    "We Agree to Provide Indemnification, Now What?"

    By Jeff Friedman

    This paper addresses certain problems to be encountered when a blasting contractor agrees to provide indemnification. Nearly 100% of all blasting work is performed pursuant to a contractual agreement.

    Jan 1, 2004

  • ISEE
    JKVBOC Blast Movement Model Applications for Ore Control at Open Pit Mines

    By Constanza Bujes, Mark Jones, Graham Crook, Yansan Jamyanbaatar, Sedat Esen

    Tracking ore characteristics such as grade and hardness from its original position into the material handling and processing stages remains one of the key challenges in open pit mining of hard rock de

  • ISEE
    Blasting on Parliament Hill, Ottowa, Adjacent to Canada's No. 1 Heritage Building

    By M V. Van Bers, A L. McAnuff, A Curic

    During the Summer of 1997, rock excavation was carried out for construction of the Centre Block Underground Services building (CBUS) abutting the most historically significant structural complex in Ca

    Jan 1, 1999

  • ISEE
    Optimization of Blast Evacuation Zones using the "Exclusion Zone" Module

    By C. Morel, P. Fredes, L. Rojas

    This article presents a comprehensive study on the development and application of the specific module called "Exclusion Zone" created by Orica to determine blast evacuation exclusion zones. This modul

    Jan 1, 2024

  • ISEE
    The Statistical Analysis of Site-Specific Blasting Data Using Prediction Intervals and Tolerance Intervals

    By Perry Sisk

    In order to protect nearby structures during a blasting project, a peak particle velocity limit is often stipulated by a government agency or the owner of a particular structure. At the start of a bla

    Jan 1, 2013

  • ISEE
    Dilution and Ore-Loss Optimization in Underground Mines

    By Sami Kara, Marsel Nabium

    This paper provides an overview of the solution applied in underground Silver mine in Russia. The paper reviews the dilution problem throughout the entire mining process, and provides a rational appro

    Feb 1, 2020

  • ISEE
    Dilution and Ore-Loss Optimization in Underground Mines

    By Sami Kara, Marsel Nabium

    As a mining project is developed from conceptual to production phases, there exists a variety of uncertainties and difficulties that affect the operation’s designs and economic values. A notable desig

  • ISEE
    The Chemical Kiloton Experiment the Utilization of 50/50 Heavy ANFO at the Nevada Test Site

    By Don Larson, Gordon Coleman

    The United States Department of Energy, through its contractor Lawrence Livermore National Laboratory, has entered into a contract with Alpha-IRECO, Inc. for the emplacement of approximately 2.9 milli

    Jan 1, 1994

  • ISEE
    Firing Reliability of Electronic Detonators

    Electronic detonators are receiving increasing acceptance in the blasting industry. Electronic detonators offer several distinctive features over electric and non-el (shock tube) detonators including

    Jan 1, 2010

  • ISEE
    Drilling and Blasting in Environmentally Sensitive Areas

    By William Clark, Rick Taylor

    "Ajax Contracting was awarded the project to drill, blast and crush 100,000 tons of quarryrock for the Forest Service In Elk City, Idaho, during the summer of 1992. This projecttakes place in an area

    Jan 1, 1993

  • ISEE
    Numerical investigation of impact of misfires and out-of-sequence delays on fragmentation and gravity flow in SLC

    By C. Yi, D. Johansson, C. San Miguel, M. Wimmer

    Sublevel caving (SLC) is a mass mining method based upon the utilization of gravity flow of blasted ore and caved waste rock. Production blasting has significant impact on the efficiency and productiv

    Jan 1, 2024

  • ISEE
    Shaft Holing Project at Bulyanhulu Gold Mine, Tanzania

    By W. De Graaf, C. Mkumbo

    Bulyanhulu Gold Mine Limited (BGML) commissioned a project of sinking a Bulk Air Cooling Shaft during its programme to improve the ventilation system on the mine. As part of this project, a ventilatio

    Jan 1, 2011

  • ISEE
    Journal: Effect of Depth Below Mudline of Charge Placement During Explosive Removal of Offshore Structures

    By Craig Adams, William Poe

    Introduction The United States Department of the Interior, Minerals Management Service (MMS) is mandated under the Outer Continental Shelf Lands Act (OCSL A) and the Energy Policy Act of 2005 to overs

    Jan 1, 2011

  • ISEE
    Expanded Blast Design For Tight Controlled Hard Rock Trenching Adjacent To Twin Burried Live Oil Pipelines

    By A. Ravi Kumar

    A trench is a structure to accommodate fluid carrying pipelines for water, gas, petroleum products etc. Trench serves the purpose to haul the fluids in bulk over long distances safely and economically

    Jan 1, 2008

  • ISEE
    A Radio Frequency Hazard Assessment Probe Circuit

    By Florian B. Janoski

    The annual consumption of electric blasting caps in the United States approaches 100,000,000, so, over the last eleven to twelve years about one billion have been used. The author has made hazard asse

    Jan 1, 1977

  • ISEE
    Integration of Big Data from Drilling and Blasting for Plant Throughput Optimization at Constancia Mine

    By Hernan Escalante, Jonathan Alvis, Paulo Alcazar

    Constancia Mine, operated by Hudbay Perú and located in the district of Velille, Chumbivilcas province, Cusco, is an open-pit operation characterized by low-grade ore. In this context, operational eff

    Jan 26, 2026

  • ISEE
    A Comparative Study Of Ppv Analysis Of Tunnel Rounds Using Both Non Electric And Programmable Electronic Detonation

    By Andrew Wetherelt

    Blast vibrations are of paramount importance in a society where ever increasing development is putting more stringent requirements on their control. Increasing civil development and more complex extra

    Jan 1, 2007

  • ISEE
    Modular Ballistic Pendulum for Measurement of Impulse from Tamped Explosives

    By Roland Alford

    The ballistic pendulum is a well-established piece of test equipment originally developed for estimating the velocity of bullets and projectiles. When trying to understand the effects of different tam

    Feb 6, 2023

  • ISEE
    Research and Application of HM (Hole-mixed) Truck for Emulsion Explosives

    By Zhiwei Jiao, Ziqing Guo, Mushen Wang, Yueda Fang, Qiuming Tang

    In order to achieve anti-terrorism, production safety, better explosive performance, lower cost, and environment protection, we developed HMS (emulsification in borehole).Long-process PM (plant-mixed)

    Feb 1, 2020

  • ISEE
    Drilling and Blasting in Hot and Reactive Ground Conditions at Barrick Goldstrike's Meikle Mine

    By D. Scott Scovira, Remi Proulx

    The Meikle Mine is a high grade, underground gold mine utilizing primary-secondary longhole open stoping with delayed backfill to produce 3000 stpd of ore. Hot and reactive ground conditions were enco