The effect of operating conditions on stratification kinetics in a batch jig, L.C. Woollacott, A.K. Tripathy, and J.H. PotgieterBy L. C. Woollacott, A. K. Tripathy, J. H. Potgieter
This paper presents the second of a two part study on density stratification in a laboratory batch jig. The first study, reported elsewhere, investigated the effect of operating conditions on the stra
Jan 1, 2020
-
Dependence of solar reflector soiling on location relative to a ferromanganese smelterBy K. J. Craig, M. A. Swart, Q. G. Reynolds, L. Hockaday
A solar reflector soiling study was carried out at a ferromanganese smelter in South Africa to assess the soiling rates at different locations around the plant. Several meteorological parameters were
Jun 5, 2023
-
A process mineralogical study to improve beneficiation efficiencies of Dwarsrivier chromite – A digital approach using automated mineralogy APCOM 2021By S. Blancher, A. Perroton, H Smith, T. Nzima, T. Wallmach, V. Dieudonné
Chromite beneficiation is generally performed by crushing and density separation using spirals. At the Dwarsrivier Chrome mine spiral efficiencies seam to vary, the reason for which is not evident. T
Sep 1, 2021
-
Seminar on Reactivity of Lime in Steel MakingA Seminar to discuss 'Reactivity of Line in Steel Making' was held in the auditorium of Iscor's Headquarters Building in Pretoria on the 5th August, 1971. The Institute organised thi
-
Best Practice Sampling Methods, Assay Techniques, And Quality Control With Reference To The Platinum Group Elements (Pges)By K. Lomberg
In this paper the process of sampling and assaying as it relates in particular to the platinum group elements (PGEs) is presented. A discussion of the geology of PGE deposits is included to provide an
Jan 1, 2014
-
Co-firing of high-ash discard coal and refuse-derived fuel – ash and gaseous emissionsBy K. Isaac, S. O. Bada
This research focuses on the co-firing of discard coal with refuse-derived fuel (RDF) to utilize this abundant resource in South Africa for energy generation and reduce the volume of waste disposed of
Aug 2, 2022
-
Determination of rhodium from fire assay using lead collection with the addition of co-collector, followed by acid dissolution to enhance recovery and analytical accuracyBy R. Letsaole, H. Mabowa, J. Sehat, J. Tshilongo, T. Rampfumedzi, N. Ntsasa, A. Mkhohlakal1
This study explores the use of co-collectors to enhance the recovery and determination of rhodium during fire assay with lead collection, followed by acid dissolution using conventional hot plate meth
Mar 6, 2026
-
Fines generation from South African manganese ores during preheating in a rotary kilnBy M. S. Moholwa, J. D. Steenkamp, H. L. Rutto
Manganese ores are the major source of manganese for the production of manganese ferroalloys. There is a gap in the knowledge of the decrepitation behaviour of manganese ores, which presents a problem
Nov 30, 2022
-
Development of a Method for Evaluating Raw Materials for Use in Iron Ore Sinter in Terms of Lime AssimilationBy W. Ferreira
Steel is produced in a basic oxygen furnace from hot metal obtained from a blast furnace. A sintered iron ore with good hightemperature properties (strength and permeability) should be used as feed to
Jan 1, 2014
-
Mineralogical analysis of different components in waste printed circuit boards, Xiang-nan Zhua, Chun-chen Nie, Hao Zhang, Yue-xian Yu, Jun Qiu, Lin Li a, and Xian-jun LyuaBy Xiang-nan Zhu, Hao Zhang, Lin Li, Jun Qiu, Yue-xian Yu, Chun-chen Nie, Xian-jun Lyua
Waste printed circuit boards (WPCBs) are excellent metal resources. Mineralogical characteristics of different components in WPCBs were analysed in this study. Organic-enriched particles, fibreglass-e
Jan 1, 2020
-
Stability Problems And Rock Support At The Tellnes Open Pit Mine, NorwayBy Bjørn Nilsen, Brian J. Ballou
The Tellnes open pit mine in Southwestern Norway has been operating since 1960. The maximum height of pit walls is currently about 150 meters with the current mine plan extending this distance to 400
Jan 1, 2006
-
Liner Optimisation To Improve Availability Of The Ridgeway SAG Mill (ce87862d-0ddc-4fb1-a4ed-b071f2daa7ac)Mill relining is a major contributor to overall plant downtime. Reducing the number of mill liner pieces removed from and replaced in the mill has a direct impact on the overall reline time and in tur
Jan 1, 2007
-
Skorpion Zinc: optimization and innovation - SynopsisThe Skorpion process comprises three processing steps-atmospheric leaching in sulfuric acid, zinc solvent extraction and electrowinning to produce special high grade zinc. The major mode of impurity t
Jan 1, 2007
-
Analysis of pressure drop and hold-up during vertical transport of limestone slurry in lean phase and heterogeneous regimeBy J. K. Pothal, S. Basu, R. Barik, P. K. Senapati, A. Dubey
The aim of this paper is to study the characteristics of limestone particles (size varies from 4 mm to 20 mm) during its transportation from open cast mines through pipes. The influence of four differ
Mar 4, 2025
-
1.4 Oats ? ?Why MMCRM?s??By Christopher J. Oates
Overview ? Mining Codes ? Best Practice ? Mining Standards Guidelines ? Get it right from the start ? External Auditors ? The 5% rule ? MMCRM's - The Key Components ? The MMCRM Report /
Jan 1, 2005
-
Removal Of Unburned Carbon From Fly Ash Using A Cyclonic-Static Microbubble Flotation Column - SynopsisBy Y. J. Cao
The purpose of this study was to investigate the flotation behaviour of unburned carbon in a cyclonic-static microbubble flotation column (FCSMC). The ash sample, collected from a power station in Gua
Jan 1, 2012
-
Estimation of Lateritic-Type OrebodiesBy A. G. Journel, CH. Huijbregts
"Centre de Morphologie MathématiqueSpecial problems arise in the evaluation of lateritic-type orebodies (Ni-Co, bauxite) or, more generally, orebodies affected by surface weathering. In this type of o
Jan 1, 2014
-
KX36-Rediscovering The Diamond Exploration Potential Of The Central Kalahari In BotswanaBy A. J. Rogers
The KX36 kimberlite was discovered using a high-resolution gradient aeromagnetic survey, with follow-up detailed ground geophysics and deflation soil sampling used to assess and prioritize the geophys
Jul 1, 2013
-
The Application of Ductile Support Methods in Alpine TunnelsBy B. Moritz, W. Schubert, E. A. Button
ABSTRACT: Geological conditions associated with alpine environments in combination with high overburden in many tunnelling projects lead to squeezing behaviour. The main problems associated with such
Jan 1, 2003
-
Lean construction: Implementing the Last Planner System on mining projectsBy M. C. Bekker, T. Govindasamy
The potential benefits of implementing the Last Planner System (LPS) on mining infrastructure projects were explored through two case studies in the South African mining industry. The first part of th