Ventilation Planning For The El Mochito Mine

- Organization:
- Society for Mining, Metallurgy & Exploration
- Pages:
- 7
- File Size:
- 524 KB
- Publication Date:
- Jan 1, 1993
Abstract
Recent work to upgrade the ventilation system for the el Mochito lead/zinc mine in central Honduras is discussed. Network modeling and underground measurements were used to evaluate cost-effective alternatives for achieving satisfactory ventilation in a complex and expanding underground operation. Both interim and long-term solutions were implemented to make mining possible under difficult conditions. INTRODUCTION Mining operations at the el Mochito Mine, located in the central highlands of Honduras, Central America, have been virtually continuous since the opening of the mine in 1948. Initially a high-grade silver mine, the mine has expanded along a westward trend of pipe-like orebodies to a distance of roughly one mile from two centrally located shafts. Production of the relatively large San Juan orebody at the western most extension of the mine (Paddock, 1981) led to the introduction of diesel-powered equipment; however, the ventilation infrastructure was insufficient to meet the needs of mechanized mining. A succession of owners/operators in the 1980s allowed the existing ventilation infrastructure to decay to the point that ventilation in the production areas of the mine was very poor. Environmental conditions in some working areas were not conducive to efficient ore extraction because of high dry bulb temperature, high humidity, and diesel emissions. Upon acquiring the mine in 1990, Breakwater Resources of Tucson, Arizona began an aggressive program to refurbish the mine infrastructure to complete extraction of the San Juan orebody and to allow the extension of the mine another 2500 ft to the west for extraction of the Nacional orebody. The program included increasing the capacity of the main ventilation system. This article presents a case history of the process of upgrading the ventilation system in a mine where extensive old workings cause large air leakage. This process has been one of selecting solutions to difficult technical problems that are compatible with the existing mine infrastructure and economic constraints. The initial ventilation system is described in the background section, along with ventilation projections for the mine expansion. Field characterization of the ventilation system for design verification and fan specification is then discussed. The paper describes a series of interim changes to the system to improve ventilation pending completion of new ventilation boreholes. In addition, the temperature/ heat problems in the mine are described. BACKGROUND Initial Condition of Ventilation System The ventilation system is illustrated in Figure 1, which shows the extent of mining with the main ventilation paths superimposed. Early mining around the two shafts opened up vertical connections (stopes and raises) over the entire 2420 ft (737.6 m) of vertical extent, and mining progressed to the west primarily using compressed air and electric-powered equipment. Since ventilation was not a complex problem in the original mining system, the stopes and interconnecting raises were not sealed. The San Juan orebody was much larger than the silver ore zones mined previously, being primarily zinc and other base metals. Its geometry, size, and grade allowed the use of vertical crater retreat (VCR) stoping with diesel mucking and haulage equipment. Its depth, along with the existence of warm groundwater, resulted in a mine climate problem on the lower levels. To establish a complete ventilation circuit, two vertical boreholes (Bonanza Nos. 1 and 2) had been drilled by previous owners from the surface in the vicinity of the San Juan orebody. The system design called for air to be drawn down the intake shafts, across the lower mine levels to the San Juan workings, then up through the San Juan ramps and ore passes to these two exhaust boreholes (see Figure 1). In practice, however, only the Bonanza No. 1 borehole was drawing air through the desired path. Leakage across the old upper levels from the intake shafts, the Caliche tunnel, and from intervening abandoned stopes and raises supplied most of the air flowing to the base of the Bonanza No. 2 borehole. In effect, there were two ventilation circuits in semi-parallel through the mine, of which only one was delivering appreciable air to the San Juan workings.
Citation
APA:
(1993) Ventilation Planning For The El Mochito MineMLA: Ventilation Planning For The El Mochito Mine. Society for Mining, Metallurgy & Exploration, 1993.