    TBM Recovery Shaft Construction - SR-99 Tunnel

    By Lance Rasband, Richard Hanke, John Starcevich

    "The 17.4 meter (57 ft) diameter tunnel boring machine (TBM), the world’s largest at the time of her launch in 2012, locally referred to as “Bertha,” is stuck. Incapacitated due to mechanical failure

    Jan 1, 2016

  • DFI
    Underpinning and Temporary Earth Retention for the ReTRAC Trench in Reno

    By K. Ronald Chapman, Claus Ludwig, Doug Jenevein

    "In the spring of 2005 Schnabel Foundation Company completed a $15.2 million Design/Build subcontract to underpin 11 structures, and provide 202,800 square feet of earth retention for the Reno Transpo

    Jan 1, 2006

  • DFI
    Interactive 3-Dimensional Modeling of Anchors at Bluestone Dam

    By Jamey Rosen, Georgette Hlepas

    "Bluestone Dam is a concrete gravity structure with an overall length of 2,060 feet and a maximum height of 165 feet above the streambed. Several major project modification designs have been implement

    Jan 1, 2016

  • DFI
    A Case History On Design, Construction, And Performance Of Stone Column Ground Improvement Beneath An Mse Embankment

    By Karen Dawson

    This paper presents a case study of the deformation-based design, construction, and performance of stone column ground improvement (GI) beneath a mechanically stabilized earth (MSE) wall and bridge ab

  • DFI
    Construction Of A New Quay Wall For A Sea Tank Terminal In The Port Of Antwerp

    By Stefan Mewes

    Europe’s second-largest seaport has installed a new combi wall consisting of pipe piles, sheet piles and inclined shaft grouted piles to support it. The new Liebherr piling rig with swinging leader wa

    Sep 1, 2022

  • DFI
    Screening Tool for Impact Hammer Selection

    By Gerald Verbeek, David Tara

    "When selecting an impact hammer to drive a particular pile, the decision is often based on local experience. In those cases, the contractor falls back on previous experience or draws on the experienc

    Jan 1, 2017

  • DFI
    Woodrow Wilson Bridge Cofferdams

    By Roderic A. Ellman

    The new Woodrow Wilson Bridge (WWB) will replace the existing bridge over the Potomac River to connect Alexandria, Virginia to Prince Georges County, Maryland. The new WWB will extend approximately 1.

    Jan 1, 2005

  • DFI
    Design Of The Marine Foundations For The Skyway Project Of The San Francisco Oakland Bay Bridge

    By Gerry Houlahan

    The east span of the 3.5 km long SF-Oakland Bay Bridge is supported by different types of foundations along its span. Starting from the west, its first 460 m section comprising twin concrete box-girde

    Jan 1, 2013

  • DFI
    Utilizing Drones to Improve Project Workflows

    By Barritt Lovelace

    Collins Engineers has been researching and implementing the use of drones on Civil Engineering Projects since 2015. Applications include bridge inspection, asset management, mapping, construction site

    Jan 1, 2019

  • DFI
    Interactive Encased Stone-Column Foundation - Synopsis

    By P. M. Deshpande

    An interactive short column system is evolved as alternative to deep foundation system in deep layers of marine clay, the interaction of encased stone column and marine clay carry load without causing

    Jan 1, 1996

  • DFI
    Design Build & Failure: Perils at a High Risk Shoring and Retaining Wall Project.

    By Mark Spence, Tom Lardner, Matthew Janes

    "IntroductionThe design-build method streamlines project delivery through a single contract between the Contract manager and the design-build team. The design-build method places emphasis on collabora

    Jan 1, 2015

  • DFI
    Design And Analysis Of Cooling Tower Pile Foundations

    By Michael W. Oakland

    This paper summarizes the analysis and design of a pile foundation system for two 400 ft. diameter, 500 ft. high cooling tower using a detailed finite element analysis package. The cooling towers are

    Jan 1, 2010

  • DFI
    Pile Settlement Design Using Continuous Surface Wave Testing And Modulus Degradation

    By Hennie F. T. Barnard

    Where geotechnical designs are governed by settlement requirements, soil and rock moduli are important parameters for design. This paper reports on a method that was used to utilize dynamic modulus me

  • DFI
    Pile Settlement Design Using Continuous Surface Wave Testing and Modulus Degradation (9593f752-8bd1-4766-938c-27b4baad33f2)

    By Hennie F. T. Barnard, Theodore E. B. Vorster

    Where geotechnical designs are governed by settlement requirements, soil and rock moduli are important parameters for design. This paper reports on a method that was used to utilize dynamic modulus me

    Jan 1, 2017

  • DFI
    Laboratory Validation Of In-Situ Tests - 1. Introduction

    This paper summarizes seven years of Italian ex­perience with the use of large calibration chambers for the calibration, under closely controlled stress and strain conditions, of some in situ testing

    Jan 1, 1987

  • DFI
    Engineering Sustainability

    "What can we do in ground engineering to reduce damage to the environment, to repair historic pollution, to reduce our demand on basic resources and to reduce the carbon footprint of our industry? Som

    Jan 1, 2009

  • DFI
    Session 30 "Grouting for Tunnels 2"

    By Raymond Henn

    Yes we have also used some however, again because of the nature of the maintenance window where we have that two hour (at best) window every night and due to the numerous other crews that are wanting

    Feb 10, 2003

  • DFI
    OPA Contender Features Innovative ACIP Pile Test

    By Andres M. Baquerizo, Matthew E. Meyer, Carlos Ortiz

    "The Metropolitan Miami development, a downtown mixed-use complex developed by Miami-based MDM Development Group, has weathered the economic downturn by adapting to the needs and pressures of the loca

    Jan 1, 2012

  • DFI
    The Resonant Driver: Ultra High Frequency Pile And Casing Installation

    By Matthew Janes

    The installation of piles and casings is becoming increasingly difficult as restrictions on vibration become common in major urban areas. The use of high frequency, resonant excitation of a pile or c

    Jan 1, 2008

  • DFI
    Retaining Structure for Berth at Krishnapatnam

    By P. V. Chandramohan

    "The paper deals with the arrangement of structural members for a retaining structure used as a berth in the port of Krishnapatnam. The height of retention is 24.3m. A T-shaped diaphragm wall acts as

    Jan 1, 2015