Static And Dynamic Tests For Evaluation Of The Vertical Load Bearing Capacity Of Piles - Summary
By Madan B. Karkee
The understanding and the development of sound theoretical basis concerning the pile foundations has been phenomenal during the past few decades, considering the thousands of years the piles have evid
Jan 1, 1997
-
Design And Construction Of The Sutong Bridge Foundations
By Robert B. Bittner
The Sutong Bridge across the lower Yangtze River in China will have, when completed, the longest span (1,088 m) and the highest towers (306 m) of any cable stayed span in the world. The foundations fo
Jan 1, 2007
-
Limited Access Underpinning And Re-Leveling Of A Six-Story Office Building Using Jet Grouted Micropiles
By Tom Szynakiewicz
Micropiles are routinely used in the United States for foundation support and underpinning applications. The high capacities achievable with the use of micropiles, combined with specialty rigs for ea
Jan 1, 2008
-
Compensation Grouting Under Real-Time Monitoring, Rio Piedras Project, San Juan, Puerto Rico - Deep Foundations Institute 25th Annual Meeting And 8th International Conference New York USA, October 5-7, 2000
By Jean-Pierre Hamelin
Ground movements induced by underground excavation are always of critical concern, particularly in urban areas. Compensation grouting now appears as a safe means to control these movements. The paper
Jan 1, 2000
-
Post-Tensioned Diaphragm Wall "T" Panels For Large Unbraced Excavation Spans - Introduction
By Nino Catalano
The combination of two top levels of cross-lot braces designed and installed to act as a truss, and vertical post-tensioning of the panels allow the unbraced excavation of a 36' span. Philoso
Jan 1, 1994
-
Vibwall Installation - Cardiff Bay Barrage ? Synopsis
By Graeme McWhirter
This paper discusses the Installation of a Vibwall for the Cardiff Bay Barrage Project Wales, UK, by Kvaerner Cementation Foundations. Only the second use of the technique in the UK the wall was succe
Jan 1, 2000
-
Excavation Support At The Capitol Visitor Center In Washington DC
By Harald Ludwig
In 2002, excavation support work commenced on the Capitol Visitor Center project located adjacent to the nation?s Capitol building in Washington, D.C. The outlying work (Slurry Wall Work at Main Site
Jan 1, 2006
-
PSEG Lawrenceburg Energy Facility Augered Cast -In-Place Piles Case History
By Chris D. Shewmaker
So you want to install 2,600 augered cast-in-place piles, about 155,000 lineal feet, in 33 working days? It can be done. The Public Service Enterprise Group (PSEG) decided to build a combined cycle po
Jan 1, 2004
-
Use Of Nondestructive Testing To Evaluate Defects In Drilled Shafts: Status Of FHWA Research - Background
By Clyde Baker
Drilled shafts for many situations offer an economical alternative to driven piles. The Federal Highway Administration (FHWA) has spent considerable time and money in research and developing design an
Jan 1, 1989
-
Design and Construction of the Thames Water Lee Tunnel Shafts, London
By Sivilay Sayavong, David Puller, Julian Gatward, David Hard, Martin Stanley
"AbstractThe Thames Water Tideway Tunnels programme involves the upgrade of London’s combined sewer and storm water system. The first section is the Lee Tunnel between the Beckton Sewage Treatment Wor
Jan 1, 2014
-
Dynamic Pile Testing In Soils Exhibiting Set-Up - Introduction
By Juan M. Antorena
A dynamic testing program was performed to evaluate installation procedures, assess capacity of 610-mm (24-inch) diameter open ended steel pipe to evaluate set-up and provide minimum pile tip elevatio
Jan 1, 1995
-
Integrity Testing Of Deep Foundations - Synopsis
By R. T. Stain
Integrity testing of deep foundations is now common practice in Europe, indeed in the City of London such testing is a contractural requirement on every site. This paper is in two parts: Part
Jan 1, 1987
-
Non-Destructive Testing Methods For Drilled Shaft And Acip Piles
By George Piscsalko
There are numerous methods currently available to assess the integrity of drilled shaft and ACIP piles. Each method has its advantages and limitations. This paper will compare the various available me
Jan 1, 2011
-
An Evaluation Of Augered Cast-In-Place Pile Design Methodolgies For Compression Loading In Sand
By Giuliana A. Zelada
This paper reports on a study of 43 compression load tests (five fully instrumented) and ten pullout tests of auger cast-in-place (ACIP) piles in sand. Eight design methods reported in the literature
Jan 1, 2000
-
Case History: Estimating Ground Vibrations Caused By Pile Driving
By Tracy Brettmann
A new method for estimating ground vibrations caused by pile driving was developed as a result of a vibration monitoring program performed for a large pile driving project. The method is accurate, rat
Jan 1, 1999
-
Deep and Extra Deep Diaphragm Walls in Shanghai – Increasing Demand for Infrastructure in Megacities Drives the Requirement of Increasing Depth for Diaphragm Walls
By Wu Jie Mei, Li Yao Liang, Franz-Werner Gerressen, Arthur Bi
Diaphragm walls (D-walls) are known as underground structural elements commonly used for retention systems and permanent foundation elements. In addition, they are also quite often used as deep ground
Jan 1, 2018
-
Minipiles And Postgrouted Bored Piles - Two Techniques For Special Site Conditions - Summary:
By Stefan K. Schwank
The paper describes the two foundation techniques - mini piles and postgrouted bored piles. The mini pile system is presented with its design and installation parameters, especially the drilling techn
Jan 1, 1991
-
[Halliburton / Brown & Root Report] - Brown & Root Civil - GeoJet Foundation System - I. Introduction
By Gordon] [Reavis
Halliburton Services and Brown & Root have developed a unique foundation system that blends oilfield and construction technologies to construct deep foundations which offer significant advantages acro
Jan 1, 1993
-
Fundamental Tests On The Performance Of High Capacity Pin PilesSM
By Donald A. Bruce
Pin Piles are small diameter, bored, cast-in-place piles used to underpin structures. They were first employed over 40 years ago in Italy, and have been used in the U.S. since the late 1970's. Ho
Jan 1, 1993
-
Automated Instrumentation For ACIP And Drilled Displacement Piles - 1. Introduction
By John Lemke
Current practice for monitoring static pile load tests commonly consists of measuring load and displacement at the top of a pile. This is typically accomplished by monitoring dial gauge movements, lin
Jan 1, 2002