Process Developments At Tailings Leach Plant
By Martin Banda, Gift C. Chisakuta, Moses Chabinga
KCM made a major modification to the Nchanga Tailings Leach Plant (TLP) changing the circuit from feeding post leach thickeners in parallel with leach discharge for solid ?liquid separation to a Count
Jan 1, 2005
-
Laboratory Investigations Of The Electrical Resistivity Of Cokes And Smelting Charge For Optimizing Operation In Large Ferrochrome Furnaces
By Krogerus. H., P. Jokinen, T. Lintumaa
Keywords: Pyrometallurgy, furnace, coke, smelting charge, optimization, ferrochrome The main consumer of ferrochrome is stainless steel production. Stainless steel must maintain a reasonable pric
Jan 1, 2006
-
The Role Of Orientation Of Crystal Lattice On The Development Of Bacterial Leaching Patterns On Pyrite Single Crystals
By S. Ndlovu
To investigate the influence of orientation of crystal lattice on the bacterial leaching of pyrite crystals, single crystals of 100, 111 and110 plane orientations were used for the study. Experiments
Jan 1, 2004
-
Alternative Dissolution Of Zircon Samples And Simultaneous Analysis Of Major And Trace Components ? Synopsis
By S. J. Lötter
Analysis of the major and minor components of raw zircon as well as plasma-dissociated zircon was undertaken using inductively coupled plasma optical emission spectroscopy (ICP-OES). Microwave-assiste
Jan 1, 2012
-
Role of Metal Accounting in Assessing and Managing the Business Risks Involved in Production Planning
By Donald Leroux, Simon Gariépy, Luc Lachance
"Quantitative information about the quality of metal balance results is often overlooked when making important plant production planning decisions. Not only is this common omission made in a context w
Jan 1, 2015
-
Using Machine Carousel To Reduce Cladding Support Cycle At Pk2 Ventilation Shaft
By Braam Blom
PK2 Ventilation shaft is part of Paardekraal No 2 twin shaft system that is being developed to replace depleting Merensky reef production at Paardekraal shaft complex. The sinking team at this shaft f
Jan 1, 2009
-
The Evolution Of Strategic Long-Term Planning At Anglo Platinum
By D. C. Andersen, G. L. Smith, J. Pearson-Taylor
Following a restructuring of Anglo Platinum Limited in 2004 the strategic long-term planning function has been centralized. This paper describes the revised strategic long-term planning process coveri
Jan 1, 2006
-
Simulation of integrated underground mining-processing
The paper examines the design issues associated with the integration of mineral processing within underground mining systems. It demonstrates conceptual integrated system design options appropriate to
Jan 1, 2003
-
An analysis of the practical and economic implications of systematic underground drilling in deep South African gold mines
By D. G. Krige
Using chip sample data and spatial structure parameters from a large mined-out section of a South African gold mine the advantages to be gained from a regular underground borehole drilling programme h
Jan 1, 2003
-
Geotechnical Considerations In The Design Of The MOCB Mining Method At Konkola No.3 Shaft.
By M Lipalile, A B. Tunono, A W. Naismith
Konkola No 3 shaft experienced severe mining induced stress and time related deterioration in ground conditions in an area where an over-cut and bench (OCB) mining method was used to extract a shallow
Jan 1, 2005
-
Implementation Of An Alternative Matte-Level Measurement Solution At Lonmin Marikana Smelter Division For Improved Process Monitoring
By T. J. Goff
Keywords: accurate control, matte level, smelting operations, process control, tapping, sounding bar, electromagnetic measurement [ ] Accurate control of matte levels during primary matte smelting
Jan 1, 2011
-
Improvement Of High-Temperature Electric Characteristics Of Manganese Ores
By K. Saito, Y. Miyauchi, T. Nishi, Y. Kizu
At Tokushima Plant of Nippon Denko Co., Ltd. high-carbon ferromanganese is produced by the electric furnace method using lump manganese ores and sintered manganese ores manufactured from fine manganes
Jan 1, 2004
-
Use Of Sintered Pellets In Production Of High Carbon Ferro Chrome
By C. N. Harman, N. S. S. Rama Rao
Production of Ferro-alloys through submerged electric arc furnace involves use of electric power as one of the major inputs. Hence the production by this power intensive process can be made economical
Jan 1, 2007
-
Degree Of Prereduction Without Coke Consumption In Industrial Furnaces
By Rodney Ishak, Merete Tangstad
In the HC FeMn production, better utilisation of coke and electric power is vital for reducing the production costs. The higher manganese oxides in the charge are reduced to MnO in the prereduction zo
Jan 1, 2007
-
Sampling - A Critical Component To Gold Mining Project Evaluation (60ce14f9-844a-41ea-89be-138917950365)
Poorly designed sampling protocols generally result in high project risk by artificially increasing grade variability (ie the nugget effect). Sample collection, preparation and assay protocols that su
Jan 1, 2007
-
Seismic Monitoring Of A Simulated Rockburst On A Wall Of An Underground Tunnel
By A. M. Milev
A simulated rockburst was conducted underground at Kopanang Mine, previously called Vaal Reefs No. 9 Shaft. The rockburst was simulated by means of a large blast detonated in solid rock close to a cro
Jan 1, 2001
-
Using Machine Carousel To Reduce Cladding Support Cycle At Pk2 Ventilation Shaft (311f8feb-63e6-4d23-980e-900e4671e984)
By Braam Blom
PK2 Ventilation shaft is part of Paardekraal No 2 twin shaft system that is being developed to replace depleting Merensky reef production at Paardekraal shaft complex. The sinking team at this shaft f
Jan 1, 2009
-
Remote Mine Wide Communications
Mine wide, underground wireless communications are possible with the use of Ultra Low Frequency (ULF) technology. Due to the propagation through rock of ULF radio signals a relatively small antenna ca
Jan 1, 2007
-
An Overview Of The Zincor Process
Keywords: Pyrometallurgy, zinc, electrowinning Zincor has been producing zinc since 1969 via the roast-leach-electrowinning process. It is the only primary zinc producer in South Africa, and curr
Jan 1, 2006
-
Gravity Circuit Optimisation Via Mathematical Modelling By Particle Size Classes
By Ishwinder Grewal, Michael Fullam
Many factors affect the overall performance of a gravity circuit beyond that of the primary gravity recovery device. It is critical to examine the gravity circuit in its entirety in order to determin
Jan 1, 2006