    Real-time Assisted Driving System in Open Pit Mining Operations using Google Earth

    By E. J. Sun

    The ADS system was developed to reduce accidents related to haul trucks operating under low visibility conditions in surface mining and construction sites, which is based on the GPS, mesh-wireless net

    Oct 1, 2009

  • CIM
    Process Development for Milling B-Zone Ore at Rabbit Lake

    By S. Dicarlo

    "In late 1985, B-zone ore was first processed through the Eldor Mines mill at Rabbit Lake. Extensive modifications had been completed in order to mill this ore. In-plant process development was initia

    Jan 1, 1988

  • CIM
    Developing Operation, Maintenance and Surveillance Manuals for Tailings and Water Management Facilities

    By Ian Bruce

    Tailings and water management facilities are essential and integral components of mine and mill operations. They must be managed for the long term in order to ensure that safe and environmentally resp

    May 1, 2002

  • CIM
    A Simulation Model For Underground Roadway Development Processes

    By Ernest Baafi

    A simulation model RoadSIM using the ARENA modelling system has been developed to evaluate roadway development options for a given development panel configuration. The RoadSIM simulation system has pr

    Oct 1, 2009

  • CIM
    Evaluating Multi Zone Ore Bodies of the Raglan Nickel Deposit using Current Planning Techniques Complemented by Real Option Pricing.

    By Bruno Lemelin

    Falconbridge Ltd Raglan Mine has been in production since 1998 and has produced annually some 900 000T of ore grading 3.1% nickel, 0.9% copper and 0.06% cobalt. The mine is located in Nunavik, Norther

    May 1, 2004

  • CIM
    Advancing Asset Performance at the Montcalm Operation

    By Juan Anes, Dominic Fragomeni, Tim Edwards, Dave Scott, Simon Yu

    "The Montcalm concentrator operation was successfully commissioned in fall of 2004 at the Xstrata Copper’s Kidd Creek Metallurgical Site, Timmins. The start-up met or exceeded the Type 1 profile as de

    Jan 1, 2009

  • CIM
    Coal Quality Estimation using Geophysical Logging Without Radioactive Sources

    By Filipe Beretta

    This study investigates geophysical logging capacity to predict coal quality. It was analyzed for possible correlation, some parameters determined via laboratory analysis of coal against results for t

    Oct 1, 2009

  • CIM
    Metallurgy of the Mt. Milligan Porphyry Gold/Copper Deposit

    By A. B. Cron, R. MacPhail, L. Melis, K. Armstong

    "Mt. Milligan is a porphyry gold/copper deposit in north-central British Columbia. Diluted and mineable drill-indicated reserves total 449 million tons at an average grade of 0.013 oz gold/ton and 0.1

    Jan 1, 1991

  • CIM
    An Instrumented Laboratory Cell for Gold Cyanidation Modelling

    By M. Kane, B. Bissonnette, D. Hodouin

    "A laboratory cell has been designed for a careful investigation of gold ore cyanidation using mathematical modelling of the process kinetics. The cell is a stirred vessel with continuous monitoring a

    Jan 1, 1990

  • CIM
    Social Implications of Mining Operations on Nearby Communities - A Case Study

    By Steven Townend

    Mining-related activities have been known to create a challenging operating environment for mining companies located in close proximity to communities. Issues such as noise, vibrations from mining ope

    May 1, 2011

  • CIM
    Meeting Recruiting Challenges - Victor Project

    Project Schedule ?Construction 2005 ?2008 (3 years) ?Operations mid 2008 ?2020 (12 years) ?Closure 2020 ?2023 (3 years) ?Post-closure monitoring Victor Economic Facts ?$982 million investment;

    May 1, 2006

  • CIM
    Sustainable standards for the mining and metallurgical industry of the 21st century

    By D. J. Kemp

    The 20th century saw changes in the mining and metallurgical industry not only technically but also in social and environmental expectations. As projects continue to become larger their visibility rai

    Jan 1, 2005

  • CIM
    Using Rock Physics for Constructing Synthetic Sonic Logs

    By I. O. Ojala

    Detailed knowledge of velocity-depth trends is essential for constructing well-to seismic ties, determining background velocity and generating synthetic seismic traces for interpreting seismic amplitu

    May 1, 2009

  • CIM
    From Tribulation to Triumph – Flotation Improvements at the New Lac des Iles Concentrator

    By Tom Olsen, Tom Ohrling, Peter Taggart, Chris Martin

    "North American Palladium commissioned the new concentrator at the Lac des Iles mine in the summer of 2001. The 15,000 tonnes per day mill replaced the existing 2,400 tonnes per day facility, as part

    Jan 1, 2003

  • CIM
    A Review of Flotation Columns Application in Rougher Circuits

    By M. Massinaei, M. R. Yarahmadi, S. Zeidabadi, M. Oliazadeh

    "Although the majority of new flotation column installations continue to be for cleaning or recleaning, an increasing number of flotation projects are specifying columns for roughing or scavenging dut

    Jan 1, 2011

  • CIM
    The Paracatu Expansion Project III ? Building the Largest Gold Concentrator of the World

    By Luis A. Tondo

    The Paracatu Expansion Project III in Brazil was implemented between 2006 and 2008 to increase the existing capacity from 20 to 61 Million tons per year of gold ore treatment. This expansion led the B

    May 1, 2009

  • CIM
    Cluff Lake Mill - Phase 2 Expansion

    By H. A. Schnell

    "The Phase I Mill at Cluff Lake in northern Saskatchewan was designed to accommodate a very specific high grade uranium ore. As this high grade ore was depleted, construction was undertaken on a new m

    Jan 1, 1985

  • CIM
    Fuel cell risk assessment, regulatory compliance, and implementation of the world’s first fuel cell-powered mining equipment at the Campbell Mine (2f329a25-0d4f-40d5-a572-5230f6f201ab)

    By T. MacKinnon, M. C. Bétournay, D. Eastick, F. C. Delabbio, C. Graves

    "The successful implementation of a new technology in an underground production mine requires many challenges to be overcome. These challenges include mine hardening of new technology, mitigation of s

    Jan 1, 2005

  • CIM
    Flotation Circuit Analysis at Zinifex Century Mine

    By Dan Alexander, Ivan Crnkovic, Sarah Schwarz

    "Several plant studies have been conducted at the Zinifex Century Mine over the past 5 years. For each of the plant studies, surveys of the zinc primary circuit were conducted, characterisation measur

    Jan 1, 2008

  • CIM
    Automated Real-Time Elementary Analysis of Drill Dust using LIBS Technology

    By Karl Nienhaus

    The BGMR has developed a method for an online-analysis during drilling processes in cooperation with Fraunhofer Institute for Laser Technology in Aachen and various industrial partners. This allows fo