Application Of Electro-Kinetics To Expedite Pile Setup In Kaolinite Clay
By Susheel R. Kolwalkar
A significant increase in the side shear capacity over a period of time is often observed in case of driven piles. This phenomenon is referred to as ?setup? or ?freeze?. This phenomenon cannot be pred
Jan 1, 2008
-
Analysis Of Load Tests Of Drilled Shafts. For Support Of Overhead Signs
By Roy H. Borde
The design of foundations to support overhead signs is primarily based on providing adequate resistance against horizontal wind loads. The typically used subgrade reaction model for the load-deflectio
Jan 1, 1988
-
Classical And Finite Difference Method To Estimate Pile Capacity Compared With Pile Load Testing Results
By Yogesh Prashar
Three conventional uplift tests and 12 Rapid Pile Load Tests (RLT) were performed on total of fifteen 16-inch square pre-cast concrete driven piles at a test site in Emeryville California in December
Jan 1, 2002
-
Dynamic Monitoring Program Results Indicator Pile Tests -I-880 - Introduction
By D. Michael Holloway
The realignment of Interstate 880 replaces the double-decked (Cypress) viaduct collapsed in Oakland, California during the 1989 Loma Prieta Earthquake. The California Department of Transportation (CAL
Jan 1, 1996
-
Base Grouted Piles - Mr. P. M Cashman, Independent Consultant
By W. J. Kingwell
My comments and questions are addressed to Mr. Troughton. It seems to me that the tests were very well tailored to determine long term effects on performance of bearing piles as groundwater pressures
Jan 1, 1991
-
Designed, Dynamically Load Tested And Installed Pile Foundation In Southwest Florida - A Case History
By Christopher J. Pacitto
This paper presents a case history of an engineered, monitored, and tested program that provided an effective and satisfactory basis for the completion of pile foundations for Twin Dolphins 1 at La Pe
Jan 1, 2002
-
Dynamic Pile Testing In Soils Exhibiting Set-Up - Introduction
By Juan M. Antorena
A dynamic testing program was performed to evaluate installation procedures, assess capacity of 610-mm (24-inch) diameter open ended steel pipe to evaluate set-up and provide minimum pile tip elevatio
Jan 1, 1995
-
Monitoring And Quality Control Of A 100 Metre Deep Diaphragm Wall
By D. A. Bruce
To check the feasibility and the quality of a very deep diaphragm wall, a tern of adjacent panels has been constructed, up to a depth of 100 m, in the Milan sandy gravelly soil by means of a hydraulic
Jan 1, 1989
-
Pile Design For Offshore Structures Subjected To Subsidence
By Juan J. Campo
The Freeport-McMoRan Main Pass Mine development in the Gulf of Mexico is a complex designed to extract up to 67 million long tons of sulphur over a 40 year period. The initial development includes 15
Jan 1, 1992
-
Preserving The Foundations Of Some Of Boston?s Oldest Buildings
By Michael J. Atwood
Many buildings in Boston are founded on untreated wood piles, which can deteriorate and lose their structural capacity if groundwater levels are lowered below the tops of the piles, exposing the wood
Jan 1, 2011
-
Innovative Riverbank Erosion Control Retaining Wall System for the Brazos River
By Tracy Brettmann, Will Bohlen
An innovative retaining wall design consisting of tangent drilled shafts with supplementary seal piles was used to limit continuing bank erosion along the Brazos River in Southeast Texas. The riverban
Jan 1, 2018
-
Underpinning Support Pipeline Compressor Station Founded On Timber Piles Potter, Ontario - DFI Conference, Toronto, Oct 1997 - Underpinning Support - Pipeline Compressor Station - Background
By Brian Isherwood
TransCanada Pipelines, Calgary (TCPL) is one of North America's leading transporters of natural gas through its energy transmission business. TransCanada also operates significant complementary b
Jan 1, 1997
-
Maritime Structures
By D. Waite
The Chairman opened the session by wondering why so few papers on Maritime Structures had been received for this conference. Perhaps because the marine environment is so hostile and the access so diff
Jan 1, 1991
-
Application Of Bu-Type Steel Sheet Pile On Construction Of Ports ? Preface
By Zhou Lu-Jian
The Port of Shekou is situated at Shenzhen Bay on the east bank of Lingding Ocean. Its coastline is about 6 km long and the water depth near the shore is Favourable. Across the bay is the ' New T
Jan 1, 1991
-
Diaphragm Wall Construction In Hong Kong
By Arturo Ressi di Cervia
The utilization of diaphragm wall construction in Hong Kong began in 1974 with the construction of the New World Center, the first diaphragm wall job built in the British Colony. That landmark job
Jan 1, 1993
-
Design & Construction Of Pile Foundations For A Building Complex - A Case History
By S. K. V. Avasarala
This paper presents a case history of design, prediction, probe and production pile driving monitoring, loading tests and installation of over 3,300 prestressed concrete piles for a building complex c
Jan 1, 1995
-
Test Pile Program Carrier Pier And South Wharf Naval Station Puget Sound Everett, Washington
By David G. Winter
The first test pile for the carrier pier and south wharf at NAVSTA Puget Sound was driven on December 27, 1989, and the final pile was tested on February 26, 1990. Implementation and modification of t
Jan 1, 1990
-
Open Well Caissons Of A 1917 Railroad Bridge: How 19th Century Construction Can Influence 21st Century Construction (f1b0a5f2-b1b8-41d4-bbfb-fab6f395e7a0)
By Alan D. Fisher
Amtrak made a decision to replace an aging bascule bridge with a vertical lift bridge for their crossing of the Thames River in New London, Connecticut. The new lift bridge occupies the same alignmen
Jan 1, 2008
-
Installation Of Marine Pile Foundations At The Skyway Project For The San Francisco Oakland Bay Bridge (16c93b01-e1c3-48e5-bd32-54e8ea2106cb)
By Robb L. Swenson
Construction of foundations for the Skyway Segment of the San Francisco Oakland Bay Bridge required innovative techniques due to the mass of the structures being inserted and the unique subsurface of
Jan 1, 2013
-
Case History - Augered Cast-In-Place Piling Installed Into Weathered Sandstone
By Edwin W. Meyer
The augered cast-in-place piling technique was used to install deep foundations 20 feet into weathered sandstone. The project involved the upgrading of the Air Quality Control System (AQCS) for a 560
Jan 1, 2006