Rockpass Stability And Rehabilitation At AngloGold Ashanti?s Tau Lekoa MineBy G. B. Dukes
Scaling of rockpasses was problematic at Tau Lekoa Mine prior to production commencing in 1991. High horizontal stress levels relative to the host rock mass strength have been instrumental in causing
Jan 1, 2006
-
The Application Of Multi-Parametric Block Models To The Mining Process (63e50f28-b646-4a6d-8d50-bd8beecc9a2a)The development of 3D multi-parametric models facilitate the provision of resource information well in advance of the mining face. Using the model, one can evaluate mining areas not only for grade and
Jan 1, 2007
-
Physico-chemical properties and transition metal complex formation in alkali pyrosulphate and hydrogen sulphate meltsBy H. Hamma, R. Fehrmann, M. Gaune-Escard, G. Hatem, S. B. Rasmussen, K. M. Eriksen
The molten salts M2S2O7and MHSO4, the binary molten salt systems M2S2O7-MHSO4and the molten salt-gas systems M2S2O7-V2O5and M2S2O7-M2SO4-V2O5(M = Na, K, Rb, Cs) in O2, SO2and Ar atmospheres have been
Jan 1, 2004
-
A Case Study Of High-Temperature Corrosion In Rotary Cement KilnsBy J. H. Potgieter
This paper describes two cases of corrosion that occurred in dry-process, rotary, cement-clinker kilns. In the case of the kiln with five pre-heater stages, the attack occurred primarily from sulphate
Jan 1, 2004
-
Capping and Kriging Grades with Long-Tailed DistributionsBy M. Maleki
Variogram analysis and kriging lack robustness in the presence of outliers and data with long-tailed distributions, which often arises when estimating grades in precious metal deposits. The capping te
Jan 1, 2014
-
Foreword (5cd4104b-2719-4b5f-9b35-542aaddf3a8e)By Paul Fouche
The past decade has seen a tremendous revival of the base metal industry in Africa, coupled with an unprecedented increase in the prices of base metal commodities in the last couple of years. The them
Jan 1, 2007
-
Guaigui Multipurpose Project Rock Slope StabilityBy Bjørn Nilsen, Werner Stefanussen
The construction of the Guaigui Multipurpose Project includes a 74 metre high concrete face rock fill dam, a 350 metre long diversion tunnel and a 350 metre long spillway tunnel. The topography in the
Jan 1, 2006
-
The Importance of People in the Process of Converting a Narrow Tabular Hardrock Mine to MechanizationBy D. Vogt, T. Hattingh
"This paper argues that the technology change to mechanization is also going to require a change in people. It presents a model for technological progress and adapts it to the mining industry. It then
Jan 1, 2016
-
Online Measurement Of Factors Influencing The Electrostatic Separation Of Mineral SandsBy J. M. Lottering
Paper written on project work carried out in partial fulfilment of B Eng (Chem) degree Operational factors influencing the electrostatic separation of mineral sands were investigated in a laborator
Jan 1, 2006
-
The Use And Applicability Of Flow Models To Quantify Intermine Flow In The Western Witbank CoalfieldsAfter the closure of collieries, they naturally start to fill up with water. As a result, hydraulic gradients develop between them and different hydraulic pressures are exerted onto peripheral areas o
Jan 1, 2005
-
An Improved Dc-Arc Process For Chromite SmeltingBy J. P. W. Bennie, A. de Jong, G. M. Denton
Mintek together with Middelburg Steel & Alloys, developed the DC arc furnace process for the production of ferroalloys with the expressed objective of smelting ore fines (<1mm) without the need for ag
Jan 1, 2004
-
New Pillar Strength Formula For South African CoalBy J. N. Van der Merwe
The data base of failed pillar cases as used by Salamon and Munro (1967) in their original analysis to determine the strength of coal pillars empirically, has been updated for this study. It is shown
Jan 1, 2003
-
Hydrothermal Preparation of Biochar from Pent Coffee Grounds, and its Application for the Removal of Cadmium from Coal Tailings LeachateBy R. Weideman, M. Le Roux, F. B. Waanders, Q. P. Campbell, E. Fosso-Kankeu, D. Moyakhe
"*Paper written on project work carried out in partial fulfilment of B.Eng (Chemical Engineering) degreeSynopsisSpent coffee grounds were transformed into biochar using a hydrothermal method. Some of
Jul 1, 2019
-
1.2 McWha - Manufacture And Use Of Reference MaterialsBy Mike McWha
Drivers to increasing RM use ?Compliance issues ?Section 12 JSE Listing Rules ?Canadian NI 43-101 ?Sarbanes Oxley ?Shortage of African ore reference materials ?Poor perceptions about quality
Jan 1, 2005
-
Pillar Failure in Deep Coal Seams: Numerical SimulationBy S. Badr, R. Mendoza, M. U. Ozbay, M. D. G. Salamon
ABSTRACT: The use of coal pillars at depth is fraught with problems due roof control difficulties and the possible occurrence of coal or pillar bumps. In the USA the largest and most important applic
Jan 1, 2003
-
A new preparation scheme for a difficult-to-float coking coal by column flotation following grindingBy Yijun Caoa, Xiuxiang Taoc, Zhongbo Hub, Yinfei Liaoa
A new preparation scheme for a difficult-to-float coking coal from the Kailuan Mine, Tangshan, China was investigated. The results showed that grinding followed by column flotation was beneficial for
Jan 1, 2015
-
The Balancing Act Of Size Vs. Cost Vs. PracticalityBy Org de Wet
This paper summarises the strategy for selection between a two module coal plant incorporating large, but less equipment, and a three module coal plant with more but smaller equipment. The two options
Jan 1, 2006
-
DC Furnace Containment Vessel Design Using Computational Fluid DynamicsBy M. Shapiro, L. A. le Grange, B. Henning
Effective pyrometallurgical process vessel design requires accurate assessment of the heat fluxes through the walls of the furnace. This is particularly important for freeze lining operation which is
Jan 1, 2004
-
Formation and stabilization of rock cavern roof archesBy M. Lu, E. Broch
Abstract: The formation and mechanism of rock cavern roof arches are studied and effects of rockbolts reinforcement are evaluated. It is concluded that a self-supported roof arch may be formed by the
Jan 1, 2003
-
The Application Of Numerical Modelling To The Design Of Electric FurnacesBy T. Plikas, L. H. Gunnewiek, L. Oshinowo
Electric furnace smelting is one of the principal unit operations for ferroalloy production, and increased process intensity, improved availability, minimal maintenance and a lon
Jan 1, 2004