Collaborative Data Sharing During Seepage Barrier Wall Construction at Bolivar Dam – Perspectives from Owner, Contractor and Sub-ContractorBy Robert Bachus, Jamey Rosen, Fabio Santillan, Georgette Hlepas
"A seepage barrier of length 4,800 feet and maximum depth 144 feet is being installed at Bolivar Dam in Ohio. This project is owned by the United States Army Corps of Engineers and contracted to Trevi
Jan 1, 2017
-
TTMJ – The New System for Slurry (Diaphragm) Wall JointsBy Maurizio Siepi, Paul van Horn, John Coupland, Julian Crawley
"TTMJ is the acronym for the Slurry (Diaphragm) Wall Tension Track Milled Joint currently in development as part of the European Union's innovative and far-reaching Horizon 2020 initiative (FTI Pilot-
Jan 1, 2017
-
Recent Developments in Wind Turbine Foundation Design: Post Tensioned Single PierBy Mohsen Elsayed, Amr Sallam, Ahmad Mohamed, Xuebing Zheng, Mohamed Alrowaimi
The foundation is an essential component of the wind turbine that ensures continued operation under stable and safe conditions. Both shallow and deep foundations are utilized to support wind turbines
Jan 1, 2019
-
Selection And Design Of Continuous Flight Auger And Drilled Displacement PilesBy Dan Brown
This paper provides an overview of the advantages and limitations of continuous flight auger (CFA) and drilled displacement (DD) systems compared to other deep foundation systems, along with a summary
Jan 1, 2005
-
The Underwater Cut-Off At The Walter F. George DamBy Gianfranco Di Cicco
Seepage problems were recorded for more then 40 years at the Walter F. George lock and dam. In 2001 the Mobile district of The U.S. Army Corps of Engineers turned to the installation of a 200 feet dee
Jan 1, 2013
-
Installation of 10 Feet Diameter CIDHs in Soft Clay Using Rotator/Oscillator on TrestleBy Babak Mamaqani, Pirooz Barar
The Moanalua trestle spanned over Moanalua Stream, Honolulu, HI and was designed to accommodate construction of five 10 feet diameter cast in drilled hole (CIDH) piers as a part of Honolulu Authority
Jan 1, 2019
-
Load and Resistance Factor Design – Past, Present and FutureBy Silas C. Nichols, Jennifer E. Nicks
"Limit states design (LSD), or load and resistance factor design (LRFD), is a method to account for the uncertainty in loads and resistance through a reliability calibration that requires all applicab
Jan 1, 2015
-
Quality Control and Testing of Jet Grouting and its Interpretation in Relation to the Christchurch Town Hall Restoration Project.By David Chadwick, Paul Marsden, Chris Hughes, Mathias Delapille
"Following damage caused by the 2011 Christchurch earthquakes, the NZ$127.5million Christchurch Town Hall Restoration project is due for completion in 2018. The building is undergoing extensive repair
Jan 1, 1900
-
Design And Construction Constraints Imposed By Unique Geologic Conditions In New York City - SynopsisBy George J. Tamaro
The design and construction of foundations in the New York City area are usually dictated by the widely varying geologic conditions encountered in the five boroughs, particularly along the spine of Ma
Jan 1, 2000
-
Washington Avenue Tunnel Project: Fortifying Aging Underground InfrastructureBy Andrew R. Klaetsch, Peter W. Deming
"The Washington Avenue tunnel in Kingston, NY was completed in 1912 to convey combined storm water and sanitary sewage. Over a mile in length, the tunnel was driven almost entirely in bedrock, with th
Jan 1, 2016
-
Diaphragm Wall Technique Used In A Different Way Cutting Trenches Up To 823 Ft. (251 M) For An Exploration And Bulk Sampling ProgramBy Stefan Schwank, Alexander Blatt, Franz-Werner Gerressen
Diaphragm wall technique is usually used to install diaphragm walls, which are known as underground structural elements commonly used for retention systems and permanent foundation elements as well as
-
University Of Minnesota Football Stadium Down Hole Pile: Innovative Solution For Difficult ConditionsBy Eric J. Pederson
The down hole hammer is widely used in specialty geotechnical construction. The common uses include tie-back anchor installation, micropile installation, and general soil/bedrock drilling operations.
Jan 1, 2008
-
Pile Installation Recorder Tests For ACIP/CFA Piles - IntroductionBy Garland Likins
The Texas Department of Transportation, now considering using Augered Cast-In-Place (ACIP) Piles (also known as Continuous-Flight-Auger or CFA Piles) in their foundations, awarded a research project t
Jan 1, 1998
-
Design And Performance Of Helical Screw Piles In Collapsible And Expansive Soils In Arid Regions Of The United StatesBy David R. Black
Foundation problems due to collapsible and expansive soils are well known throughout the arid western United States. Millions of dollars are spent annually to counteract the effects of such soils for
Jan 1, 2002
-
Case Study on the Frederick Douglass Memorial Bridge and the use of Large Diameter Open End Steel Pipe Piles, Washington, DCBy Karl A. Higgins, Michael D. Venezia
The South Capitol Street Corridor Project is one of the District Department of Transportation’s (DDOT) largest projects, and is currently under construction. This case study will focus on the design o
Jan 1, 2019
-
Innovative Driven Pile Solution for the Rhode Island Route 6/10 Interchange ProjectBy Seth H. Hamblin, Leo J. Hart, John E. Regan
The Route 6 /10 10 Interchange Design/Build project, located in Providence, Rhode Island, involves the design and construction of five (5) new elevated bridge structures to replace and reconfigure the
Jan 1, 2019
-
Capitol Complex Phase 1 ExpansionBy Eric S. Lindquist, Charles A. Luxford
The State of Texas recently adopted a master plan to expand the existing Capitol Complex in Austin. Phase 1 of this expansion will add two new State office buildings and five levels of underground par
-
Cement Deep Soil Mixed Walls/Grout Plug for Groundwater Cut Off and Excavation Support at the Bart Warm Springs ExtensionBy Harry Schnabel, Mitchell L. Fong, Douglas R. Jenevein, Thomas S. Lee
"The Warm Springs Extension (WSX) is one of a series of projects that will eventually extend the Bay Area Rapid Transit System (BART) from Fremont to San Jose, California. A cut and cover tunnel was u
Jan 1, 2015
-
Innovative Micropile Retrofit Of Two Existing StructuresBy Terence P. Holman
Micropiles are employed to retrofit existing foundations, including underpinning prior to future construction operations and resupport of existing structures that have experienced distortion and settl
Jan 1, 2007
-
Estimation Of Compressibility And Consolidation Characteristics Of Lightly Overconsolidated Soils From In-Situ Time Settlement PlotsBy Lenin T., Madhav M. R., Padmavathi V.
Use of PVDs and preloading on the ground can significantly reduce the time taken for ground to consolidate. Many soils in situ are lightly overconsolidated, with overconsolidation ratios (OCR) ranging
Sep 1, 2022