  • DFI
    Foundation Construction Challenges At 100 11th Avenue In Manhattan - Osterberg Cell Load Test In Mica Schist

    By Cem Altuntas

    This paper is the second in a series of two describing the design and construction of a foundation for a major high-rise real estate development on the west side of Manhattan, N.Y. The foundation memb

    Jan 1, 2008

  • DFI
    Micropile Performance Variability: A Fundamental Case Study

    By Walter E. Vanderpool

    Type 1B micropiles (Bruce and Juran, 1997) can be installed rapidly and efficiently. During an 85-day period, 536 micropiles were installed to depths of 61 meters within a site 41 meters by 43 meters.

    Jan 1, 2002

  • DFI
    Time-Dependent Increase Of The Bearing Capacity Of Displacement Piles

    By Florian König

    It is well known that the bearing capacity and stiffness of displacement piles may increase significantly with time, a phenomenon usually referred to as set-up. In cohesive soils the set-up is commonl

    Jan 1, 2006

  • DFI
    Producing Sealing Walls And Sealing Slabs By Applying The Soilcrete Process

    By E. W. Raabe

    The paper discusses the increasing role of specialist grouting techniques to form water seals or cut-offs for deep basement construction. Raabe and Toth discuss the various grouting methods available

    Jan 1, 1989

  • DFI
    Understanding The Vibratory Pile Driver/Extractor: A Field Man's Perspective - 1. What Is A Vibro Driver/Extractor And How Does It Work?

    By John L. White

    The vibro driver/extractor is a machine that grips to a pile and vibrates it up and down. When the vibrating pile is lowered into the ground, all soil around the pile begins to vibrate. A vibrating pi

    Jan 1, 1990

  • DFI
    Drilled Pier Foundation In Hard Carbonate Rock ? Synopsis

    By K. E. Darnell

    Drilled pier foundations have long been a favored foundation type for heavily loaded structures. Drilled piers derive their load-bearing capacity from end-bearing, and/or sidewall friction. This type

    Jan 1, 2010

  • DFI
    Piles In Expansive Soil For Large Tension Forces ? Synopsis

    By G. W. Plant

    This paper describes the design philosophy and construction details of piles between 25m and 32m deep to support 160m high and 110m base diameter cooling rowers for a major power station. It is sited

    Jan 1, 2010

  • DFI
    The Underwater Cut-Off At The Walter F. George Dam

    By Gianfranco Di Cicco

    Seepage problems were recorded for more then 40 years at the Walter F. George lock and dam. In 2001 the Mobile district of The U.S. Army Corps of Engineers turned to the installation of a 200 feet dee

    Jan 1, 2013

  • DFI
    Skin Friction In Shale: Results Of The Hwy. 81 Bridge, Yankton, SD Drilled Shaft Load Test

    By Scott M. Mackiewicz

    This project includes replacement of the historic vertical-lift span Meridian Bridge (U.S. Highway 81 over the Missouri River) that connects Yankton, South Dakota with rural Cedar County, Nebraska. T

    Jan 1, 2008

  • DFI
    A Geotechnical Instrumentation Case Study

    By Mehih Demirkan, Kevin Tehansky

    Located about an hour drive south from Washington, D.C., the Maryland Transportation Authority (MDTA) contracted with Skanska-Corman-McLean (SCM) to deliver a new Governor Harry W. Nice Memorial/Senat

    Apr 1, 2023

  • DFI
    Application of Non-Destructive Testing to Drilled Shafts

    Technically speaking, the concept of NDT sounds like the "magic bullet" when faced with a questionable drilled shaft. All the Contractor or Engineer needs to do is select an NDT method, apply it, unde

    Jan 1, 2004

  • DFI
    Real Time Monitoring the Historic Old South Church, Boston, Massachusetts

    By Pierre Gouvin, Michael Oakland

    "This paper covers the rapid response methods used to monitor the emergency response to damage to an historic structure. An architectural gem, the latest incarnation of the old south Church was comple

    Jan 1, 2017

  • DFI
    Mini-Pile Design and Construction Methods Change to Mitigate Soil Loss through Glacial Till (db8ff9fc-ef1a-44d4-9e2e-ad6c00fcf7e5)

    By Cassandra A. Wetzel

    "Rock socketed mini-piles are a desirable foundation alternative when design capacity is more than 40 tons and there is limited access. In this case history mini-piles were designed to support between

    Jan 1, 2017

  • DFI
    Laboratory Mixing and Testing for Controlled Waste Disposal Site

    By Tomohiro Yamasaki

    "At the pre-construction foundations of the controlled waste disposal site built at the Port of Kinuura, the clayey soil account for the most, and with lesser amounts of sand compaction piles and sand

    Jan 1, 2015

  • DFI
    Underpinning Atlanta International Airport Concourse E for APM Tunnel Extension

    By Clinton O. Rex, Adam S. Hurley, W. Morgan NeSmith

    "Hartsfield-Jackson Atlanta International Airport underwent a $1.2 billion dollar expansion project centered on the construction of the new Maynard H. Jackson International Terminal. Passenger access

    Jan 1, 2017

  • DFI
    Field Test of Electroosmosis with the Injection of Saline Solution of Taipei Silty Clay

    By Chang-Yu Ou, Shao-Chi Chien, Hsuan-Hsiang Chang

    "A field test was performed to investigate the applicability of electroosmosis with the injection of saline solution of Taipei silty clay. The calcium chloride solution and sodium silicate solution we

    Jan 1, 2005

  • DFI
    Vibrations Caused by Pile Driving (bb4f9935-841f-4be3-bb1b-f95875d26e25)

    By K. Rainer Massarsch

    "Part 1 of 2 By K. Rainer Massarsch, Geo Engineering AB, Stockholm, SwedenINTRODUCTIONConstruction activities, such as driving of piles and sheet piles, soil compaction or excavation generate noise an

    Jan 1, 2004

  • DFI
    High Capacity Hollow Core Bar Piles

    By Lawrence F. Johnsen, Felix Ferrer, Dino Tomasetti, Cassandra A. Wetzel

    "A 17 story building was constructed at the Brooklyn Navy Yard on a site with a long history of development. Most recently the site supported a dewatering well and craneway to service two adjacent dry

    Jan 1, 2017

  • DFI
    Alternative Deep Foundation Solutions – DMM at LPV-111 in New Orleans

    By Peter Cali, Wesley Schmutzler

    "The Deep Mixing Method (DMM) was employed to raise and support the LPV (Lake Pontchartrain and Vicinity) -111 Levee in New Orleans. Even using innovative technologies, the tight schedule to achieve t

    Jan 1, 2017

  • DFI
    Stone Column Treatment and Elaborate Load Tests Verification for Improving Subsoil Conditions on a Large-Scale Residential Development Project

    By Vijaya Bhushan Rao, Jason Redgers

    A substantial lifestyle destination in the United Arab Emirates, in the Emirate of Abu Dhabi comprising of 1315 villas, town houses and non-residential leisure facilities is built over an area of 280

    Sep 8, 2021