Search Documents

Sort by

  • AUSIMM
    Establishing the Design Parameters of a Control Blast for Long-term Stability of the Hang Wall at Rampura Agucha Mine

    By R Shrimali, P Rajmeny, L Shekhawat, A Joshi

    Rampura Agucha open pit mine has successfully been excavated to a depth of 320 m, incorporating multistage working. The key to success is the implementation of presplitting as control blast measures a

    Aug 24, 2015

  • IMMS
    Establishment Of The Endeavour Hydrothermal Vents Marine Protected Area

    By S. Kim Juniper

    The discovery of chemosynthetic-based ecosystems at hydrothermal vents in the deep ocean was arguably one of the most important findings in biological science in the latter half of the 20th century. M

    Jan 1, 2001

  • AIME
    Estimated Rock Stresses At Morrow Point Underground Power Plant From Earthquakes And Underground Nuclear Blasts

    By R. B. Campbell

    One of the three power plants that will be in the Curecanti Unit of the Bureau of Reclamation's Colorado River Storage Project is the power plant at Morrow Point Dam. Presently under construction

    Jan 1, 1968

  • AUSIMM
    Estimating Comminution Indices from Ore Mineralogy, Chemistry and Drill Core Logging

    By R Berry, J Hunt, T Kojovic

    Geometallurgy aids the understanding of orebody variability through the integration of geological and processing information, thereby enabling spatial mapping of processing (eg comminution or separati

    Sep 29, 2013

  • SME
    Estimating Dewatering Rates And Designing Deep-Well Dewatering Systems For Open-Pit Mines By Use Of Numerical Simulation

    By E. Scott Bair

    Renewed interest in the vast reserves of anthracite coal in eastern Pennsylvania led to the use of a numerical model for simulating the hydrologic effects of constructing an open-pit anthracite mine.

    Jan 1, 1980

  • DFI
    Estimating Kinematic Demands From Lateral Ground Deformations On Pile-Supported Wharves

    By Arash Khosravifar Ph. D. P. E., Thomas Torkelson P. E., Milad Souri Ph. D. P. E.

    Kinematic demands from lateral ground deformations can be a major cause of damage to maritime and highway transportation structures such as wharves, piers, and bridges. These kinematic demands are dif

    Oct 1, 2022

  • SME
    Estimating Life Cycle Greenhouse Gas Emissions For A Surface Coal Mine

    By O. Ditsele

    Coal plays an important role in the energy needs of the World. Given its wide abundance and low cost, coal use is bound to increase with the growing energy demand. Despite its importance, there are gr

    Jan 1, 2010

  • CIM
    Estimating Loading on Rebar Bolts Using Distributed Optical Sensing Technology

    By D. Beneteau, L. Feldman, D. Milne, A. Hyett, G. Snell

    "Behaviour of rebar bolts subjected to combined shear and bending in underground potash mining applications is not well understood. An experimental investigation compared load applied to resin-grouted

    Jan 1, 2019

  • AUSIMM
    Estimating Mine Operating Costs - Trials and Tribulations

    The projection of operating costs for mining, processing, and other site operating costs is an exercise which can be fraught with considerable peril. Not only are the physical characteristics of eac

    Jan 1, 1990

  • SAIMM
    Estimating Mine Planning Software Utilization for Decision-Making Strategies in the South African Coal Mining Sector

    By T. Celik, B. Genc, C. Musingwini

    "Mine planning software continues to be an important factor when it comes to the development of the South African mining industry. To contribute to this development, a new methodology to define and me

    Jan 1, 2016

  • SME
    Estimating Post-Mining Pit Lake Geochemistry Utilizing Geochemical And Numerical Modeling

    By D. A. Bird

    Geochemical models using published thermo-dynamic data and laboratory derived kinetic rate laws allow prediction of post-closure pit lake geochemistry at open pit mining sites. A combination of "forwa

    Jan 1, 1994

  • SME
    Estimating Process Design Gold Extraction, Leach Residence Time and Cyanide Consumption for High Cyanide-Consuming Gold Ore

    By G. Plenge, M. Brittan

    "Plant design parameters for gold extraction, leach residence time and cyanide consumption are generally determined from standard bench-scale bottle roll or agitation leach tests. The application of l

    Jan 1, 2015

  • SME
    Estimating Recoverable Reserves: Developments In Geostatistical Ore Reserve Estimation (6233c2f1-d6b2-4041-9d9a-0a3cb963948b)

    The accurate estimation of ore reserves along with capital and operating costs are two key components to the successful outcome of any feasibility study. In recent years, there have been many project

    Jan 1, 1994

  • AUSIMM
    Estimating Reserves Of Stone And Sand For Use By The Construction Industry

    It is no longer possible to establish a quarry on the most convenient hill then abandon the site, leaving a scar if the stone or sand in the deposit is found to be unsatisfactory. Before approval i

    Jan 1, 1979

  • SME-ICGCM
    Estimating Rock Mechanics Parameters through Shear Wave Analysis with Well Cad

    By William R. Kohl, Craig B. Clemmens

    "Since 2010, North Central Resources, Bridgeport, WV, has been using the sonic log to estimate the rockmechanics properties of the coal and adjacent strata in their exploration drilling program. In 68

    Jan 1, 2015

  • AUSIMM
    Estimating Sampling and Analytical Errors of Multiple Source Mine Output Blended into a Shipping Product

    Most internationally traded iron ore resources are derived from multiple mine sites, transported to a port facility where they are blended and possibly further processed prior to shipping. Provided th

    Mar 1, 2010

  • SME
    Estimating Secondary Mining Potential Of Inactive And Abandoned Appalachian Highwalls

    By D. E. Hinkle

    Past surface-mining operations in Appalachia primarily followed mountain con-tours. It is estimated that about 18,000 mi. of highwalls are exposed throughout Appalachia. An evaluation procedure for de

    Jan 1, 1989

  • SME
    Estimating Site Closure Costs A Critical Tool For Reclamation Planning

    By T. Hawthorne, H. Barnes

    Homestake Mining Company has developed an estimating model, based on other closed projects, to audit and prepare new estimating plans. The results of recent closure audits reveal that the original bu

    Jan 1, 2000

  • NIOSH
    Estimating the Crush. Zone Size under a Cutting Tool in Coal

    By R. Karl Zipf, Z. T. Bieniawski

    "SummaryAs part of an effort.to understand the mechanics of fine fragment formation in coal, which is important in studies of respirable dust due to mining, fracture toughness measurements and the str

    Aug 31, 1989

  • CIM
    Estimating the Energy Recovery Potential of Newmont’s Carlin Mine Dry Grinding Circuit

    By Aidan Giblett, Michael McGlynn, Peter Radziszewski

    "On the basis that 99% of the energy input into a mill is converted into heat, it is possible to estimate the amount of energy captured in the slurry, the amount that is lost to the environment as wel

    Jan 1, 2016