Geotechnical Mine Design Of The Foidel Creek MineBy H. N. Maleki
The results of five years of geotechnical investigations are presented to develop productive and stable longwall layouts for the Foidel Creek Mine. The program was initiated during the pre-mining stag
Jan 1, 1988
-
Monitoring and Prediction of Ground Movements Above Underground Mines in the Eastern United StatesBy M. Karmis
mining factors and representative ground movement parameters. Based on this analysis, the previously developed prediction methods were modified and tested for their applicability in the Appalachian co
Jan 1, 1987
-
Crosshole Seismics: Applications In MiningBy Richard E. Thill
Two Cross-borehole systems were developed by the Bureau of Mines, one operating at a central frequency of 20 kHz for close-in spacing between boreholes (2-20m) and another operating at a dominant freq
Jan 1, 1989
-
Time-Dependent Analysis Of Underground Opening StabilityBy Changshou Sun
Excessive deformation occurred in the underground openings of Jinchuan Nickel Mine, the largest nonferrous underground mine in China. Developed in weak rock formations at great depth, the underground
Jan 1, 1999
-
Enhanced Surface Control For Roof And Rib Support (8fec630d-2a24-4d9d-8993-15ef5bf95858)By Stephen C. Tadolini
The risk of injury caused by minor roof falls continues to increase in underground mining. Most ground control injuries result from small rock falls that occur in a supported area, but do not involve
Jan 1, 2001
-
Case Studies Of Depillaring Under Special Strata And Mining ConditionsBy P. R. Sheorey
Four case studies of special geomining conditions from Indian coalfields are discuss- ed. These cases relate to (a) pillar extraction in two seams simultaneously under a difficult roof (Satpura I and
Jan 1, 1988
-
Bolting Practice In Longwall Gateroads At The Miike CollieryBy Kikuo Matsui
Standing supports such as steel arches or square work supports along with the necessary struts and lagging have been traditionally employed in the longwall gateroads of the Japanese underground coal m
Jan 1, 1993
-
Longwall Surface Subsidence Prediction Through Numerical ModellingBy Noor Mohammad
Comprehensive numerical modelling of the subsidence associated with longwall mining in UK Coal Measures strata has been conducted and validated against UK data. The Rock Mass Classification System (RM
Jan 1, 1997
-
Influence of Structural Stress Concentration and Structural Irregularity on Longwall Gateroad Roof ControlBy Daniel Su
Following several roof falls in the E3 longwall development of a Consol Pennsylvania Coal Company underground coal mine, an underground roof geology reconnaissance program consisting of twenty-nine 20
Jan 1, 2002
-
Engineering Methods For The Design And Employment Of Wood CribsBy Thomas M. Barczak
Wood cribs are used extensively to stabilize mine openings by providing resistance to deflections of the immediate roof and floor and by supporting the weight of unstable rock masses. While the unit c
Jan 1, 1993
-
Effects of Panel Mining Sequence and Retreat Direction on the Roof Stability of Longwall Headgate EntriesBy Jinsheng Chen
The major functions of longwall headgate entries are to provide access ways to the outby submains or mains for coal transportation and to the longwall face for fresh air and for transporting men and m
Jan 1, 1998
-
Modelling Of Pillar Stability In Room And Pillar MinesBy Douglas Morrison
By applying modern 3D numerical modelling techniques to the analysis of a pillar cascade failure in a room and pillar mine, it has been possible to simulate the collapse and develop an understanding o
Jan 1, 2003
-
Failure Characteristics Of Roof Falls At An Underground Stone Mine In Southwestern Pennsylvania (75950903-1172-4003-a90c-706052b9d4ea)By Anthony T. Iannachione
The location and time of 2,007 microseismic emissions from a limestone mine in southwestern Pennsylvania were compared with the development of mine faces and the characteristics of the mine layout. Ba
Jan 1, 2001
-
Estimation Of In-Situ Stress At Ikeshima Colliery Using AE And DRA MethodBy Hideki Shimada
A low cost methodology that allows the determination of in- situ stress using oriented core specimens has been investigated. The technique can be used to determine the stresses during the early stages
Jan 1, 2001
-
Stress Analysis and Support Design for Longwall Mine-Through Entries (A Case Study)By Keith Heasley
An eastern longwall mine was required to mine through a set of three entries located midway down the length of a panel. Of course, the mine desired to design a successful support system for the mine-t
Jan 1, 2003
-
Determination Of Basis For The Double Use Of Rectangular Rockbolted Roadways In The D/C Seam At The Auguste Victoria MineBy Karl H. Brandt
In the Auguste Victoria mine a bolted rectangular roadway has been kept open for the first time in the seam D/C after retreat. The target of the project was to gain a basis for planning and experie
Jan 1, 2001
-
The Structural Response Of A Steel Lattice Transmission Tower To Mining-Related Ground MovementsBy Robert W. Bruhn
A 125 foot high steel lattice frame tower supporting a 500 kV EHV transmission line and located over the gateroads of a longwall mining operation was subjected to ground movements from the mining of a
Jan 1, 1990
-
Subsidence Prediction Influence Assessment and Damage ControlBy Y. Luo
An extensive subsidence research program conducted by the authors has greatly improved the accuracy and the capabilities of subsidence prediction under complicated mining and surface conditions. The t
Jan 1, 1997
-
Design And Planning Of Lower Seam Longwall GateroadsCase study data were analyzed to develop and quantify empirical stress transfer relationships between seams for both longwall and room and pillar mines. Layering in the innerburden and the distance be
Jan 1, 1995
-
Stability Of Interpanel-Pillar And Deformation Of Gateroad Due To Longwall MiningRetreat longwall method with re-use of gateroad has been traditionally employed in Japan, mainly because of the advantage of higher recovery. But the Miike Colliery has newly introduced the interpanel