South 196th/200th Street Corridor And Bridge Crossing, Kent, WashingtonBy James Su
The Green River Valley in Kent, Washington, is a fast growing area containing retail facilities, warehouse factories and industrial businesses, including the Boeing Space Center. Traffic from Intersta
Jan 1, 1998
-
Quality Control Of Augered Cast-In-Place And Displacement Piles ? IntroductionBy Rudolph P. Frizzi
Quality control is essential for augered cast-in-place (ACIP) piles (also known as continuous flight auger (CFA) piles outside the United States) and augered displacement (AD) piles since the pile is
Jan 1, 2002
-
Woodrow Wilson Bridge Cofferdams (ef6ed0b3-5c8c-41f1-8337-00ee57bff823)By Roderic A. Ellman
The new Woodrow Wilson Bridge (WWB) will replace the existing bridge over the Potomac River to connect Alexandria, Virginia to Prince Georges County, Maryland. The new WWB will extend approximately 1.
Jan 1, 2013
-
Prediction Of Jet Grout Column Diameter In Cohesive SoilBy Chu E. Ho
Current methods of determining jet grout column diameters are highly empirical and site specific, and do not take into account the jet hydrodynamics and soil parameters explicitly. A theoretical model
Jan 1, 2006
-
United States Capitol Visitor Center - Drilled Shafts, Utility Conflicts, And CommunicationBy Giovanni A. Bonita
The United States Capitol Visitor Center (USCVC) is one of the largest underground structures ever constructed in the Washington, DC, metropolitan area. The 600,000 ft2 (55,750 m2) structure is entir
Jan 1, 2006
-
Mini-Pile Design And Construction Methods Change To Mitigate Soil Loss Through Glacial TillBy Cassandra A. Wetzel
Rock socketed mini-piles are a desirable foundation alternative when design capacity is more than 40 tons and there is limited access. In this case history mini-piles were designed to support between
-
Supported Excavation Movement Causing Lateral Displacement and Cracks in Drilled Shafts - Lessons Learned from a Case Study in ChicagoBy Eric R. Borys, Amaneh E. Kenarsari, Brett Gitskin
This case study discusses impacts of excessive Earth Retention System (ERS) lateral movement at a project in city of Chicago. The ERS (cantilevered sheeting) moved inward towards the excavation and ca
Jan 1, 2018
-
Construction Of A Continuous Flight Auger Secant Wall: Chattahoochee Water Treatment Plant, Atlanta, Georgia - Project DetailsBy Gordon King
The City of Atlanta Water Department required the construction of a two sludge tanks and a wet well at the existing Chattahoochee Water Treatment Plant. Western Summit won a design build contract to b
Jan 1, 2003
-
100-Day Document - Mandatory Discussion, Mediation And Arbitration Of Construction Disputes ? 1.0 Coverage1.1 The parties agree to submit all claims, disputes or controversies arising out of, or in relation to, the interpretation, application or enforcement of this agreement, including dispute resolution
Jan 1, 1994
-
Numerical Analysis of Pile-Supported T-Walls Subject to Large Settlements and Flood LoadingBy Alexander B. Reeb, Richard J. Varuso, George M. Filz, Jehu B. Johnson
"T-walls, which are concrete floodwalls in an inverted “T” shape, are an integral component of the Greater New Orleans Hurricane and Storm Damage Risk Reduction System (HSDRRS). In order to resist lar
Jan 1, 2017
-
Value Engineering of Reinforcement used in Large Diameter Drilled ShaftsBy Shahid Islam, Lucian Bogdan
Deep and large diameter drilled shafts use mostly bundles of Grade 60 (415 MPa) reinforcing bars as longitudinal reinforcement with rebar splices to make it longer. Lower Grade steel requires large nu
Jan 1, 2018
-
Design And Construction Of An Earth Retaining Structure - Using A Pile In Self-Hardening Grout (PSHG) WallBy Allan Sylvester
Construction of the Shot Tower Metro Station in Baltimore, Maryland was performed in two phases. In the first phase, a contractor was retained to excavate the station in order to construct twin tunnel
Jan 1, 1997
-
Efficacy and Execution of Floating Lattice-Shaped Cement Treatment against LiquefactionBy Sachihiko Tokunaga, Hirofumi Taguchi, Kenji Maruyama, Hidenori Takahashi, Yoshiyuki Morikawa
"Abstract The present study proposed a new liquefaction countermeasure to improve sandy ground and conducted a trial execution. The new method is a floating-type and lattice-shaped cement treatment me
Jan 1, 2014
-
Evaluation Of Design Methods For Tieback Retaining Walls In Seattle - IntroductionBy John P. Turner
The behavior of tieback retaining walls depends on many factors, including soil properties, groundwater conditions, construction sequence, spacing and stiffness of tiebacks and soldier piles, tieback
Jan 1, 1990
-
Berminghammer II 25 Vertical Travel Lead System: Innovative Technology For Deep Foundation Soil Mixing - 0.0 IntroductionBy Andy Schroeder
Located in Hamilton, Ontario Canada, Berminghammer Foundation Equipment, is a manufacturer of advanced foundation equipment with 30 years of experience. The company is represented in more than 20 coun
Jan 1, 1997
-
The Analysis And Computation Of Soil-Pile (Wall) Interaction For Deep Excavation Of High-Rise BuildingBy Lu Peiyan
A computation model of soil-pile (wall) interaction under lateral loading is presented in this paper. The model has been applied to some engineering projects, and the comparison between computation re
Jan 1, 1991
-
Special Foundation Construction For Large Deep Excavation Pits In Berlin - Summary:By Wolfgang G. Brunner
The center of Berlin is currently a huge jobsite, where international architects, designers, consultants, construction and ground engineers as well as investors take on the challenge of the biggest an
Jan 1, 1999
-
Drivability Of Piles By VibrationBy Don C. Warrington
This paper is a survey of the various methods and research efforts by which the drivability of piles is determined. First, a brief outline of the basic theory and the important parameters for driving
Jan 1, 1989
-
Application Of Hydrofracture Principles To Grouting In Deep Foundation ? SynopsisBy Z. M. Zhang
Fracture grouting is a particular technique which can be used in soils and rocks with low permeability to increase groutability and penetration rates and to solve some special foundation problems by i
Jan 1, 2010
-
Design Of Deep Foundations Over Shallow Mine WorkingsBy Tianfei Liao
Extensive site investigations revealed that abandoned shallow mine workings exist under a site planned for construction of a major new facility. Since the mine voids were susceptible to collapse, they
Jan 1, 2009