Water Tightness Of Diaphragm Walls

- Organization:
- Deep Foundations Institute
- Pages:
- 7
- File Size:
- 513 KB
- Publication Date:
- Jan 1, 2006
Abstract
For the realisation of the underground railway line RandstadRail in the city area of Rotterdam a bored tunnel is under construction. Diaphragm walls up to a depth of about 40 m were used to construct the building pits for the start shaft, the Blijdorp Station and the end shaft. The water tightness of the diaphragm walls was determined by leakage tests that were executed after the construction of the walls, but prior to the excavation of the building pits. The tests showed satisfactory results with a hydraulic resistance of the diaphragm walls of at least 500 days. To determine the water tightness of diaphragm walls it is recommended to follow the specific procedure as described in this paper.