Technical Note - Hollow Threaded Rebar For Cross Hole Sonic Logging Access Tubes Combined With Longitudinal Concrete Reinforcing In Drilled Shafts
By Josef K. Alter
Crosshole Sonic Logging (CSL) of drilled shafts requires 1.5-in (38-mm) or 2-in (51-mm) I.D. sonic access tubes to be installed inside the steel reinforcement cage. The sonic access tubes do not contr
Jan 1, 2011
-
In-Situ Study On Improvement Of Soft Ground Using Stone Columns For Railway Embankment
By Kishore Kumar B., Eswaran Prasad C R, Srini Naik B., Ramakrishna Raju N
The authors through this paper intend to introduce the non-vibro technique of ground improvement by stone column, being used for the first time in India under the Western Dedicated freight Corridor in
Nov 1, 2022
-
Influence Lines For The Pile Loading On Bridge Pier Foundations
By M. B. Wechsler
An analysis is developed for determining the maximum loading, as well as the potential uplift of the piles on bridge pier foundations. There are considered piers supported on two through seven rows of
Jan 1, 1989
-
Drilled Shaft Design For Noise Wall Barriers Along I-20 In Columbia, SC
By Anil Bhandari
Using subsurface data collected at each drilled shaft location is an ideal approach for conducting drilled shaft design. However, conducting subsurface tests at each drilled shaft location and subseq
Jan 1, 2011
-
How Well Do Helical Piles Resist Earthquakes as Foundation Systems? WHERE TO GO FROM HERE?
By Amy B. Cerato, Shawn Allred, Tatiana Vargas
"Helical piles are deep foundation elements that resemble, and are installed like, a large steel soil screw — they have a slender steel shaft with one or more round helix bearing plates welded to the
Jan 1, 2017
-
Mission Valley Viaduct Piledriving - 1998 DFI Conference Seattle, Washington October 8, 1998
By David A. Jack
The Mission Valley Viaduct is located in San Diego, California. This structure is the intersection of Interstate 8 and 805. The project consists of the main viaduct, 8 connecting ramps, and one highwa
Jan 1, 1998
-
Construction Of Long Tubular Column Foundations Under Deep Water ? Synopsis
By C. L. Liao
The chief experiences for constructing deep tubular columns foundation under deep water are as follows: 1. P.C. tubular columns were sunk inside the caisson. 2. P.O. tubular columns of 3.6 M. diameter
Jan 1, 2010
-
Analysis Of Driving Stress Measured In The RC Long Pile
By Yu Zhenquan
At the construction site of Bao Shan Iron &. Steel Mill in Shanghai, lots of RC driven piles with length of 50 to 60m were applied. The most unfavourable distribution of stress along the pile shaft wa
Jan 1, 1991
-
Dewatering Practice For Deep Basements In Hawaii
By Masanoub R. Fujioka
A brief discussion of the methodologies involved in dewatering practices, particularly as used in Hawaii in coralline formations. A description of early dewatering practices includes a number of case
Jan 1, 1986
-
Behavior Of Large Bored Piles With Grouted End
By Zhang Yaonian
This paper describes full-scale tests on ten large bored piles with grouted end conducted for three projects in the urban area of Fuzhou city. Test program included site investigation, pile installati
Jan 1, 2004
-
A Simple Solution For Slope Stabilization Using Micropiles
By Dan Brown
A method is outlined for computing the contribution of a micropile group to global stability of a sliding mass. The forces in the micropile are computed in a way which accounts for the effect of soil
Jan 1, 2007
-
Application Of High-Strength Concrete To Drilled Shafts - 1. Summary
By A. E. Fiorato
A test program was conducted to evaluate use of high-strength concrete in drilled shafts (caissons). The objective of the program was to determine if internal temperatures developed during cement hydr
Jan 1, 1991
-
Negative Drag - A Practical Example - Synopsis
By A. Verghese Chummar
The paper presents a field study where the effect of negative drag caused the failure of a pile foundation system. Utilising the field observations the probable negative drag that acted on the piles i
Jan 1, 1996
-
Deep Compaction Of Saturated Loess By Means Of Sand-Gravel Piles ? Synopsis
By Z. G. Lin
In Xian, China, compaction by means of soil (or lime-soil) piles is one of the effective methods widely used for densifying loess and eliminating its collapsibility. However, as a result of groundwate
Jan 1, 2010
-
120 Years of Caisson Foundations in Chicago
By Robert E. Schock, Eric J. Risberg
"Less than 20,000 years ago, the last of the glaciers retreated from the Chicago region. They left behind sheets of glacial clay till underlain by dense, over-consolidated till (“hardpan”) below which
Jan 1, 2016
-
Use Of Anchors In Floors Of Large Drydocks And Wagon Tipper Sheds ? Synopsis
By W. H. Liu
The stability of floors of large drydocks and wagon tipper sheds at coal terminals is an important matter but quite difficult to solve. Anchors can be used to join floors to foundations thus ensuring
Jan 1, 2010
-
-
Technical Note Evolution Of Top Of Pile Measurement Techniques In Deep Foundation Static Load Testing
By Jon Sinnreich
Ensuring the accuracy of collected data during deep foundation static load tests is of paramount importance. Typically, pile head displacements are measured relative to a purpose-built reference syst
Jan 1, 2009
-
Inelastic Response Of Extended Pile Shafts In Laterally Spreading Ground During Earthquakes (Student Paper Competition 2010)
By Arash Khosravifar
The seismic design of extended pile shafts for the combined effects of dynamic shaking and liquefaction-induced lateral spreading is investigated using nonlinear dynamic finite element analyses (NDA).
Jan 1, 2010
-
Acrylamide Grouting: Successfully Controlling Groundwater From Canada To South America
By Jom Gentry
Acrylamide chemical grout (C3H2NO) has been successfully used for over 50 years to control groundwater and stop infiltration. This paper will address three unique projects involving the control of gr