Comparing Conflicting Conclusions from Different Integrity Testing Methods on the Same Drilled ShaftsBy Alex Ryberg, Matthew L. Becker
Several integrity testing methods exist which may be used to evaluate drilled shafts. Each test method has advantages and limitations. On occasion, the results from different test methods may lead to
Sep 8, 2021
-
Design And Construction Of Underground Basin Using Composite Slurry Wall 500 Feet Away From The Pacific OceanBy Ihab Allam PE, Meeok Kim. PE. Ph. D
The wet weather equalization basin (EB) planned for Pacifica, CA is a 45 feet deep rectangular shaped underground water tank containing over 2.1 million gallons of water, and located only 500 feet awa
-
Helical Pile Foundation Solution for Landfill RedevelopmentBy Kevin Baumgartner, Steven Babcock
A landfill in Phoenix, AZ reached capacity and was graded over in the 1970s. The property was subdivided into lots in 2007 to create a business park. However, the challenging site conditions caused by
Sep 8, 2021
-
Trump International Is OPA Winner"Standing 92 stories high and just over 1,362 ft tall, Chicago’s Trump International Hotel and Tower is perfectly positioned at the center of one of the world’s most impressive skylines.The Tower serv
Jan 1, 2009
-
Bio-Grout Based Soil ImprovementBy Terzis D. PhD, Katterbach M.
While awareness around the environmental impact of existing grout materials and chemical binders is increasing rapidly, biotechnologies are growing traction as sustainable alternatives in groundwork o
May 1, 2022
-
Hudson’s Revitalization: The Use of Robotics in the Work PlaceBy Dave P. DeClerck
Hardman Construction was faced with the challenge of completing a large earth retention project on a constricted downtown Detroit site, while maintaining a safe and productive worksite. To do so, new
Jan 1, 2019
-
Settlement Reducing Auger Cast-In-Place Piles below a Mat Foundation of a 41-Story StructureBy Swaminathan Srinivasan, Aaron J. Muck
"When an opportunity arises to combine state-of-the-art concepts with advanced modeling tools, engineers need to take what they know and apply forward thinking to geotechnical solutions to promote the
Jan 1, 2015
-
Countermeasures Against Soil Liquefaction At Galataport Project In Istanbul, TurkeyBy Carlandrea Albonico, Salvatore Miranda
The paper describes an innovative geotechnical engineering solution that has been provided within the scope of the Galataport Project, in Istanbul, Turkey. Among all interesting geotechnical works inc
Nov 1, 2022
-
Skin Friction In Shale: Results Of The Hwy. 81 Bridge, Yankton, SD Drilled Shaft Load TestBy Scott M. Mackiewicz
This project includes replacement of the historic vertical-lift span Meridian Bridge (U.S. Highway 81 over the Missouri River) that connects Yankton, South Dakota with rural Cedar County, Nebraska. T
Jan 1, 2008
-
The Cosmopolitan Resort & Casino, Las Vegas, NV Specialty Foundation Work Under Extreme ConditionsBy Lawrence Piccagli
This past spring of 2006, BENCOR installed the concrete reinforced diaphragm walls for the COSMOPOLITAN RESORT & CASINO in Las Vegas, Nevada. The project highlights include the excavation of approx. 3
Jan 1, 2007
-
Theoretical Simulation Approach For Load Settlement Characteristics Of Piles In Shale Deposits. - Synopsis :-By Subrata Ray
A large no of power stations are being set up in Chandrapur area having coal deposits. Several industries are also coning up in this area. The subsurface is geologically formed under Gondwana system a
Jan 1, 1996
-
Rock Excavation and Underpinning below a 19-Story BuildingBy Kevin P. Gleckler, Steven C. Highfill
"Escalators to access platforms for the Second Avenue Subway Station at 72nd Street in Manhattan are to be installed in the basement of an existing 19-Story residential building. The escalators, which
Jan 1, 2016
-
Jet Grout Underpinning of Sensitive Structures in Urban EnvironmentsBy Alexander Ciccone, John H. Gill
Jet grouting is a highly versatile ground modification technique that can offer significant commercial and technical advantages over traditional concrete pit underpinning applications. Despite these a
Jan 1, 2019
-
Session 18 "Grouting for Micropiles & Anchors"By Jim Bruce
No answer required. From the drilling equipment suppliers, but the specifications must be tailored to be project-specific. Yes, the sonic technique is very interesting as we said, and it is not so muc
Feb 10, 2003
-
Lateral Load Testing Of Pile FoundationsBy Anne Lemnitzer
Full-Scale cyclic field testing was performed on a 3x3 pile group consisting of nine cast-in-drilled-hole (CIDH) reinforced concrete shafts and a comparable single-shaft in order to investigate group
Jan 1, 2010
-
Northeast Boundary Tunnel – Mount Olivet Road Drop ShaftBy Jeremiah M. Jezerski, Russell H. Lutch
The Mount Olivet Road Drop Shaft (MOR-DS) support of excavation (SOE) is a circular unreinforced concrete shaft with an inside diameter of a 30.5 ft (9.3 m) and depth of 120.5 ft (36.7 m), constructed
Oct 1, 2022
-
Material Properties for Analysis of Deep Mixing Support SystemsBy Alex Grenoble, Alex Reeb, George Filz, Farzad Abedzadeh
"This paper summarizes available information on the characteristics and properties of deep-mixed soilcement produced by the wet method. The topics covered in this paper include: unit weight, unconfine
Jan 1, 2015
-
Re-Use Of Old Pile Foundations In AmsterdamBy Remco Offenberg, Marcel Bielefeld, Martijn van Delft
The question of the continued suitability of existing foundations arises when the function of the superstructure changes. This can occur when the superstructure is replaced or when the existing struct
May 1, 2022
-
Economic Design Of Piling Platforms On Coarse Grained SubgradeBy Patrick Wong
The design of piling platforms is addressed in BRE (2004) for both fine grained and coarse grained subgrades. However, for coarse grained subgrades, piling platform designs can often be overly conserv
Nov 1, 2022
-
Washington Avenue Tunnel Project: Fortifying Aging Underground InfrastructureBy Andrew R. Klaetsch, Peter W. Deming
"The Washington Avenue tunnel in Kingston, NY was completed in 1912 to convey combined storm water and sanitary sewage. Over a mile in length, the tunnel was driven almost entirely in bedrock, with th
Jan 1, 2016