Search Documents

Search Again

Search Again

Refine Search

Publication Date
Clear

Refine Search

Publication Date
Clear
Organization
Organization
  • DFI
    Numerical Study On Behavior Of Unreinforced And Reinforced Disconnected Piled Raft Foundation

    By P. Seethalakshmi, Yatakuri Yaswanth Naidu

    The use of a single pile, group of piles with pile cap, piled raft foundation system, etc., are prevalent in transferring the superstructure load from the soft soil layers to the firm underground laye

    Sep 1, 2022

  • DFI
    Value-Engineering of H-Pile Foundations in Karstic Geology

    By Rachael M. Fischer, Daniel J. Woeste, Terence P. Holman

    "A new 50 MW biomass renewable energy power plant was planned for construction in southwestern Georgia. The original foundation design consisted of very conservatively designed H-pile groups with vert

    Jan 1, 2016

  • DFI
    John F. Kennedy Airport Site Redevelopment: Tapertube Pile Foundation

    By Gisele R. Passalacqua, Aly Mohammad, Joanna Smith

    The $13 billion John F. Kennedy (JFK) airport construction redevelopment program includes new terminals and buildings that are supported on piles to meet the airport expansion demand due to increased

  • DFI
    Development of Lattice-Shaped Cement Treatment Method for Liquefaction Countermeasure

    By Seiji Mizutani, Hirofumi Taguchi, Makoto Yoshida, Hidenori Takahashi, Naotoshi Shinkawa, Kazuo Konishi, Yoshiyuki Morikawa, Masaya Kawata

    "The lattice-shaped cement treatment method has been used to improve the seismic performance of liquefied sandy soil in Japan. The efficacy of the method has been confirmed by the huge earthquake in J

    Jan 1, 2015

  • DFI
    Drilled Displacement Piles in the Northeastern United States

    By Jr NeSmith

    "Drilled Displacement piles are a product of screw pile technology originally developed in Europe. The process involves rotating tool into the ground that displaces the soil laterally as it advances,

    Jan 1, 2016

  • DFI
    Nicholson In The Neighborhood: Virginia’S North Hill Project

    By Dominic Ammon, Mark Rothbauer, Paul Landers P. E.

    Across the Potomac River from the location of the DFI47 Annual Conference (October 2022), in Alexandria, VA, two large permanent anchored walls with a decorative shotcrete face were recently construct

    Oct 1, 2022

  • DFI
    Deep Mixing in the United States: Milestones in Evolution

    By Donald A. Bruce

    "The Deep Mixing Methods (DMM), in their current forms, have been employed in the United States since 1986, although an earlier version had seen service from 1954. The earlier developments were strong

    Jan 1, 2015

  • DFI
    Self Hardening Slurry Wall Installation By Hydromill At The Herbert Hoover Dike ? An Innovative Solution

    By Mario Mauro

    In 2007 the US Army Corps of Engineers classified the Herbert Hoover Dike in Florida as a Dam Safety Action Classification (DSAC) 1 dam, and started the implementation of one of the largest dam rehabi

  • DFI
    Case Histories of Circular Secant Pile Access Shafts for Tunnels

    By Piotr Kozlowski, Stanley L. Worst, Matthew J. Niermann

    Circular secant pile shafts were installed along the tunnel alignments for both the Ohio Canal Interceptor Tunnel project in Akron, Ohio and the Ohio River Tunnel project in Louisville, Kentucky. The

    Jan 1, 2019

  • DFI
    Urban High Capacity Deep Foundation Solutions in Sites with Complex History and Geology

    By Karen C. Armfield, Gisele R. Passalacqua, Joanna Smith

    New York City is an urban environment with a history spanning over 200 years. The coastline of New York has changed over the years. In the East River, old bulkhead and remnant of relieving platforms t

    Jan 1, 2019

  • DFI
    Excavation-Induced Movement of Adjacent Foundations

    By Hugo Meggitt, Damian R. Siebert, Wystan Carswell

    Excavation-induced ground movements are a critical component in the design and construction of deep excavations in urban settings due to the potential adverse effects on adjacent structures and infras

    Jan 1, 2019

  • DFI
    Engineering The Mansion's Heritage

    By Ken MacLeod

    A development at 83 Queens Road in Melbourne, Australia required construction of a three level basement. The normal geotechnical constraints of excavating adjacent to an existing relatively new buildi

    Jan 1, 2006

  • DFI
    Building The Devil’s Playground: How a Ground Improvement Program Eliminated the Need for Pile Foundations

    By Christian B. Woods, Joe C. Drumheller

    "Kenneth A. Huber, P.E., Langan Engineering & Environmental Services, New York, New York, USAThe dream to bring New Jersey Devils hockey to the largest city in New Jersey became a reality in the summe

    Jan 1, 2015

  • DFI
    Construction of a Deep Soil Mixed Cut-Off and Retaining Wall in Richmond BC

    By Keith MacKay, John Carter, David Siddle, Fernando Faminia

    "The River Green Residential development, is located in the municipality of Richmond, BC adjacent to the Fraser River. Ground conditions at the site consisted of medium to fine grained alluvial sands

    Jan 1, 2016

  • DFI
    Adjacent Top-Loaded Bi-Directional Test And Conventional Bidirectional Load Test Results – Site Ii

    By Patrick J. Hannigan, Seth Robertson, Rozbeh B. Moghaddam

    The Top-Loaded Bi-Directional Test (―TLBT‖) and the conventional Bi-Directional Load Test (―BDLT‖) are full-scale static load test methods. In both methods, the test loads are applied bi-directionally

    Oct 1, 2022

  • DFI
    Design and Construction of the Cannelton Hydroelectric Plant Cofferdam and Cut-Off Wall

    By James M. Tantalla, Dwight Metcalf, Roderic A. Ellman Jr.

    "The construction of a new low head hydro-electric plant at the Cannelton Lock and Dam required the design and construction of a cofferdam to accommodate a deep excavation extending approximately 150

    Jan 1, 2016

  • DFI
    Jet Grouting for Echo Dam Seismic Rehabilitation

    By Tara Schenk-McFarland, Mark Bliss

    Echo Dam, located near Coalville, Utah, is a facility that provides storage for irrigation and municipal use. Original construction of the dam was completed in 1931. Because of seismic concerns, the s

    Jan 1, 2017

  • DFI
    Alternative Analytical Methods for Borehole Permeability Tests in Seepage Barrier Walls

    By R. Lee Wooten, David R. Shields, Darren D. Clark

    "Borehole permeability tests that measure flow or head changes in boreholes located within seepage barrier walls are commonly used to estimate the in situ permeabilities of those walls for quality con

    Jan 1, 2016

  • DFI
    Driven Pile Foundation Design and Construction Issues for a Highrise Building in Manhattan

    By Satyajit Vaidya, Rudolph Frizzi, Sandy Larimer

    "This paper presents a case history in design and construction of a deep foundation system that included high-capacity open-ended driven piles constructed to support a high-rise building in Manhattan,

    Jan 1, 2016

  • DFI
    Data Collected and Lessons Learned from Load Test Program for ACIP Piles Supporting Highway Bridges

    By Reinaldo J. Villa, Joshua C. Adams

    The I-395/SR-836/I-95 reconstruction project is an $818-million design-build construction effort that includes construction of viaduct, segmental and signature bridges in Miami leading into Miami Beac

    Sep 8, 2021