    Explosives Malfunction from Sympathetic Detonation to Shock Desensitization

    By C Yeung, G Fitz, R Heater, P D. Katsabanis

    Explosives malfunction due to shock waves is a serious concern for successful blasting results. Malfunction can range from sympathetic detonation to desensitization and modification of firing times of

    Jan 1, 1994

  • ISEE
    What Every Defense Lawyer Wished his Blasting Company Clients Knew

    By Jay P. Tobin

    This paper will address the legal standards applicable to construction blasting lawsuits and offer best practices suggestions for pre-blast inspections, documenting the construction blasting work, rec

    Jan 1, 2015

  • ISEE
    The Effect of Rock Strength on Perimiter Blasting and the "Blastibility" of Massive Rock

    By Qingshou Chen, Paul N. Worsey

    It has been recently argued that rock strength has little effect on the final results of pre-split blasting and is of only minor importance when blasting rock in general. However, it can be shown that

    Jan 1, 1986

  • ISEE
    The Impact of Blasting on Excavation Design - A Geomechanics Approach

    By Cameron McKenzie, John Heilig, Patrick Andrieux, Andree Drolet

    It is widely accepted that both underground and surface blasting operations can de-stabilise excavations to the point where it can threaten the feasibility of mining through personnel safety or OK dil

    Jan 1, 1994

  • ISEE
    South African Blasting Practice in Shaft Sinking

    By Rodney C. Espley-Jones, John C. B Wilson

    South Africa is well known for its shaft sinking exploits, and many of the world's biggest and deepest shafts are to be found there. Blasting practice differs in a number of respects from that followe

    Jan 1, 1979

  • ISEE
    Blasting Cost Minimization at Duvha Opencast

    By S A. Steyn, I P. Douglas

    Duvha Opencast is a large South African dragline operation supplying coal to the Duvha Power Station which is operated by Eskom, the state power utility. For Duvha to remain competitive with other col

    Jan 1, 1991

  • ISEE
    The Use of Explosives to Backfill and Reclaim Former Quarry Sites

    By Conny Postupack, Jim Petrunyak, John Hope

    The authors discuss the concepts, engineering considerations, and cost relationships involved in the use of drilling and blasting to accomplish backfilling and reclamation with minimum use of mechanic

    Jan 1, 1989

  • ISEE
    Blasting with ANFO/Poylstyrene Mixtures

    By Karl Kure, Anders M. Heltzen

    Mixtures of prilled ANFO and 0,5 - 3 mm polystyrene balls are interesting substitutes to the tube charges or other types of reduced explosives or detonation fuses. Experiments have shown detonation ab

    Jan 1, 1980

  • ISEE
    Fragmenting Oversize Boulders

    By J Mensah, G C. Sen

    Often large boulders of rock have to be fragmented in civil or mining engineering operations. These oversize boulders are encountered after primary blasts in both surface and underground excavations o

    Jan 1, 1989

  • ISEE
    Fragment Size Distribution Assessment Using a Digital Image Based Measurement System

    By Mark S. Stagg, Stephen A. Rholl, Steven G. Grannes

    A method of determining the fragment size distribution of rock quarry muckpiles using photographic and digital-image processing techniques has been developed by the Bureau of Mines. To assess the frag

    Jan 1, 1993

  • ISEE
    Application of Air Decking to Blasting - Finding from Numerical Modelling

    By P. D. Katsabanish

    Air decking applications are examined using numerical modelling and the AutodynTM code. The mechanism of damage is illustrated and discussed. Air decking is shown to provide advantages over stemming w

    Jan 1, 2005

  • ISEE
    Submarine Blasting at Palmer Station, Antarctica

    By John Wright

    During June and July 1999 a United States Antarctic Program (USAP) team of three commercial divers and one blaster successMy removed an underwater rock obstruction which interfered with safe docking p

    Jan 1, 2001

  • ISEE
    Emperical Characterization of Oil Shale Fragmentation Experiments

    By P Wapner, C Lo Edwards, S CO Schmidt, J N. Johnson, R Oliver

    Shale oil recovery rates that can be achieved in underground in situ retorts can be strongly influenced by the shale breakage and fragment-size distribution achieved during rubblization. Since the fra

    Jan 1, 1979

  • ISEE
    Improved Blast Results with Variable Density, Gassed Emulsions

    By L D. Lawrence, R S. Day, Gordon Coleman

    Commercial emulsion explosives are typically characterized by their relatively high detonation velocities due to the intimacy of oxidizer and fuel and to their sensitization with glass microballoons.

    Jan 1, 1990

  • ISEE
    Pressure Irregularities in the Loading of Vehicles by Buried Mines

    By Leslie Taylor, W. L. Fourney, Uli Leiste

    Over the past few years, our laboratory has been investigating the loading on vehicles due to the detonation of buried explosives. We have been using target plates to represent the bottom of the vehic

    Jan 1, 2008

  • ISEE
    Presplitting and Collapsing Part of an Old Underground Room and Pillar Mine

    By Dennis Dobson, Keith M. Henderson

    Lone Star Industries, Inc. in Cape Girardeau, Missouri operates an open pit mine to produce limestone for its portland cement manufacturing plant. The present mining method, for safety and legal reaso

    Jan 1, 1997

  • ISEE
    Blast Design of Shafts and Adits in Vibration Sensitive Environments - An Alternative to the "Pie" or "Series" Method-

    By Roger L. Keller

    This paper covers the design and test blast procedures for several drop shafts and edits leading to the completion of a recent Rochester Pure Waters Expansion Project . Due to the projects "in-town" p

    Jan 1, 1991

  • ISEE
    State-of-the-Art Explosive Void Measurement System

    By J P. F Warkentin, A W. Bauer

    Recently, significant improvements have been made in both blast design methods and blasting accessories. The introduction of extremely accurate blast delays now allows proper implementation of advance

    Jan 1, 1991

  • ISEE
    "We Agree to Provide Indemnification, Now What?"

    By Jeff Friedman

    This paper addresses certain problems to be encountered when a blasting contractor agrees to provide indemnification. Nearly 100% of all blasting work is performed pursuant to a contractual agreement.

    Jan 1, 2004

  • ISEE
    Blasting 250 Feet from a Historic Structure

    A case history is presented where a variance was permitted by the court to change a 500 foot limit to 250 feet for blasting overburden at a surface coal mine in the proximity of a historic structure.

    Jan 1, 1991