Resonance Pile Driving with Zero Ground Vibration
By Mark Johnson, Mathew Janes
"The Resonator RD 260 Resonant Pile Driver delivers ground disturbance free, high production pile driving. The Resonator has recently been used on numerous production pile driving sites in the Netherl
Jan 1, 1900
-
No. 1 Queens Road - Melbourne, Australia
By Tom George
"INTRODUCTIONNo. 1 Queens Rd was an existing 10-storey office building founded on large pad footings. This project involved the construction of a 6-level, 15m (50-ft.) deep basement excavated immediat
Jan 1, 2005
-
A Review of the Design Formulations for Static Axial Response of Deep Foundations from Cone Penetration Test Data
By Fawad S. Niazi
Analysis of deep foundations in terms of axial capacity has been a topic of great interest in the soil-structure interaction problems. Soil behavior is governed by a series of complex stress-strain ch
Jan 1, 2013
-
Diameter Effects On p-y Curves
By Ignatius P. O. Lam
This paper presents information on design analyses of large diameter piles using conventional p-y curves as recommended by the American Petroleum Institute (API RP2A, 1993). API RP2A adopted the soft
Jan 1, 2013
-
Deepest Ever Large Diameter Pipe Pile Installation Demonstration Project New East Span San Francisco-Oakland Bay Bridge
By Saba Mohan
For the three full-scale pile installations, two different high-energy hydraulic hammers were selected for the installation. However, these hammers may not have sufficient energy to drive these large
Jan 1, 2002
-
Session 25 "Grout Mixtures and Materials I"
By Stephan Jefferis
It is my understanding that the Scandinavians have done some fundamental work on durability. I have seen a study published whereby the author, Helen Anderson, comments on the durability of polyurethan
Feb 10, 2003
-
Evaluation Of Pile Load Test Results
By Rasin Duzceer
In this paper, the results of pile load test on 24 piles from twelve sites are presented. The pile load tests were performed on 14 driven and 10 bored piles of varying diameters and lengths installed
Jan 1, 2002
-
Stone Columns At Trenton Water Treatment Facility - Suitable Alternative To Remove And Replace For Mat Foundation
By Darrell Wilder
The Trenton Water Treatment Facility in Trenton, New Jersey, is expanding to upgrade existing facilities and to meet the increasing demands of the public. The facility sits uncomfortably between the
Jan 1, 2008
-
Heating And Cooling Structures With Steel Pile Foundations Closed Loop Standing Column Well Technology
By Paul Suver
The closed loop standing column well (CLSCW) system uses a closed circuit of water to develop the same thermal heat exchange characteristics that are achieved from traditional open circuit standing co
-
Heating and Cooling Structures with Steel Pile Foundations - Closed Loop Standing Column Well Technology (df25801f-7df6-457c-ab18-569c2a6ce07f)
By Paul Suver
"The closed loop standing column well (CLSCW) system uses a closed circuit of water to develop the same thermal heat exchange characteristics that are achieved from traditional open circuit standing c
Jan 1, 2017
-
A Coupled FE-BE Formulation For The Prediction Of Vibrations Due To Vibratory And Impact Pile Driving
By H. R. Masoumi
This paper presents a numerical model for the prediction of free field vibrations due to vibratory and impact driving. As the focus is on the response in the far field, where deformations are relative
Jan 1, 2006
-
Engineering Practice Of Ground Improvement ? Introduction
By H. R. Taber
The extensive subject area "Engineering Practice of Ground Improvement" will be treated within the limitations of space and the writer on the basis of personal practice and experience?largely in North
Jan 1, 2010
-
Session 23 "Grout in Rock and Mining"
By John Davie
We used a Remtek survey in Glenrock and had very good luck with it when we first started the initial investigation. We would have loved to have used that more but my understanding is the equipment is
Feb 10, 2003
-
Some Experiences In Construction And Design Of Stone Column Reinforced Ground ? Synopsis
By C. W. Sheng
In this paper conventional construction procedure is briefly described for the installation of stone columns in soft ground in China. A viewpoint concerning the mechanism of ground improvement by use
Jan 1, 2010
-
The FHWA Geotechnical Program for 2017
"Every year during the Transportation Research Board (TRB) Annual Meeting in Washington D.C., the Federal Highway Administration (FHWA) National Geotechnical Team (NGT) takes time to talk about what w
Jan 1, 2017
-
Innovation In Spliced Prestressed Piles: Testing And Use Of The Emeca Pile Splice
By John C. Ryan
The Emeca Pile Splice, an innovative mechanical prestressed concrete pile splice, is the first robotically welded splice to be fabricated in the United States. An analytical and experimental study wa
Jan 1, 2010
-
Electronic Instrumentation in Support of Installation of Special Foundation Projects as Part of the Digital Future - Ensuring Safe Production and Improving Quality Control
By Franz-Werner Gerressen
New developments are required each day as our industry becomes more competitive. To improve performance, continue and to ensure future demands can be met. This requires the development of technical su
Jan 1, 2019
-
Design Build & Failure: Perils at a High Risk Shoring and Retaining Wall Project.
By Mark Spence, Tom Lardner, Matthew Janes
"IntroductionThe design-build method streamlines project delivery through a single contract between the Contract manager and the design-build team. The design-build method places emphasis on collabora
Jan 1, 2015
-
On The Ultimate Capacity And Radial Stress Distribution Of Driven Piles In Sands
By E. Ulrich Klotz
It is difficult to predict accurately the capacity of driven piles in sand. In practice, this uncertainty either leads to conservative designs if the capacity is under-predicted, or worse, if the cap
Jan 1, 2002
-
LRFD For Deep Foundations: Replacing The Traditional Factor Of Safety In Design
By Lance A. Roberts
The Federal Highway Administration (FHWA) has mandated the use of the AASHTO Load and Resistance Factor Design (LRFD) specifications for all new federally-funded transportation infrastructure projects