Search Documents
Search Again
Search Again
Refine Search
Refine Search
-
Design, Construction, and Long-Term Monitoring of a Pile-Supported LNG Tank in Savannah, GeorgiaBy Cheng Lin, Guoming Lin
"This paper presents a case history for the design, construction and long-term performance monitoring of a driven prestressed concrete (PSC) piled foundation supporting a large liquefied natural gas (
Jan 1, 1900
-
Seepage Barrier Mix Design Development, Installation, and EvaluationBy George W. Little, John Councilman
"The selection, evaluation, and modification of contractor mix designs for self-hardening seepage barriers, completed by the slurry trench excavation method, can be one of the most critical and challe
Jan 1, 2016
-
Lateral Load Tests on Step Tapered Bored Piles in Calcareous SandsBy Nabil F. Ismael, Mohamed El Deeb
"The behavior of laterally loaded step tapered bored piles in calcareous sand was examined by field tests. Lateral load tests were carried out on straight and step tapered bored piles 5.3 m long embed
Jan 1, 2005
-
Bearing Capacity of Post Grouted Drilled Shafts Using a Load Transfer ApproachBy Miguel E. Ruiz, America L. Fernandez, Miguel A. Pandon
"Post-grouted drilled shafts (PGS) are a deep foundation system in which grout is injected at high pressure throughout the tip after the drilled shaft has been installed. Pressure grouting of drilled
Jan 1, 2005
-
Artificial Ground Freezing: A Smart Application Below The Airport Of PerthBy Luca Pingue, Regine Jagow-Klaff, Franco Muratore, Carlandrea Albonico, Damiano Frontini, Rudolf Wernecké
This paper describes an artificial ground freezing (AGF) application carried out to ensure both watertightness and structural support for the safe excavation of four cross passages of the Forrestfield
May 1, 2022
-
Evaluation of Existing T-Z Models for Caliche Based on Numerical Analysis of Bi-Directional Load Tests Using NVShaftBy Ramin Motamed, Fahim M. Bhuiyan, Raj V. Siddharthan, Joseph Toth
The difficulty in material characterization and the erratic response of cemented soil layers, such as caliche in the Las Vegas valley, creates challenges for practicing engineers to reliably predict t
Sep 8, 2021
-
Constructing Tsunami Walls with Pressed-In Sheet and Pipe Pile Combi-WallsBy Takefumi Takuma, Tsunenobu Nozaki, Masashi Nagano
The city of Naruto in the southwestern part of Japan is situated at the mouth of the mighty Yoshino River. An approximately 1,000m-long levee/bulkhead along one of the river’s tributaries in the city
Sep 8, 2021
-
Session 16 "Deep Mixing Method IV"By Mary Ellen Bruce
Let me first address the issue of the wet grab samples. The wet grab samples that were attempted to take on the Central Artery were hindered by the fact that the way the mixing was being done was only
Feb 10, 2003
-
Rehabilitation of U.S. 70 Bridge over Lake Hamilton (de2c0766-552c-4812-a9ab-394a9bebc445)By Ryan P. Sullivan, G. Alan Klevens, Jian Huang
"BACKGROUNDLake Hamilton in Hot Springs, AR was created in 1932 when the Arkansas Power and Light Co. completed Carpenter Dam on the Ouachita River to generate electricity. Today, the 7,200-acre (2,91
Jan 1, 2007
-
Rehabilitation of U.S. 70 Bridge over Lake HamiltonBy Ryan P. Sullivan, G. Alan Klevens, Jian Huang
"BACKGROUNDLake Hamilton in Hot Springs, AR was created in 1932 when the Arkansas Power and Light Co. completed Carpenter Dam on the Ouachita River to generate electricity. Today, the 7,200-acre (2,91
Jan 1, 2007
-
Sustainable Products For Geotechnical WorksBy Marcus Daubner, Karsten Beckhaus, Florian Bauer
The construction industry can and needs to contribute to a more sustainable world. Accordingly, geotechnical works potentially have a significant share. In this context, Bauer understands “sustainable
May 1, 2022
-
Secant Pile Barrier Wall Overlap, Thickness, and Position at the U.S. Army Corps of Engineers Wolf Creek Dam, Jamestown, KYBy Bernard B. Vannoy, Howard W. Gault, Ramesh Bobba
"Treviicos-Soletanche Joint Venture (JV) and the US Army Corps of Engineers (USACE) have installed a 3800-foot long, 275-foot deep and minimum 2-foot wide secant pile barrier wall at Wolf Creek Dam in
Jan 1, 2015
-
Study Of Ground Settlement And Volume Loss Associated With Tbm Tunnelling By Analytical And Numerical MethodsBy Suresh Chikati, Gangadharan Santhanam
Twin tunnels were constructed to a length of 863m using TBM in one of the underground metro projects. The tunnels pass through complex geological conditions (soil, rock and mixed conditions). This pap
Sep 1, 2022
-
Applications of Nondestructive Testing Methods for Mass Foundation Blocks - Feasibility StudyBy Hamed Layssi, Farid Moradi, Thomas Tingson
This paper describes the feasibility and pilot study of of using existing non-destructive testing solutions for evaluating structural integrity and mechanical performance of mass concrete foundations.
Sep 8, 2021
-
Alternative Design Approach for Drag Load and Downdrag of Deep Foundations within the LRFD FrameworkBy Timothy C. Siegel, Derrick Dasenbrock, Rich Lamb, Paul J. Axtell
"The axial resistance provided by deep foundations may be divided into two components: side resistance and tip resistance. The direction that the side resistance acts depends on the relative movement
Jan 1, 2015
-
Behavior of a Piled Raft in Dry Cohesionless Soil Subjected to Lateral LoadingBy Srijit Bandyopadhyay, Aniruddha Sengupta, G. R. Reddy, Raj Banerjee
The objective of the present endeavor is to compare the performance of a pile raft system in foundation sand subjected to lateral loads. To study the behavior of pile raft system in sand a laboratory
Jan 1, 2015
-
Execution Example of the Expanded Dry Jet Mixing (EX-DJM) MethodBy Kiyotaka Ohno, Nobushige Yasuoka, Yosuke Hioki
"The diameter of improved columns adopted by the original DJM Method had been 1000 mm, however, in order to comply with the social need for construction cost reduction, the Expanded Dry Jet Mixing (EX
Jan 1, 2015
-
Deep Excavation By Controlled Rock Blasting Considering Ground Condition And Nearby Structures In Ug Metro Station – A Case StudyBy P. K. Ray, Sudip Kumar Koley, Sainath M. Reddy, Devulapalli L. S Rasagna
Bangalore Metro Rail Project- phase II is one of the technological challenging project, particularly construction of underground metro rail system. The Bengaluru city is very congested area and connec
Sep 1, 2022
-
Stability Analysis Of A Rubble Mound Breakwater Resting On The Weak Seabed By 2D Finite Element ModellingBy Vijaya R, Boominathan A
The design of a rubble mound breakwater resting on a problematic seabed is quite challenging and expensive. In the present study, stage-wise construction of a typical section of the breakwater for a p
Sep 1, 2022
-
Holistic Thermal Assessment And Control Of Ground Freezing For A New Underground StationBy Christian Leble, Dr. -Ing. Jakob Vogelsang, Dr. -Ing. Oksana Solt, Dipl. -Ing. Joachim Meier, Dr. -Ing. Wolfgang Orth
In the course of closing the gap between the Brandenburg Gate and Alexanderplatz, the Museum Island station was built by Implenia Construction GmbH. The tunneling for the platform hall took place on a