 30.5 ft (9.3 m) and depth of 120.5 ft (36.7 m), constructed

    Oct 1, 2022

  • DFI
    Quality Assessment Of Drilled Shaft Foundations At The Jane Byrne Interchange

    By Travis Coleman, Elvis Ishimwe

    Currently, more than 400 drilled shafts have been constructed by various contractors at the I-90/94 and I-290 Jane Byrne (Circle) Interchange, located near downtown Chicago, Illinois. Cross-Hole Sonic

  • DFI
    Ground Improvement by Dynamic Replacement within Intertidal Mangrove Mud Environment, Ichthys LNG, Darwin

    By J. Racinais, P. Vincent

    "In September 2011, Menard Oceania (MO) was engaged by Mac Mahon John Holland Joint Venture (MJHJV) to provide ground improvement solution for the $34bn Ichthys LNG development. With close to 400,000m

    Jan 1, 1900

  • DFI
    Lateral Stresses On Multilevel Tieback Walls

    By Liiban A. Affi

    The most difficult task of designing multilevel tieback walls for deep excavation support is the determination of lateral stresses. These lateral stresses act not only on the shored height, but also

    Jan 1, 2010

  • DFI
    Application Of Pile Test Data For The Foundation Design Of Rail Viaduct At Carrum, Victoria

    By Nick M. Withers, Suthagarann Visvalingam, Cillian Mc Colgan

    The level crossings removal project in Victoria is removing 75 level crossings across Melbourne to improve safety by separating trains from traffic, with other benefits such as reduced congestion, an

    Nov 1, 2022

  • DFI
    Static Behavior of Steel H-Piles under Axial Load using Scale Models in Very Soft Clays

    By Francisco A. Flores, Rigoberto Torres

    The Complementary Technical Standards of Mexico’s City Building Code do not mention the criteria to compute the bearing capacity of Steel H-piles. It is necessary to increase knowledge in using steel

    Sep 8, 2021

  • DFI
    Interpretation and Evaluation of Thermal Integrity Profiling Measurements

    By Seth Robertson, Daniel Belardo, Travis Coleman

    Thermal Integrity Profiling (TIP) is a non-destructive method used to evaluate drilled deep foundation integrity. This integrity testing method is specified more frequently, and is becoming an indust

    Sep 8, 2021

  • DFI
    Constructing Tsunami Walls with Pressed-In Sheet and Pipe Pile Combi-Walls

    By Takefumi Takuma, Tsunenobu Nozaki, Masashi Nagano

    The city of Naruto in the southwestern part of Japan is situated at the mouth of the mighty Yoshino River. An approximately 1,000m-long levee/bulkhead along one of the river’s tributaries in the city

    Sep 8, 2021

  • DFI
    Ideas To Improve Driven Pile Foundation Design And Installation Procedures

    By Armin W. Stuedlein, Steven R. Saye

    The differences between calculated axial pile capacity and the capacity realized during and following installation has long presented a significant concern for foundation engineers and contractors. Su

  • DFI
    Pullout Capacity of Pile Groups in Sand

    By S. P. Mukherjee, Smita Tung

    "Piles are generally subjected to uplift in case of under ground and water front structures. Sometimes piles are also to resist uplift loads in transmission towers, dry rock, and so on. Experimental i

    Jan 1, 2015

  • DFI
    Value-Engineering of H-Pile Foundations in Karstic Geology

    By Rachael M. Fischer, Daniel J. Woeste, Terence P. Holman

    "A new 50 MW biomass renewable energy power plant was planned for construction in southwestern Georgia. The original foundation design consisted of very conservatively designed H-pile groups with vert

    Jan 1, 2016

  • DFI
    Grouted Micropiles for Foundation Remediation in Expansive Soil (8th Michael W. O?Neill Lecture)

    By John D. Nelson

    Foundation underpinning is a common component of remediation schemes for distressed foundations on expansive soils. For many applications in expansive soil, micropiles have distinct advantages over ot

    Aug 1, 2013

  • DFI
    Comparing Conflicting Conclusions from Different Integrity Testing Methods on the Same Drilled Shafts

    By Alex Ryberg, Matthew L. Becker

    Several integrity testing methods exist which may be used to evaluate drilled shafts. Each test method has advantages and limitations. On occasion, the results from different test methods may lead to

    Sep 8, 2021

  • DFI
    Data Collected and Lessons Learned from Load Test Program for ACIP Piles Supporting Highway Bridges

    By Reinaldo J. Villa, Joshua C. Adams

    The I-395/SR-836/I-95 reconstruction project is an $818-million design-build construction effort that includes construction of viaduct, segmental and signature bridges in Miami leading into Miami Beac

    Sep 8, 2021

  • DFI
    Innovative Crosshole Sonic Logging Testing Drilled Shafts

    By Joshua C. Adams, Les Chernauskas, Edward L. Hajduk

    "Drilled shafts are increasingly being used to support bridge and building foundations. Because these foundations usually carry very high design loads and often serve as non-redundant, single load car

    Jan 1, 2009

  • DFI
    Performance of Large-Diameter Bored Pile Socketed In Sandstone and Siltstone in Thailand

    By Zaw Zaw Aye, Sereyroath Chea, Nutthapon Thasnanipan, Thayanan Boonyarak

    "As there are only limited numbers of bored pile constructed in sandstone and siltstone in Thailand, load transfer and settlement behavior of a pile in these rocks are still not fully understood. Majo

    Jan 1, 1900

  • DFI
    Capacity of Hydraulically Jacked Piles

    By Howard A. Perko, Melinda J. Hummel

    "Hydraulically jacked piles, herein referred to as jacked piles, are commonly used for underpinning existing structures to arrest settlement or augment an existing foundation for higher loads. They co