Design Parameter For Jacked PileBy Sugie Prawono
Jacked pile is the only piling system in which the load capacity of the pile, at any penetration depth, could be monitored directly during its installation process. Each installed pile could have a gr
Jan 1, 1999
-
Installation Of Bored Pile Casings Through An Asbestos Tip By Rotary DisplacementBy Lewis Stansfield
A rotary displacement method was used to install permanent steel casings for bored piles through an asbestos tip. This method was chosen in preference to alternative driven systems because it was quie
Jan 1, 2000
-
Skilled Operative Training For The Foundation Industry - SummaryBy Geoffrey Birch
A skilled and efficient workforce is a pre-requisite for the success of modern construction companies. The drive for improved performance, innovation and best value must be matched by the enhanced ski
Jan 1, 2000
-
Application Of Electro-Kinetics To Expedite Pile Setup In Kaolinite ClayBy Susheel R. Kolwalkar
A significant increase in the side shear capacity over a period of time is often observed in case of driven piles. This phenomenon is referred to as ?setup? or ?freeze?. This phenomenon cannot be pred
Jan 1, 2008
-
Geojet®-Turbojet® - A Deep Mixing Method For The Solution Of Geotechnical ProblemsBy Maurizio Siepi
The realisation of most of the civil engineering works is subordinate to the execution of consolidation works, in order to improve the soil physical-mechanics characteristics. The works classifiable w
Jan 1, 2002
-
New Method for Reduction of Settlement Drilling Casings for Steel Core PilesBy Larsson Lars-Erik, Rani Isa, Martin Jönsson, Håkan Bredenberg, Mats Larsson
"IntroductionSteel Core Piles are used extensively in Scandinavian countries, where hard rock is found within reasonable depths. A steel core is cast into a drilled steel tube casing and a rock hole i
Jan 1, 2014
-
Jetting-Assisted Sheet Pile DrivingBy Marie-Pierre Bourdouxhe-Barnich
Since 1997, in partnership with the Laboratoire Central des Ponts et Chaussées in Strasbourg, ProfilARBED has been carrying out a vast study to qualify the improvements jetting can make to vibratory d
Jan 1, 2002
-
Evaluating Efficiency of Geo5 in the Analysis of Pile FoundationBy Elizabeth Varghese, Sanket Rawat, Prachuryya Kaushik, Ravi Kant Mittal
"Geo5 Software is gaining popularity worldwide due to its expediency in analysis and design of pile foundation. The analysis is based on various theoretical, empirical and semi-empirical methods avail
Jan 1, 2017
-
A Comparison Of Static And Statnamic Load Tests In Sand: A Case Study Of The Bayou Chico Bridge In Pensacola, Florida ? SummaryBy Michael D. Justason
This paper details the static and Statnamic load testing on a 600 mm square pre-stressed concrete pile. The pile was located at Pier 15 on the 20 million-dollar Bayou Chico Bridge Project in Pensacola
Jan 1, 1997
-
A Quality Control System For Augered Cast-In-Place Pile InstallationBy George G. Goble
The use of augercast piles has been limited by the engineer's concern for the structural quality of the installed pile. The nature of the pile is such that its final structural continuity is very
Jan 1, 1997
-
Foundation Design and Construction Challenges with Marsh Deposits in a High Seismic Risk ZoneBy M. Reza Saberi, T. Ted Miyake
Driven piles are a common tool in any engineer’s toolbox for supporting large structures over very soft ground, especially in high seismic risk zones. Challenges include achieving sufficient vertical
Jan 1, 2018
-
Axial Cyclic Degradation of Marine Piles: A Strain-Based Fatigue LimitBy Aaron S. Bradshaw, Ryan M. Coulson
The offshore wind industry in the United States is slowly emerging with the recent construction of the first offshore wind farm located off the coast of Rhode Island. The turbines at the Block Island
Jan 1, 2018
-
Case History: Use Of Rock-Socketed Augered Cast-In-Place PilesBy Tracy Brettmann
The use of rock-socketed Augered Cast-In-Place (ACIP) piles is new to the Austin and central Texas region. This case history describes the design methodology, load test results, quality control proced
Jan 1, 1998
-
The Use Of Stone Columns On Settlement And Liquefaction Susceptible SoilsBy Ivan Jackson Madura
The new Paradisus Coco Beach Resort in Rio Grande (PR) is located on an old swamp area, which has been filled with relatively clean to silty sands. The swampy deposits consists of organic silts, peat
Jan 1, 2002
-
Lateral Load Capacity of Helical Piles in SandBy Balu E. George, Subhadeep Banerjee, Shailesh R. Gandhi
"A three-dimensional analysis of laterally loaded helical piles installed in cohesionless soil is presented. Finite Element Analysis was conducted using commercially available Plaxis 3D AE version, as
Jan 1, 2017
-
Application Of Neurofuzzy Approach To Estimate Duration And Evaluate Delay For Diaphragm Wall And Barrette ConstructionBy Thoedtida Thipparat
The diaphragm walls and barrettes are very important to the constructions of multi-storeyed buildings, elevated expressways, subway railway stations, etc. Uncertainties particularly increase in accord
Jan 1, 2006
-
Diaphragm Walls Seismic Design According to the EurocodesBy J. Matos e Silva
"Abstract Although one can think that it is very low the probability of a seism occurrence during the execution of an excavation in an urban lot protected by a diaphragm wall curtain, reality shows th
Jan 1, 2014
-
A Case History Studying On Displacement Controlling In Deep ExcavationBy Feng Yongxuan
Anchored sheep pile is normally used in deep excavations, many of which only require stability in accordance with Terzaghi theory. In this paper, based on the experience, new lateral earth pressure me
Jan 1, 1991
-
Construction Of Pile Foundation For Railway ViaductsBy M. D. Khattar
The paper describes the salient construction features of the Pile foundation work for the Railway viaducts in Algeria. Six viaducts were constructed for execution of the Railway line between Aintemouc
Jan 1, 1989
-
Production And Testing Of 600 Reinforced-Concrete Piles For The Central Bank Of IraqBy H. Meseck
The new building of the Central Bank of Iraq in Baghdad was footed in difficult underground conditions on more than 600 reinforced concrete driven piles, with cross-sectional diameters of 45 x 45 cm a
Jan 1, 1989