The Construction and Testing of a Polycarbonate Safe Haven Wall
By Braden T. Lusk, Rex A. Meyr, Kyle A. Perry
Following three major mining accidents in 2006, the MINER Act of 2006 was enacted by MSHA and required every underground coal mine to install refuge alternatives to help prevent future fatalities of t
Jan 1, 2014
-
Modeling and Optimization of Wall Damage in Underground Stope Blasting
By Abraham Lindo
"Blasting plays a key role in hard rock underground mining. It is by nature a violent and destructiveextraction method designed to economically fragment the rock into a suitable size for it to be load
Jan 1, 2016
-
Blasting in Challenging Environments
By Richard Goodridge, Stephen Thomsqn, S Rodgers, D Tunaley
The mining, quarry and construction industries are facing’new challenges everyday. These challenges can be imposed by economic objectives or through external factors such as extreme geological conditi
Jan 1, 1998
-
Digital Detonators keep PA Coal Mine Operating
By Douglas Bartley, Jay Elkin
The state of Pennsylvania was at one time one of the leading coal producing states in the east. However, legislation and industry trends over the last 10 years have adversely affected the amount of bi
Jan 1, 2003
-
Analysis of Parameters of the Ground Vibration Produced by Bench Blasting at a Boron Open Pit Mine in Turkey
By Gungor Tuncer, Ali Kahriman, Abdulkadir Karadogan, Mehmet Aksoy, Kagan Ozdemire
With increasing environmental constraints on the levels of disturbance induced by blasting operations upon nearby residents, there is an increasing need to be able to design cautious blasting with gre
Jan 1, 2005
-
Blasting 1 Million Tons, 205 Meters from a Town
By Thierry Bernard, Guy Gagnon
Blasting at very close proximity to urban areas is typically a situation where both local communities and mining stakeholders get nervous. The context becomes logically even more tensed when the blast
Jan 1, 2014
-
Blast Vibration Analysis, the Fourier Transform and Delay Effects on Frequency
By Randall M. Wheeler
"Fourier analysis is a very powerful frequency analysis tool. However, it is frequently misunderstood and sometimes used inappropriately. Part of this workshop will involve the basics of Fourier serie
Jan 1, 1998
-
Pre-Splitting With The New AIRDEK Technique
By David G. Borg, John Bussey
The new AIRDEK (tm) technique for pre-splitting in surface coal mines produces highwall conditions that have greater safety with lower costs for explosives, labor, and drilling. Successful application
Jan 1, 1988
-
Improved Coal Extraction Using Signature Hole Analysis and Electronic Detonators at the Knight Mine
By Stuart Brashear, Eddie Colburn
The Birmingham Coal and Coke – Knight Mine is a single seam coal mine in central Alabama. As pit development progressed in 2013, concerns over increasing vibration levels resulted in modifications to
Jan 1, 2015
-
A Numerical and Experimental Study of Static and Dynamic Behavior in Cemented Elastic Disks
By V. Petr, G. G. W. Mustoe, T. G. Rozgonyi
We introduced a numerical method that is applicable for the analysis of static and dynamic deformations of elastic media. In this numerical study, each elastic body is modeled with a system of several
Jan 1, 2000
-
Measuring Blast Movement to Reduce Ore Loss and Dilution
By Darren Thorton, David Sprott, Ian Brunton
Blasting causes movement of the rock and can be detrimental to the accurate delineation of the ore and waste regions within the resulting muck pile. The consequences can be ore loss and dilution. Howe
Jan 1, 2005
-
Isolating Single Hole Vibration Signals from Multi-Hole Shots
By Rob Famlield, Gavin Yuill, William Birch
The Blasting Research Group at the University of Leeds, in the United Kingdom, continues to be highly active in the area of the environmental impact of blasting. In recent years a major part of this r
Jan 1, 2002
-
Journal: Near Field Vibration Monitoring for Rock Mass Damage Control Tala Hydroelectric Project, Bhutan India
By H. Venkatesh, Balachander R.
This article discusses the method that was adopted for controlling damage to rock mass while excavating an underground powerhouse cavern at Tala Hydroelectric Project. It discusses in detail the near
Jan 1, 2006
-
The Computerized Design Program for Tunnel Blasting
By Jeon Jeon, Yong-Kun Choi, Chung-In Lee, Yong-Hun Jong, Hag-Soo Kim
In this study, a computer program to design tunnel blasting pattern has been developed. The program consists of two parts; one is for tunnel blasting pattern design and the other is for blasting model
Jan 1, 2005
-
DynoMiner™ APS Underground Explosive Loading System
By Daniel Roy
This paper introduces a new, safer bulk emulsion loading system for underground mining operations. The features and benefits of the equipment, along with the use of Dyno Nobel Inc. patented gassed emu
Jan 1, 2003
-
Close - In Blasting
By Adam Gray, Emery Gray
State-of-the-art seismographs can be employed to assist the blasting engineer in understanding the propagation of vibration waves generated by blasting. Wave traces and frequency plots are used to adj
Jan 1, 2005
-
Case History: Controlled Demolition of a Reinforced Concrete Structure in San Sepolcro, Italy
By Roberto Folchi
This note deals about the controlled demolition work for the dismantling of an industrial structure in San Seplocro, Italy. The structure to be demolished, the FLOWERS SILOS, consisted in a multilevel
Jan 1, 1994
-
Laser Profiling and Computer Aided Blast Design using the Criterion Survey System and Win-Profile Analysis Software
By Steve Colburn
The CRITERION Survey Systems utilize both theodolite mounted and hand held reflectorless distance meters. These are eye safe, easy-to-use, and specifically designed to endure the harsh environments ch
Jan 1, 1998
-
Stemming Enhancement Tests
A series of stemming confinement tests were conducted at a test site near Vernal, Utah. The purpose of the study was to determine the relative performance of various stemming enhancement “plugs”, stem
Jan 1, 2000
-
Journal: 100 Years / Engineering News New York January 5, 1905 Methods and Cost of Blasting and Handling Boulders (52912f89-42e4-4811-8c7f-344764181b42)
By Daniel Hauer
Blocking. (5) The “blocking” of boulders is a much cheaper way of breaking them up than “mud capping.” It should always be used in preference to that method except when too much time will be consumed
Jan 1, 2006