    Stacking of Potash Mill Tailings (a53a3fa3-c9c5-495d-81ff-6d030f92ec59)

    By P. G. Roden, G. A. Maki, P. J. Fullmann

    "In October 1984, Rocanville Division began using a stacking system to handle potash mill tailings. Previous to this date, mill tailings were slurried to the top of the tailings pile and allowed to de

    Jan 1, 1986

  • CIM
    Melt Extraction of Gold Fibers and Precious Metal Doped Fibers and Preparation of Porous Gold Fiber Structures

    By Olaf Andersen

    Crucible melt extraction yields short metal fibers with eqivalent diameters as low as 50 µm from almost arbitrary metals and alloys. Highly porous components can be made from such fibers by suitable d

    Oct 1, 2003

  • CIM
    Structural, Electronic, and Impurity-doping Effects in Catalytically Active Gold Nanoclusters and Nanostructures

    By Hannu J. Häkkinen

    Metal clusters exhibit unique size-dependent physical and chemical properties that differ from those of bulk materials or large particles. Here we discuss recent theoretical investigations of the cata

    Oct 1, 2003

  • CIM
    An Economic and Environmental Case for Re-processing Gold Tailings in South Africa

    By James A. Brown, Marius Botha, Christopher A. Fleming

    "The technical and economic feasibility or re-processing hundreds of millions of tons of tailings in a number of historic gold tailings dams in the Witwatersrand area of South Africa is being investig

    Jan 1, 2010

  • CIM
    Numerical Modeling of Standard Rock Mechanics Laboratory Tests using a Finite/Discrete Element Approach

    By S. Stefanizzi

    In the present paper, numerical simulations based on a finite/discrete element approach are used to study deformation and failure process during standard rock mechanics. FEM/DEM modeling has been used

    May 1, 2009

  • CIM
    Stratigraphic and Structural Constraints on Limestone Exploration: A Case Study from Northern New Brunswick, Canada

    By I. Dimitrov, S. R. McCutcheon

    "Industrial-grade limestone is found in both the Lower Silurian La Vieille Formation and Upper Silurian LaPlante Formation of the Chaleurs Group in northern New Brunswick. Currently, between 150 000 a

    Jan 1, 2007

  • CIM
    Framework for optimizing components in an oilwell cement slurry design

    By D. Getzlaf

    "Oilfield cementing has been utilized in the industry since the turn of the century. Originally, wells were shallow and criteria for well integrity were somewhat limited. Since that time, wells have s

    Jan 1, 2004

  • CIM
    A simplified equation for estimating the total vapour pressure of cryolitic melts

    By Edgar Dernedde

    Cryolitic melts at a temperature of about 960 °C are used in reduction cells to dissolve alumina and to produce primary aluminium. At these temperatures cryolitic melts with an acidic composition have

    Jan 1, 2004

  • CIM
    Evolving Equipment Health, a Rio Tinto Case Study

    By Daniel D. M. Adams

    Over the last 100 years industry in general has been trying to advance the ability to maintain systems through management processes. Mining has looked to utilize onboard data systems in our mobile min

    May 1, 2011

  • CIM
    Paste Fill Design at the Louvicourt Mine

    By Pierre Lacombe

    "The operation of the Louvicourt Mine will have to rely on stringent grade control and on the optimization of the amount of blocked ore made available per given development effort. All of the above be

    Jan 1, 1995

  • CIM
    Case Studies in the Use of the Falcon Gravity Concentrator

    By S. McAlister

    "Falcon Concentrators Inc. has developed a high capacity centrifuge for the recovery of fine, free gold as well as other metals and minerals which were previously thought to be unrecoverable by gravit

    Jan 1, 1992

  • CIM
    A Comparison of Open Circuit versus Closed Circuit SAG Milling at the Williams Mine

    By David Evans, David Barnes, Robert Raponi

    "The Williams Mine processes, on average, 6,450 t/d of gold bearing ore using two parallel grinding circuits, leaching and C.1.P., carbon stripping, electrowinning and refining. At present, each grind

    Jan 1, 1997

  • CIM
    Jaguar?s Caeté Gold Project in Brazil

    By Ivan C. Machado

    Jaguar Mining Inc. is implementing a 1.1 Mtpy, 7-year LOM gold project in the Iron Quadrangle (?Quadrilátero Ferrífero?), Brazil. Construction is on schedule and startup is programmed for Q2 2010. Mil

    May 1, 2010

  • CIM
    CIP - Who Needs It? A combination circuit of Gravity, Flotation and Intensive Leach may provide the Optimal Environmental and Cost Outcome for Gold Plants.

    By Garry Johansen, Andrew McCallum, Sandy Gray, Gary Patrick, Jennifer Abols

    "The authors challenge the traditional thinking that whole ore cyanidation followed by Carbon in Pulp (CIP) or Carbon in Leach (CIL) should be applied as a standard process in the majority of gold pro

    Jan 1, 2003

  • CIM
    Development and Implementation of an Operating Concept and Training Program for the Start-Up of the Stanleigh Mill

    By H. Ewaschuk

    "INTRODUCTIONRio Algom's Stanleigh Mill in Elliot Lake began production in June of 1983. The highly instrumented mill treats uranium ore at an average rate of 3900 metric tons per day. To help ensure

    Jan 1, 1985

  • CIM
    The Economics of the Carbon in Pulp Treatment of Low Grade Flotation Tailings: A Pilot Study

    By R. H. O. Wagner

    "This paper describes the bench testing, pilot plant studies of alternative flowsheets, to determine the feasibility of gold recovery, by carbon in pulp extraction, in the Schumacher Mill gold flotati

    Jan 1, 1984

  • CIM
    Expert System Technology at the Polaris Mine

    By G. A. Kosick, C. A. Harris

    "Metallurgy at the Polaris Mine is approaching an impasse, with lead and zinc concentrate grades and recoveries approaching their theoretical maximums. In an effort to increase productivity, plant thr

    Jan 1, 1988

  • CIM
    Nutrien Allan Potash Shaft Concrete Liner Remediation

    By D. R. Murray

    "In 2017, Nutrien Allan Potash remediated a portion of the concrete liner in the production shaft. A set of underslung work platforms and collection boxes were used in conjunction with hydraulic split

    Jan 1, 2019

  • CIM
    GHG Emissions in the Mining, Metallurgy and Petroleum Sectors

    By Pierre Boileau

    Outline ? Who are We? ? Canada?s GHG Emissions 1990 - 2000 ? Emissions from the Petroleum Sector ? Emissions from Petroleum Exports ? Emissions from Manufacturing Industries ? Emissions from Min

    Nov 1, 2002

  • CIM
    The Operating Range Method for Backfill Hydraulics

    By D. J. Hallbom

    This paper presents a novel methodology for the hydraulic design of mine backfill distribution systems. The ?operating range? method uses the concepts of the hydraulic grade line and equivalent pipe l

    May 1, 2007