    Design Of Axially Loaded Compression Piles According To Eurocode 7

    By Bauduin C. Besix

    The Eurocode 7 "Geotechnical Design" is based on "Limit State Design", tackling the uncertainties as much as possible at their source through: - selection of characteristic values of variables (load

    Jan 1, 2002

  • DFI
    Performance Of Non-Displacement And Displacement Piling, Adelaide Convention Centre, South Australia

    By Felix Cheng

    Extensions to the Convention Centre in Adelaide, South Australia consisted in part of construction over the existing railway system comprising nine rail lines and passenger platforms. Vibro-pile (Aust

    Jan 1, 2002

  • DFI
    Design And Performance Evaluation Of Bored Piles In Sand

    By Ashutosh S. Dhar

    Cast-in-place piles were examined in this paper from the viewpoints of construction quality, axial capacity, and load-displacement responses. The results of ten 450 mm diameter (18? f) bored piles, in

    Jan 1, 2006

  • DFI
    Ground Support And Its Toolbox

    By G. Sauer

    "More Skill is needed to avoid rather than to handle heavy ground loads." This finding, from a tunneling engineer of the nineteenth century, is still relevant today with all advanced sequential excava

    Jan 1, 2003

  • DFI
    Determining The End Bearing Capacity Of Steel Tube Piles Driven To Glacial Till In The Montréal Area Of Canada

    By Richard Deakin

    This case study describes aspects of the design of bridge foundations using 320mm diameter steel tube piles in the vicinity of Montréal, Canada. In this area, these piles are a very commonly used and

    Jan 1, 2011

  • DFI
    Applicability of Wet Grab Sampling to Quality Assurance of Deep Mixing Method

    By Masaki Kitazume

    "Abstract The wet type and dry type of deep mixing methods have been developed and widely applied for on-land and marine constructions in Japan. The quality assurance (QA) of the methods has been usua

    Jan 1, 2014

  • DFI
    Overview Of Design Methods Of Axially Loaded Piles In Europe

    By Flor De Cock

    The paper reflects part of the work from the European Regional Technical Committee on Piles (ERTC3) during its mandate between 1994 and 1999, and, in particular, describes the find­ings from an Intern

    Jan 1, 2002

  • DFI
    Berminghammer II 25 Vertical Travel Lead System: Innovative Technology For Deep Foundation Soil Mixing - 0.0 Introduction

    By Andy Schroeder

    Located in Hamilton, Ontario Canada, Berminghammer Foundation Equipment, is a manufacturer of advanced foundation equipment with 30 years of experience. The company is represented in more than 20 coun

    Jan 1, 1997

  • DFI
    Careful And Controlled Underpinning Methods In Restoration Of Damaged Houses In The Old Town Of Stockholm

    By T. Iwanowski

    Stress wave measurements and calculations are often used to make a safe determination of the bearing capacity and the integrity of driven piles. Some applications to the restoration of old buildings i

    Jan 1, 1991

  • DFI
    Steel Pile Foundations For Transmission Line Towers, As Used In Western Europe. - 1. Introduction.

    By Alexander J. Verstraeten

    The design and construction of foundations for power transmission line towers present some special problems. This paper describes a system of design and construction for these foundations that was dev

    Jan 1, 1987

  • DFI
    Experiences With A New Type Of Displacement Screw Pile - Synopsis

    By William Van Impe

    A most renewing and promissing soil displacement screw pile is called the O-pile. The O-screw pile is a soil displacement auger pile based on a screwing in - screwing out procedure. The displacement a

    Jan 1, 1996

  • DFI
    Ground Improvement for the Distressed Earth Bund Using Stone Column - A Case Study

    By M. Kumaran, A. Vetriselvan, A. Purantharan

    "This paper presents a case history of evaluating the stability of a distressed earth bund and rectification measures carried out. A 5.45 km long, 7m high earth bund for drinking water storage was con

    Jan 1, 2017

  • DFI
    Geographic Information Systems Technology Use in Tracking Quality Control in In Situ Barrier Wall Construction

    By Robert Bachus, Jamey B. Rosen

    "Abstract Large scale In Situ Barrier Wall Construction projects, specifically those related to earth dams, dikes, and levees, frequently require stringent quality control measures to ensure the succe

    Jan 1, 2014

  • DFI
    Recent Developments In Secant Bored Pile Wall Construction

    By D. E. Sherwood

    Recent developments in high torque hydraulic rotary rigs has lead to the construction of secant bored pile walls by rotary drilling methods in circumstances where earlier methods were difficult and in

    Jan 1, 1989

  • DFI
    A New Approach To Estimate The Base Bearing Capacity Of Driven Piles Based On SPT Data

    By N. Shariatmadari

    In recent years, determining bearing capacity of piles from in-situ testing data as a complement of static and dynamic analysis has been used by geotechnical engineers. In this paper, different approa

    Jan 1, 2006

  • DFI
    Business Benefits Of An Integrated CFA Rig Instrumentation System

    By Jason N. Scott

    CFA piling is a ?blind? construction process that relies heavily on the rig instrumentation to produce sound piles. If the data measured and recorded during construction can be made available to engi

    Jan 1, 2006

  • DFI
    Large Diameter Drilling Operations Of Multi Head Down The Hole Hammer Drill Through Boulders And Granite - Mach Drilling System And Some Construction Examples

    By J. Nakayama

    Construction of foundation piles or diaphragm walls through rocky or boulder containing formations has been long-standing difficulty. It has been widely understood that the down-the-hole hammer is t

    Jan 1, 1989

  • DFI
    Development and Experiences on Versatile Applications of RD-pile Wall

    By Fredrik Sarvell, Leo-Ville Miettinen, Veli-Matti Uotinen

    "Abstract The continued concentration of building activities in cramped areas of city centres means more underground construction and facilities. Demand to minimize execution time and any kind of dist

    Jan 1, 2014

  • DFI
    New Concepts For CFA (Auger Cast) Pile Controle - Synopsis

    By Shachar Magali

    This article describes two new concepts regarding the CFA (Auger Cast) piles. The first one, MALI Effect, is an approach to control the casting phase, while the second one, NETA Shear, is a technique

    Jan 1, 2000

  • DFI
    Piling The Gateway To Europe

    By Howard Roscoe

    Linking Ashford International Station to the new Channel Tunnel Rail Link required over 5000 rotary bored and CFA (continuous flight auger) piles to form tunnel walls and viaduct foundations and to su

    Jan 1, 2002